Division 600 — Incidental Construction

681Asbestos Abatement

WV · 2023 Standard Specifications✓ Full text on BuildSpecBook pages 765–775 Save this section

Ask about Section 681

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

681.1-GENERAL: 681.1.1-Description of Work: The work to be performed under this section of the specifications comprises the furnishing of all labor, materials and equipment for completion of all work as shown elsewhere within this Special Provision and/or the Contract Plans. This work includes handling and removal of asbestos containing materials, and the incidental procedures, materials and equipment required to protect workers and/or occupants of the structure and adjacent areas from contact with airborne asbestos containing materials. All asbestos materials shall be disposed of in a landfill approved by the West Virginia Department of Environmental Protection, Division of Water and Waste Management, Solid Waste. This work is to be performed by a Certified/West Virginian Licensed Asbestos Abatement Contractor. 681.1.2-Definitions: Except as specifically defined otherwise, the following definitions apply generally to the work of this section. Abatement: Procedures to control fiber release from asbestos containing materials, including removal of asbestos containing material (ACM) as per this specification. Air Monitoring: The process of measuring the fiber content of a specific volume of air in a stated period. Amended Water: Water to which a surfactant has been added. Asbestos: Fibrous silicates with a crystalline structure, including chrysotile, amosite, crocidolite, tremolite, anthophyllite and actinolite. Asbestos Abatement Contractor: Certified/WV Licensed Asbestos Contractor. Asbestos Fibers : Asbestos fibers having an aspect ratio of 3:1 and longer than five (5) micrometers. Authorized Visitor : WVDOH personnel, Authorized Agent of the WVDOH or a representative of any regulatory agency having jurisdiction over the project. Class I Project : A Class I project as defined in OSHA as being abatement of asbestos containing insulating, surfacing and/or thermal surfacing materials. Class II Project : A Class II project as defined in OSHA as being th e abatement of any asbestos containing material other than insulating, surfacing and/or thermal surfacing materials. Clean Room: An uncontaminated area or room, which is part of the worker decontamination enclosure system, with provision for storage of w orkers street clothes and protective equipment. 745 Curtained Doorway: A device to allow ingress or egress from one room or area to another while permitting minimal air movement between the rooms or areas. This curtained doorway is typically constructed by placing two (2) overlapping sheets of plastic over an existing or temporarily framed doorway and securing each along the top of the doorway. Secure the vertical edge of one (1) sheet along the side of the doorway and secure the vertical edge of the other sheet along the opposite side of the doorway. Decontamination Enclosure System: A series of connected rooms, with curtained doorways between adjacent rooms, for the decontamination of the workers, materials or equipment. Equipment Decontamination Enclosure System: A decontamination enclosure system for materials and equipment, typically consisting of a designated area of the work area, a washroom, a holding area or an uncontaminated area. Equipment Room: A contaminated area or room, which is part of the worker decontamination enclosure system, with provisions for storage of contaminated clothing and equipment. HEPA Filter: A filter capable of trapping and retaining at least 99.97% of all mono-dispersed particles of 0.3 micrometers in diameter. High Efficiency Particulate Air (HEPA) Vacuum Equipment: HEPA filtered vacuuming equipment. Holding Area : A chamber between the washroom and an uncontaminated area in the equipment decontamination enclosure system. Negative Pressure : A local exhaust sy stem capable of maintaining a minimum pressure differential of minus 0.02 inches of water column relative to adjacent unsealed areas. Removal: All herein specified procedures necessary to strip asbestos containing materials from the designated areas and to dispose of these materials at an acceptable site. Shower Room : A room between the clean room and the equipment room in the work decontamination enclosure system, with hot and cold running water and suitably arranged for complete showering during decontamination. Surfactant: A chemical wetting agent added to water to improve penetration, thus reducing the quantity of water required for a given operation or area. Washroom: A room between the work area and the holding area in the equipment decontamination enclosure system to be used for personal decontamination. Worker Decontamination Enclosure System : A decontamination enclosure system for workers, typically consisting of a clean room, a shower room and an equipment room. Wet Cleaning: The process of eliminating asbestos contamination from building surfaces and objects by using cloths, mops or other cleaning tools which have been dampened with amended water and afterwards disposing of these cleaning tools as asbestos contaminated waste. 746 681.1.3-Applicable Regulation, Standards and Guidance Regulations: The Contractor shall comply with the following regulations. If conflicts occur between these regulations and specifications, the more stringent requirements shall apply.

A.Title 29, Code of Federal Regulations, 1910.134 (Respiratory Protection ), 1910.145

(Specifications for Accident Prevention Signs and Tags), Occupational Safety and Health Administration (OSHA), U.S. Department of Labor.

