Do you need a permit?
Lincoln requires a permit for a retaining wall.
When a permit is not required
A retaining wall of 4 feet or less, sized from the lowest adjacent grade up to the wall's highest point, needs no building permit, provided nothing behind it adds load.
What Lincoln publishes for this permit
- 1 process step from application to final
- 1 published fee line from the city's fee schedule
- Checked against Lincoln's documents on September 15, 2026
Loading the full checklist…
Sources
- retaining wall — permit rules, retaining wall — fee schedule ↗verified September 2026
Other permits Lincoln publishes rules for
Listed because the city publishes a separate rule for each type — not because this project necessarily triggers one. Whether it does depends on your scope of work.
- Deck permit checklist
- Fence permit checklist
- Shed permit checklist
- Water heater permit checklist
- Re-roof permit checklist
- Electrical work permit checklist