Riverside, California Building Permit Cost Calculator
Estimates permit cost in Riverside from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○(R3) New SFD, 700 SF min & 7,000 SF max - charged as plan check fee and again as permit fee Flat fee $0.57 | $0.57 |
○(R1, R2) Multi-Family Dwelling, 3,000 SF min & 50,000 SF max - each Flat fee $0.30 | $0.30 |
○(R3) Home Remodel SFD, 100 SF min & 500 SF max - each Flat fee $0.92 | $0.92 |
○(R3) Addition + Alteration SFD, 200 SF min & 1,500 SF max - each Flat fee $0.88 | $0.88 |
○(B, M, I) Business, Mercantile, Institutional new commercial, 2,000 SF min & 20,000 SF max - each Flat fee $0.47 | $0.47 |
○Tenant Improvement, existing commercial, 1,500 SF min & 30,000 SF max - each Flat fee $0.39 | $0.39 |
○Permit issuance, each Flat fee $41.00 | $41.00 |
○Building plan check, per hour Flat fee $87.00 | $87.00 |
○Building inspection, per hour Flat fee $87.00 | $87.00 |
○Building reinspection, each Flat fee $98.00 | $98.00 |
Strong Motion Instrumentation Program (SMIP) fee, residential structures valuation x 0.00013 | see rule |
Strong Motion Instrumentation Program (SMIP) fee, commercial structures valuation x 0.00028 | see rule |
California Building Standards fee $1.00 per every $25,000 or portion thereof, in construction valuation | see rule |
General Plan Maintenance surcharge on all plan check and permit fees 10% | see rule |
Technology surcharge on all plan check and permit fees 4% | see rule |
Shell only · add-on 60% of building permit + plan check fee — select the permit fee line above to calculate | see rule |
Foundation only · add-on 25% of building permit + plan check fee — select the permit fee line above to calculate | see rule |
How this jurisdiction calculates the fee
Riverside prices new construction and major alteration per square foot by occupancy and use rather than from a construction valuation table, and the schedule publishes the same amount in both the plan check fee and the permit fee columns, so a project is charged both. Each rate carries a minimum and maximum project size and a project below the minimum is billed at the minimum - the schedule's own example notes that a 900 SF tenant improvement pays the same as a 1,500 SF one. A flat permit issuance fee applies per permit. Valuation still drives two state-related charges: the Strong Motion Instrumentation Program fee and the California Building Standards fee. All plan check and permit fees then carry a 10% General Plan Maintenance surcharge and a 4% Technology surcharge. Community Economic Development Department, Building and Safety fee schedule effective July 1, 2026.
Source: published fee schedule · Verified 11/4/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Decks, balconies, stairways 500 SF or less Flat fee $174.00 | $174.00 |
○Decks, balconies, stairways, for each additional 500 SF Flat fee $75.00 | $75.00 |
○Residential lattice patio cover 400 SF or less Flat fee $83.00 | $83.00 |
○Residential patio cover 400 SF or less Flat fee $107.50 | $107.50 |
○Permit issuance, each Flat fee $41.00 | $41.00 |
General Plan Maintenance surcharge on all plan check and permit fees 10% | see rule |
Technology surcharge on all plan check and permit fees 4% | see rule |
How this jurisdiction calculates the fee
Decks, balconies and stairways are charged a flat fee based on area, and the schedule publishes the same amount as both the plan check fee and the permit fee. A permit issuance fee applies to each permit, and all plan check and permit fees carry a 10% General Plan Maintenance surcharge and a 4% Technology surcharge.
