717Compaction Control of Base Course Material

WV · 2023 Standard Specifications✓ Full text on BuildSpecBook pages 985–986 Save this section

Ask about Section 717

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

717.1-GENERAL: The Contractor shall notify the Engineer prior to construction of the test strips as set forth in MP 700.00.24. The Contractor shall perform quality control compaction tests and record the data on the forms as set forth in the Materials Procedures (MPs). The test data shall be available to the Engineer at the time of testing or as indicated in the Contractor's quality control plan. 717.2-TEST METHODS: Maximum density, quality control density and acceptance density for crushed aggregate base course and aggregate subbase shall be determined in accordance with MP 700.00.24. 717.3-DENSITY: The crushed aggregate base course and aggregate subbase shall be compacted to the target percentage of dry density of 95%. The maximum required dry density shall be determined in accordance with MP 700.00.24 Part I on a control test strip having a compacted thickness of six

(6)inches or less. The in -place dry density of each base course layer shall be determined in

accordance with MP 700.00.24 Part II. The maximum layer thickness, other than the test strip(s), shall not exceed twelve (12) inch or as specified in the project documents. The density of layers with thickness that differ from the thickness of the control test strip(s) shall be subject to the density requirements determined by the control test strip. 963

Get an email when 717 changes

West Virginia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Roads and Bridges, 2023 Edition. Pages 985–986 of 1,006. View official source ↗

Ask about this section

Scoped to West Virginia Standard Specifications for Roads & Bridges, Section 717 — Compaction Control of Base Course Material. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.