02835Modular Block Mse Retaining Wall

UT · 2026 Standard Specifications✓ Full text on BuildSpecRev. September 16, 2021Book pages 698–703 Save this section

Ask about Section 02835

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

MODULAR BLOCK MSE RETAINING WALL

PART 1 GENERAL

1.1SECTION INCLUDES

A.Modular block Mechanically Stabilized Earth (MSE) retaining wall using

metal or geogrid soil reinforcement.

1.2RELATED SECTIONS

A.Section 02317: Structural Excavation and Backfill
B.Section 02832: MSE Backfill
C.Section 03055: Portland Cement Concrete
D.Section 03392: Penetrating Concrete Sealer
E.Section 09982: Anti-Graffiti Concrete Coating

1.3REFERENCES

A.AASHTO M 111: Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel

Products

B.ASTM A 641: Zinc-Coated (Galvanized) Carbon Steel Wire
C.ASTM A 1064: Carbon-Steel Wire and Welded Wire Reinforcement, Plain

and Deformed, for Concrete

D.ASTM C 1372: Dry-Cast Segmental Retaining Wall Units
E.ASTM D 5262: Evaluating the Unconfined Tension Creep and Creep

Rupture Behavior of Geosynthetics

F.ASTM D 6637: Determining Tensile Properties of Geogrids by the Single

or Multi-rib Tensile Method

G.UDOT Quality Management Plan

Modular Block MSE Retaining Wall

1.4DEFINITIONS Not Used

1.5SUBMITTALS Not Used

PART 2 PRODUCTS

2.1MATERIALS

A.Concrete
1.Dry Cast Concrete
a.Meet specified 28-day minimum compressive strength
2.Leveling Pad
a.Class B according to Section 03055.
B.Modular Block Fill
1.Free-draining crushed stone, 3/8 to 3/4 inch with no more than 5

percent passing the No. 200 sieve.

2.Meet electrochemical properties according to Section 02832.
C.Soil Reinforcement
1.Metal reinforcing elements
a.Welded Wire and Grid

1) Refer to ASTM A 1064.

b.Galvanize according to AASHTO M 111 or ASTM A 641 with

a coating thickness of at least 3.4 mils.

2.Geogrid reinforcing elements
a.Use geogrid consisting of a regular grid network of integrally

connected, discontinuous, select high-density polyethylene or polypropylene resin polymer or polyester tensile elements 1) Aperture geometry sufficient to permit significant mechanical interlock with the surrounding soil and rock. 2) Geogrid structure to be dimensionally stable and be able to retain its geometry under manufacture, transport, and installation.

b.Meet creep rupture test for 75-year service life according to

ASTM D 5262.

c.Meet the ultimate tensile strength from wide-width tests

based on minimum average roll values, according to ASTM D 6637. 1) Utilize geogrid reinforcement reduction factors as appropriate for the project.

Modular Block MSE Retaining Wall

D.Loop Embeds
1.As provided by the Wall Company.
2.Galvanize according to AASHTO M 111 with a coating thickness of

at least 3.4 mils.

E.Connecting Pins
1.Fiberglass Connecting Pins
a.½ inch diameter having a minimum flexural strength of 128

ksi and short beam shear of 6.5 ksi.

2.Steel Connecting Pins
a.Meet Wall Company’s requirements
b.Galvanized with a coating thickness of at least 3.4 mils.
F.Fasteners
1.Fasteners to wingwalls and abutment wall, if required, to be

provided by the selected Wall Company.

G.Filter Fabric
1.Use type and grade recommended by the Wall Company.

H Cap Block Adhesive

1.Use a medium-viscosity synthetic elastomeric polymer adhesive as

recommended by the Wall Company.

I.MSE Backfill
1.Refer to Section 02832.
J.MSE Free Draining Backfill
1.Refer to Section 02832.
K.Facing Treatment Material
1.Refer to Section 03392
2.Refer to Section 09982

2.2MODULAR BLOCKS AND CAP BLOCKS

A.Use a Department prequalified supplier of precast concrete products

according to the UDOT Quality Management Plan 505: Precast/ Prestressed Concrete Structures.

B.Meet the following requirements for drycast concrete modular blocks and

cap blocks:

1.Have a 28-day minimum compressive strength of 4,000 psi.

Modular Block MSE Retaining Wall

2.Conform to ASTM C 1372, except as follows:
a.Comply with the freeze-thaw durability requirements.
b.Comply with the following for each lot of blocks not tested for

freeze-thaw durability. 1) Have a water absorption no greater than one percent above the water absorption content of the blocks successfully tested for freeze-thaw durability.

C.Provide blocks having angled sides capable of producing concave and

convex alignment curves with a radius no less than 4 ft.

D.Finish and Appearance
1.Refer to ASTM C 1372.

PART 3 EXECUTION

3.1GENERAL

A.Haul, store, and ship wall materials in a manner that minimizes the

potential of producing defects.