B.Title 29, Code of Federal Regulations, Sections 1926.1101, Occupational Safety and

Health Administration (OSHA), U.S. Department of Labor.

C.Title 40, Code of Federal Regulations, Part 61, Subpart M, National Emission

Standards for Hazardous Air Pollutants, U.S. Environmental Protection Agency (EPA),

(NESHAPS)Asbestos Regulations.
D.West Virginia Legislative Rule, 64 CSR 63 Department of Health, Asbestos Abatement

Licensing Rule.

E.All regulations related to environmental protection and pollution control relating to

asbestos removal and disposition. 681.1.3.1-Guidance Documents: The following documents will supply guidance for the project and shall be utilized.

1.A Guidance for Controlling Asbestos Containing Material in Buildings: EPA

Publication (560/5-85-004).

2.EPA Adequately Wet Guidance Document

681.1.4-Submittals, Notices and Documentation: Ten (10) w orking days prior to commencement of work (regardless of the presence of ACM), the Contractor shall notify in writing, with a copy to the Division, the following agencies: Asbestos NESHAP Coordinator (3WC32) US EPA Region III 1650 Arch Street Philadelphia, PA 19103 West Virginia Department of West Virginia Department of Environmental Protection Health & Human Resources Division of Water & Waste Office of Environmental Health Management, Solid Waste Services 601 57th StreetSE Radiation, Toxics and Indoor Air Charleston, West Division Capitol and Washington Virginia 25304-2345 Streets One Davis Square, Suite 200 ATTN: Asbestos Coordinator Charleston, WV 25301-1798 West Virginia Department of Environmental Protection Division of Air Quality 601 57th StreetSE Charleston, West Virginia 25304-2345 ATTN: Asbestos Coordinator 747 The Contractor shall maintain copies of all required notifications and of all the following documents at the job site:

1.Copies of air monitoring.
2.Copies of negative air pressure readings taken once per shift (on Class I projects).
3.Work schedule and updated progress chart depicting all phases of the work and

completion dates.

4.A daily log of personnel having entered the work area.

681.1.5-Pre-Abatement Meeting: The Contractor and/or the Asbestos Abatement Contractor shall meet with the Engineer prior to beginning work to discuss in detail the asbestos plan, including work procedures and safety precautions. The plan must be approved, in detail, by the Engineer, prior to the start of any abatement. The Contractor shall also submit to the Engineer the following information:

1.An Abatement Plan that complies with 64 CSR 63 -8 which includes the location of

regulated areas, decontamination system and layout, sequencing of asbestos related work, disposal plan, air monitoring plan, description of personal protective equipment to be used, and detailed description of all abatement methods to be used. A WV Licensed Asbestos Project Designer must sign this plan.

2.Copies of Training Certificates, a Photo I.D. and WV Licenses for each employee that

