6-155 SECTIO N 633 – CRITICA L PATH METHOD SCHEDULE
633.0 1 DESCRIPTION . This work shall consist of developing and furnishing a critical path method
(CPM ) schedule, including narratives, updates, and revisions for the duration of the Contract. If item 633.10 00 is included in the Contract, t he provisions of this section shall supersede those of Subsection 108.03(a) .
633.0 2 Submissions .
633.0 3 BASELIN E SCHEDULE . The CPM schedule submittal shall be received by the Engineer a
minimum of 7 calendar day s prior to the preconstruction meeting . The Engineer and Contractor may review the schedule at the preconstruction meeting . Any requested information and a revised schedule shall be submitted within 7 calendar day s after receiving the Engineer’s request. 6-157 The Engineer shall be allowed 21 calendar day s to review the schedule and provide a response . The Engineer will review the schedule by assessing the schedule’s compliance with these provisions and conformance with the Contract requirements. By accepting the schedule, the Engineer does not modify the Contract in any way . The baseline schedule shall be accepted before the Notic e to Proceed . The accepted schedule will be used as the baseline schedule for the remainder of the project . The schedule shall define and sequence activities to accurately describe the project and to meet Contract requirements for scope of work , phasing, a ccommodations for traffic , and interim and Contract completion dates . The schedule shall begin with the date of Contract execution.
633.0 4 SCHEDUL E UPDATES . The schedule shall be updated during active construction at the end of
every other biweek ly estimate period (update period) and when directed by the Engineer . Projects with short duration closures are of particular importance as the project float will be l imited . The Contractor shall promptly inform the Engineer of any schedule delays or changes that occur during these periods. The Engineer shall be allowed 10 calendar day s to review the update for compliance with these provisions and provide a response . The following items shall be included with each update:
633.0 5 REVISIONS . Schedule revisions shall be submitted no more than 10 calendar day s after the
occurrence of any of the following:
633.0 6 FLOAT . Any float in the schedule is to be credited to the project only.
633.0 7 FAILUR E TO SUBMI T SCHEDULE . Failure to submit a schedule (i.e. original baseline
schedule, required updates, revisions, and when requested by the Engineer) in accordance with these provisions may be grounds for suspension of partial payments, as identified in Subsection 109.08 , until a satisfactory schedule meeting the requirements of these provisions is received by the Engineer.
633.0 8 METHO D OF MEASUREMENT . The quantity of CPM Schedule to be measured for payment
will be the number of each CPM Schedule (i.e. original baseline schedule, required updates, revisions, and when requested by the Engineer), accepted by the Engineer through the duration of the Contr act.
633.0 9 BASIS OF PAYMENT . The accepted quantity of CPM Schedule will be paid for at the Contract
unit price for each . Payment will be full compensation for preparing and submitting a schedule as specified, and for furnishing all labor, tools, equipment , and incidentals necessary to complete the work . Payment will be made under: Pay Item Pay Unit
633.10 00 CPM Schedule ................................ ................................ .......................... Each
6-159 SECTIO N 634 – EMPLOYE E TRAINEESHIP
634.0 1 DESCRIPTION . This work shall consist of providing on -the-job training for qualified employees
in accordance with applicable approved training programs.
634.0 2 GENERAL REQUIREMENTS . The training requirements specified herein supersede FHWA -
1273, Part II, Subparagraph 6b and im plement 23 U.S.C . § 140(a) . The Contractor shall provide on -the-job training aimed at developing full journeyman qualifications in the type of trade, craft, or job classification involved. The training program shall be carried out in accordance with a train ing schedule and curriculum devised to give the employee an understanding of the trade, craft, or skill together with instructions in safety operations and performance of the actual specialty covering all aspects of the work involved . The training program shall be one approved by the Agency and the U.S. Department of Transportation. The required number of employee traineeship hours to be provided by the Contractor is shown in the Contract . If a Contractor subcontracts a portion of the work , the Contractor s hall determine how many, if any, of the trainees are to be trained by the subcontractor . However, the Contractor shall retain the primary responsibility for meeting the training requirements specified herein.
634.0 3 PROCEDURE . The procedures followed in carrying out the training shall be consistent with the
approved training program for the particular trade, craft, or skill and the trainee shall be employed insofar as practical in a useful and constructive manner assisting in the work on the project until such time as the Contractor deems the trainee as being qualified to operate independently in the field in which the trainee has been trained. The Contractor shall then give the trainee a certificate of satisfactory completion of apprenticeship training specifying the field of accomplishment. The Contractor shall maintain payroll records and training records in a manner acceptable to the Engineer as to provide all the information necessary to properly and adequately support prog ress and final payment for this item, as well as to show the status of training accomplishment. It is normally expected that a trainee will begin training on the project as soon as feasible after start of work utilizing the skill involved, and remain on th e project as long as training opportunities exist in the work classification or until the training program has been completed. It is not required that all trainees be on board for the entire length of the Contract . The Contractor will have fulfilled the re quirements of this item if they have provided acceptable training to the number of trainees specified . The number trained shall be determined based on the total number enrolled on the project for a significant period.