1.Store soil reinforcement products as recommended by the Wall

Company.

2.Inspect soil reinforcement and attachment devices to verify they are

true to size and free from defects that may impair their strength and durability.

3.Keep the soil reinforcement and connections free of contaminants.
B.Construct the retaining wall system according to the authorized retaining

wall drawings, and the Wall Company’s construction manual and recommendations.

1.Apply the stricter of the two requirements where the Department’s

and the Wall Company’s requirements differ.

3.2EXCAVATION AND FOUNDATION PREPARATION

A.Excavate and prepare foundation to the lines and grades shown, or as

directed by the Engineer.

1.Refer to Section 02317.
2.Make the width of excavation equal to or greater than the length of

soil reinforcement.

3.Compact the foundation before the wall construction using at least

three passes of a lightweight, steel, smooth-drum vibratory roller, or as determined by the Engineer.

Modular Block MSE Retaining Wall

4.Over-excavate unsuitable foundation soils and replace with MSE

Backfill, or with other suitable material as directed by the Engineer.

3.3LEVELING PAD

A.Place the cast-in-place concrete leveling pad upon the foundation.
1.Place leveling pad to a thickness of at least 6 inch.
2.Provide a level surface so that the modular blocks are in complete

contact with the leveling pad.

B.Do not place modular blocks until leveling pad has been placed for at least

12 hours.

3.4WALL CONSTRUCTION

A.Construct the wall as follows:
1.Place the first course of modular blocks on the leveling pad.
a.Check the modular blocks for levelness and alignment.
b.The first course is the most important to verify accurate and

acceptable results.

c.Verify modular blocks are in full contact with the leveling

pad.

2.Install connecting devices in modular blocks as required by the Wall

Company.

a.Extend connecting pins into adjoining courses at least 1 inch

where used.

3.Pull each block forward (away from the backfill) against the

connecting pins in the previous course

4.Fill modular block voids with modular block fill when required.
a.Tamp the modular block fill in each course before

proceeding to the next course.

5.Backfill each course of blocks and compact the entire lift before

placing the next course of blocks.

6.Repeat the procedure for each additional course.
B.Construct wall facing to the following tolerances.
1.Horizontal alignment
a.Not to exceed 0.7 percent (for example, 0.75 inch in 10 ft).
2.Vertical alignment (measured from the points of maximum and

minimum offset at a bulge or depression)

a.Not to exceed 0.7 percent (measurements taken at the

bottom, center and top of bulge or depression)

Modular Block MSE Retaining Wall

3.Plumbness from top of wall to bottom of wall (measured from the

design batter)

a.Positive (into the retained mass)

1) Not to exceed 0.7 percent (for example, 1.7 inch in 20 ft of wall height).

b.Negative (away from the retained mass)

1) Not to exceed 0.4 percent (for example, 0.96 inch in 20 ft of wall height).

4.Facing Block Levelness
a.Not to exceed 0.5 percent (for example, 1.2 inch in 20 ft)
5.Joints
a.Limit the horizontal offset in any block joint during

construction to no more than 0.25 inch.

b.Limit the width of vertical joints to no more than 0.50 inch.
C.Metal Soil Reinforcement Installation
1.Place the soil reinforcement on compacted backfill.
2.Connect soil reinforcement to the blocks as required by Wall

Company.

3.Place soil reinforcement normal to the face of the wall in plan view.
a.Provide at least 2 inch clear distance between soil

reinforcement and piles or other metallic obstructions.

4.Provide at least 3 inch vertical separation between soil

reinforcement when overlapping.

D.Geogrid Soil Reinforcement Installation
1.Verify the correct orientation (roll direction) of the geogrid.
2.Place the geogrid on compacted backfill.
3.Connect geogrid to the concrete wall blocks as required by Wall

Company.

4.Pull the geogrid taut to eliminate loose folds and remove slack in

the geogrid at the block connections, pretension the geogrid, and then stake or otherwise secure the back edge of the geogrid before and during backfill and compaction.

5.Follow the Wall Company's overlap requirements for uniaxial and

biaxial geogrids.

6.Provide at least 3 inch vertical separation between soil

reinforcement when overlapping.

Modular Block MSE Retaining Wall

3.5CAP BLOCK INSTALLATION

A.Set cap blocks over top row of modular blocks with proper alignment and

uniform set-back orientation.

B.Provide a permanent connection between the cap blocks and the top

course of the modular blocks using cap block adhesive.

END OF SECTION

Modular Block MSE Retaining Wall

Get an email when 02835 changes

Utah revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Utah Standard Specifications for Road and Bridge Construction, 2026 Edition. Pages 698–703 of 1,331. View official source ↗

Ask about this section

Scoped to Utah Standard Specifications, Section 02835 — Modular Block Mse Retaining Wall. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.