will be involved with this project. 681.1.6-Personnel Protection: The Asbestos Abatement Contractor shall provide for all workers, supervisors, inspectors and monitoring technicians, disposable paper-type protective overalls plus head and shoe covers as required by OSHA regulations. Respiratory equipment selection shall be based on OSHA requirement in 1926.1101. All persons entering a regulated area shall w ear an approved respirator and protective clothing. Eye protection and hard hats shall be available as required. The Asbestos Abatement Contractor shall provide a minimum of one set of personal protective equipment for use by a Division authorized visitor(s). 681.1.7-Security: The Asbestos Abatement Contractor shall provide and post all required warning signs in accordance with OSHA regulations. The Contractor is responsible for securing the regulated area from unauthorized personnel. 681.1.8-Air Monitoring and Testing: All exposure air monitoring shall be conducted in accordance with 1926.1101 of OSHA Regulations. The analysis of all air samples shall be conducted by a certified and licensed independent testing laboratory that is not owned or financially related to the Asbestos Abatement Contractor. Air sample results shall be posted within 24 hours of the assessment. For all Class I projects, the Asbestos Abatement Contractor shall be responsible for hiring a Testing Laboratory to conduct perimeter samples outside the regulated area. The Contractor shall send to the Engineer the results of all air monitoring tests conducted by the Asbestos Abatement Contractors testing laboratory. No Class I abatement shall be performed without the air-monitoring technician being notified. 748 681.1.9-Asbestos Contamination Limits: If activities create a visible escape of dust from the work area, the Asbestos Abatement Contractor shall immediately cease abatement work and further seal the work area and apply additional wetting agent. If air test results from inside the work area or in the breathing zone of one of the employees exceeds the OSHA (TWA) Permissible limit, all workers inside the work area will be required to wear powered air purifying respirators until subsequent air tests show the asbestos levels have dropped below the permissible limit. At this time negative pressure half mask respirators may again be used. If testing outside the work area indicates that the levels of asbestos exc eed 0.01 fibers per cubic centimeter or above the background levels, then abatement work shall cease. The enclosure will be further sealed and additional wetting agents applied. Work shall resume only upon approval of the Engineer. 681.1.10-Contractor’s Certification: The Contractor shall provide written certification to the Engineer that the abatement as shown in the contract plans has been completed according to OSHA, EPA and West Virginia 64 CSR 63. 681.2-EXECUTION: 681.2.1-General: Work Procedures: Perform asbestos related work in accordance with 29 CFR 1910.1001 and as specified within this provision. Use wet removal procedures. Personnel shall wear and utilize protective clothing and equipment as specified herein. Eating, smoking or drinking shall not be permitted in the asbestos work area. Personnel other than those engaged in the removal and demolition of asbestos shall not be exposed at any time to airborne concentrations of asbestos unlessal l the personnel protection provisions of this specification are complied with. 681.2.2-Preparation of Work Area: Establish a regulated area as required by 1926.1101. All Class I and Class II asbestos work shall be conducted in a properly demarcated re gulated area. Critical barriers shall be placed over all openings into the regulated area for all Class I and Class II projects. These critical barriers shall consist of one or more layers of plastic sheeting, portable partitions, temporary wood partiti ons or other enclosures and shall be used to prevent the escape of asbestos fibers. Shut down and isolate heating, cooling and ventilation air systems in affected areas of the structure to prevent contamination and fiber dispersal to other areas. All ai r supply and return vents within the work areas shall be sealed with duct tape and two layers of plastic sheeting. In no case shall the structure ventilation system be used as a part of the local exhaust system for the asbestos work area, nor shall any fa ns or room ventilators be in operation during abatement work. Remove all heating, ventilation and air conditioning system filters located in the work areas, spray with amended water and pack impermeable clear plastic bags (6 -mil thickness minimum) with proper labeling for disposal in the approved waste site. Pre-clean the regulated area prior to installing plastic sheeting over walls, floors and other stationary items is required if visible contamination exists. This cleaning shall be performed using HEPA filtered vacuum equipment or wet cleaning methods as appropriate. Methods that raise dust, such as dry sweeping or vacuuming with equipment not equipped with HEPA filters is prohibited. For Class I work, cover floor and wall surfaces with plastic sheeting sealed with duct tape. Cover floors with two (2) layers of 6 -mil plastic sheeting, extending the plastic twelve (12) 749 inches up the walls. Then cover the walls with one layer of 6 mil plastic sheeting to the floor level, overlapping the floor covering a minimum of twelve (12) inches and seal with duct tape. When tape is insufficient to support plastic sheeting or where existing finishes may be damaged by the application of plastic sheeting, the Asbestos Abatement Contractor shall construct temporary wood frame supports for the plastic sheeting. All remaining equipment and other items that will not be removed are to be covered with 6 -mil plastic sheeting and sealed with duct tape. Emergency and fire exits from the work areas are to be maintained. 681.2.3-Local Exhaust System (Negative Pressure): On Class I work the Asbestos Abatement Contractor must provide a local exhaust system in compliance with 29 CFR

1926.1101. Each exhaust unit must be equipped with pre -filters and a HE PA filter through

which air from the work area is drawn and exhausted. The exhaust unit(s) shall be located opposite to and at the farthest side from the make-up air entrance to the work area, so the make- up air enters the work area through the decontamin ation facility and travels across the work area. The structure ventilation system shall not be used as any part of the local exhaust system for the asbestos control area, nor shall any fans or room ventilators be in operation during the abatement work. All supply and return air openings are to be closed and sealed. Position the exhaust unit inside the work area and exhaust through the windows, door or other openings to the exterior of the structure through the use of flexible duct connections sealing around the ducts with plastic and tape. Exhaust into the construction area will be permitted only upon approval of the Engineer. Local exhaust equipment shall be supplied in a sufficient quantity to produce a minimum of four (4) air changes per hour in ea ch removal area. A spare unit shall be kept on site at all times to ensure continuous negative air operations. The exhaust units shall be started prior to beginning removal operations and shall run continuously to maintain a constant negative pressure. Filters are to be replaced as required to maintain the efficiency of the system. The Contractor shall provide a viewing window of 9 square feet showing the enclosed work area. 681.2.4-Decontamination Enclosure Systems: The Contractor shall provide pe rsonal hygiene facilities in compliance with 1926.1101. All Class I projects involving quantities of ACM greater than 100 square feet require a decontamination system that includes a clean room, shower room and equipment room. (See Figure 1-Typical Decontamination Enclosure System) Access between any two (2) rooms within the decontaminated enclosure systems shall be through a curtained doorway. Both the work decontamination system and the equipment decontamination enclosure system shall contain ligh ted emergency exit signs on the doors of the enclosures. A worker decontamination enclosure system is to be constructed contiguous to the work area and consist of three (3) totally enclosed chambers. These chambers shall be:

a.Clean Room: In this area a p erson can dress in clean disposable coveralls and store

clean respiratory protection equipment. No asbestos contaminated items shall enter this room.

b.Shower Room: This is a separate area used for showering upon leaving the work area.

This is a contaminated area.

c.Equipment Room: This is a change and storage area for people and equipment. This

is a contaminated area. 750 The equipment room shall have a curtained doorway to the work area. The shower room shall contain at least one (1) shower for every 10 workers and be equipped with hot and cold water with temperature controls. Careful attention shall be paid to the shower enclosure to insure against leakage of any kind. A supply of soap and shampoo is to be on hand at all times in the shower room. Wastewater from the shower room shall pass through a 5 -micron HEPA hydraulic filter before being allowed to enter the structures sanitary sewer system. The equipment decontamination enclosure system for Class I projects shall consist of two

(2)totally enclosed chambers as follows:
a.A washroom used to remove contamination from bagged or wrapped ACM. Any

wastewater from this washroom must be filtered or contained and disposed of as contaminated material as noted previously.

b.A holding area with a curtained doorway to an uncontaminated area.

For Class II projects as well as Class I projects less 100 square feet, the contractor shall establish an equipment room consisting of a drop cloth adjacent to the regulated area. The area must be of sufficien t size to accommodate cleaning of equipment and removing personal protective equipment without spreading contamination beyond this area. Personal protective clothing shall be cleaned with a HEPA vacuum before it is removed. All barriers and plastic linings are to be effectively sealed and taped. Immediate repair of any damage or defects is to be completed upon discovery. A visual inspection of the enclosures is to be done at the beginning of each work shift. 681.2.5-Entry And Decontamination: All workers and visitors leaving the work area must follow the decontamination sequence. Contaminated respirators are to be worn into the shower and are not to be removed until they have been washed to remove any dust. Cartridges are to be removed and properly discarded. Respirators that have been thoroughly washed are to be stored in the clean room ready for reuse. Work Entry Sequence: All persons are to be logged in as they enter. Non -employees must sign the attached wavier before entering. The sequence for entry shall be as follows: For Class I projects, the worker enters the clean room and changes from street clothes into clean protective disposal clothing, including footwear, and don the appropriate respirator. A positive/negative pressure fit check is performed to insure proper fitting. When all required protective equipment has been donned, the worker proceeds into the work area. For Class II projects, employees shall don personal protective equipment prior to entering the regulated area. Work Exit Sequence: For Class I projects, the worker shall remove all gross contamination and debris from coveralls and footwear by wet wiping or HEPA vacuuming prior to entering the equipment room. The worker then proceeds to the equipment room. Al l clothing except for respiratory equipment is to be removed. Extra work clothing may be stored as contaminated materials in the equipment room. Disposable coveralls shall be placed in plastic bags for disposal with other contaminated material. The worker shall then proceed to the shower room and wash; removing the respirator last so as to prevent inhalation of fibers during decontamination. After showering, the worker enters the clean room and dresses in new coveralls (if returning to the work area) or street clothing (if leaving). 751 For Class II projects, the worker shall step onto the drop cloth and HEPA vacuum the protective clothing prior to its removal. The respirator shall be thoroughly cleaned after doffing. Filters in the respirators shall be removed when wet and shall be treated as contaminated waste. A new filter shall be placed in the respirator prior to reuse. There shall be no smoking, eating or drinking in the regulated area or the decontamination area. 681.2.6-Asbestos Removal: Asbestos removal techniques used by the Asbestos Abatement Contractor shall comply with OSHA, EPA and West Virginia regulations. Unless prior written approval is received from EPA and the Engineer, amended water shall be used to adequately wet all ACM removed or disturbed by the Asbestos Abatement Contractor. 681.2.6.1-Class I Projects: The following procedures shall be used on all Class I project:

a.The project shall be supervised by a competent person.
b.Critical barriers shall be installed over all openings to the regulated area (inside

projects only).

c.All persons in the regulated area shall be equipped with respiratory protection.
d.A negative pressure enclosure or glove bag shall be used
e.ACM shall not be dropped more than ten (10) feet.

681.2.6.2-Class II Projects: The following procedures shall be used on all Class II projects:

a.All persons in the regulated area shall be equipped with respiratory protection

and protective clothing.

b.The project shall be supervised by a competent person
c.Critical barriers shall be installed over all openings to the regulated area unless

a negative exposure assessment has been produced or the project is conducted outside.

d.Removal of asbestos containing flooring materials shall be conducted in

accordance with 1926.1101

e.Removal of asbestos containing roofing materials shall be conducted in

accordance with 1926.1101

f.Roofing ACM and cementitious asbestos containing siding and shingles or

transite panels shall not be dropped to the ground. These materials shall be immediately lowered to the ground via covered dust-tight chute, crane or hoist, or placed in an impervious waste bag or wrapped in plastic sheeting and lowered to the ground no later than the end of the work shift. 681.2.7-Site Insp ection: While performing work, the Asbestos Abatement Contractor may be subject to on -site inspections by a representative of the WVDOH, USEPA, WVDEP and/or WVDHHR, during the abatement process. If the work is found to be in violation of this specification, the Engineer will be requested to issue a stop work order to be in effect immediately and until the violation is resolved. Standby time required resolving the violation shall be at the Contractors expense. If at any time, the Engineer determines that work practices of the Contractor are violating pertinent regulations, endangering workers or not complying with these specifications; The 752 Engineer will immediately notify in writing the Asbestos Abatement Contractor's on -site representative that operations are to cease until corrective actions are taken. 681.2.8-Cleanup: Throughout the abatement project, maintain surfaces in the work area free of accumulations of asbestos fibers, dust and debris. All visible accumulations of asbestos material and de bris are to be removed by wet cleaning or HEPA vacuuming. Give special attention to restricting the spread of dust and debris. Prevent waste from being distributed over the general area. Wet-clean all surfaces in the work area. Remove only the plast ic sheets from floors and walls before work area is certified as asbestos free. Windows, doors and HVAC vents shall remain sealed and any HEPA filtered negative air pressure systems, air filtration and decontamination enclosure systems shall remain in service. Clean all surfaces in the work area and any other contaminated areas with water and/or with HEPA filtered vacuum equipment. After cleaning the work area, wait 24 hours to allow for settlement of dust, and again wet clean or clean with a HEPA filte red vacuum all surfaces in the work area. After completion of the second cleaning operation, a complete visual inspection of the work area to ensure that the work area is free of visible debris is to be performed. Sealed drums and all equipment used in the work area shall be included in the cleanup and shall be removed from work areas through the equipment decontamination enclosure system at the appropriate time in the cleaning sequence. When the final inspection determines that the area is free of accumulations of visible debris and a final air test shows that the concentration of asbestos fibers is less than 0.01 fibers per cc (or the predetermined baseline), the decontamination enclosures system shall be removed, and the area thoroughly cleaned with HEPA filtered vacuum equipment then windows, doors and vents can be unsealed and material from these areas and the equipment and shower rooms disposed of as contaminated waste. The Engineer is to be notified before the regulated area has been deemed an unrestricted entry area. 681.2.9-Disposal: Collect asbestos waste, scrap, debris, bags, containers, equipment and asbestos contaminated clothing which may produce air borne concentrations of asbestos fibers and place them in sealed, clear impermeable bags. Each bag shall be labeled according to OSHA, EPA and DOT requirements. Dispose of waste asbestos material in accordance with Environmental Protection Agency (EPA) and West Virginia reg ulations at an approved landfill. For temporary storage, the sealed impermeable clear bags may be stored in asbestos waste drums or skids. 681.3-METHOD OF MEASUREMENT: The quantity of work done will be on a lump sum basis. 681.4-BASIS OF PAYMENT: The quantities, determined as provided, will be paid for at the contract unit price for the items listed below. The prices and payment shall be full compensation for furnishing of material and performing all the work prescribed in a workmanlike and acceptable manner, including all tools, equipment, supplies and incidentals necessary to complete the work. All incidental work and materials for which no basis of payment is provided will be considered as completely covered by the prices bid for the items included in the Contract. 753 681.5-PAY ITEMS: ITEM DESCRIPTION UNIT 681001-* Asbestos Abatement, Class I Lump Sum 681002-* Asbestos Abatement, Class II Lump Sum * Sequence number 754

Get an email when 681 changes

West Virginia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Roads and Bridges, 2023 Edition. Pages 765–775 of 1,006. View official source ↗