Source: published fee schedule · Verified 11/2/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Electrical service 0-200 amp, each Flat fee $45.00 | $45.00 |
○Electrical service 201-1,000 amp, each Flat fee $80.00 | $80.00 |
○Electrical service 1,000+ amp, each Flat fee $176.00 | $176.00 |
○Dwelling re-wire, partial, each Flat fee $51.50 | $51.50 |
○Dwelling re-wire, full, each Flat fee $94.00 | $94.00 |
○EV charger, residential, each Flat fee $33.00 | $33.00 |
○Outlets and receptacles, each Flat fee $0.83 | $0.83 |
○Light switches and occupancy sensors, each Flat fee $0.83 | $0.83 |
○Lighting fixture, each Flat fee $5.50 | $5.50 |
○Dedicated circuit, each Flat fee $5.00 | $5.00 |
○Meter pedestal, each Flat fee $49.00 | $49.00 |
○Meter reset, each Flat fee $28.50 | $28.50 |
○Temporary power pole, each Flat fee $16.50 | $16.50 |
○Electrical switchboard sub-panels 0-600 V, each Flat fee $20.50 | $20.50 |
○Other equipment or devices, not specified, each Flat fee $28.50 | $28.50 |
○Permit issuance, each Flat fee $41.00 | $41.00 |
How this jurisdiction calculates the fee
Electrical work is charged a flat fee for each device, circuit or item of equipment, and the schedule publishes the same amount as both the plan check fee and the permit fee. A permit issuance fee applies to each permit, and all plan check and permit fees carry a 10% General Plan Maintenance surcharge and a 4% Technology surcharge.
Source: published fee schedule · Verified 11/2/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Block Walls/Fence 100 LF or less - charged as plan check fee and again as permit fee Flat fee $71.00 | $71.00 |
○Block Walls/Fence, for each additional 100 LF - each Flat fee $17.50 | $17.50 |
○Retaining Walls 100 LF or less (where the wall also retains) - each Flat fee $102.50 | $102.50 |
○Permit issuance, each Flat fee $41.00 | $41.00 |
California Building Standards fee $1.00 per every $25,000 or portion thereof, in construction valuation | see rule |
General Plan Maintenance surcharge on all plan check and permit fees 10% | see rule |
Technology surcharge on all plan check and permit fees 4% | see rule |
How this jurisdiction calculates the fee
Block walls and fences are charged a flat fee for the first 100 linear feet plus a smaller flat increment for each additional 100 linear feet, and the schedule publishes the same amount as both the plan check fee and the permit fee, so both are charged. A flat permit issuance fee applies per permit, and all plan check and permit fees carry a 10% General Plan Maintenance surcharge and a 4% Technology surcharge. Community Economic Development Department, Building and Safety fee schedule effective July 1, 2026.
Source: published fee schedule · Verified 11/2/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Residential Re-roof (Overlay) 1,000 SF or less - charged as plan check fee and again as permit fee Flat fee $51.50 | $51.50 |
○Residential Re-roof (Overlay), for each additional 500 SF - each Flat fee $12.50 | $12.50 |
○Residential Re-roof (Tear off & Re-roof) 1,000 SF or less - each Flat fee $61.50 | $61.50 |
○Residential Re-roof (Tear off & Re-roof), for each additional 500 SF - each Flat fee $12.50 | $12.50 |
○Residential Re-roof (Tear off & new sheathing) 1,000 SF or less - each Flat fee $89.00 | $89.00 |
○Residential Re-roof (Tear off & new sheathing), for each additional 500 SF - each Flat fee $12.50 | $12.50 |
○Commercial Re-roof (Overlay) 35,000 SF or less - each Flat fee $256.00 | $256.00 |
○Commercial Re-roof (Tear off & Re-roof) 35,000 SF or less - each Flat fee $290.50 | $290.50 |
○Commercial Re-roof (Tear off & new sheathing) 35,000 SF or less - each Flat fee $338.00 | $338.00 |
○Self-Certification Re-roof (permit fee only, no plan check fee) Flat fee $61.00 | $61.00 |
○Permit issuance, each Flat fee $41.00 | $41.00 |
General Plan Maintenance surcharge on all plan check and permit fees 10% | see rule |
Technology surcharge on all plan check and permit fees 4% | see rule |
How this jurisdiction calculates the fee
Re-roofing is charged a flat fee set by the roofing method - overlay, tear off and re-roof, or tear off with new sheathing - for a base area, plus a flat increment for each additional area band; residential bands run in 1,000 SF then 500 SF steps and commercial bands in 35,000 SF steps. The schedule publishes the same amount as both the plan check fee and the permit fee, so both are charged, except for a self-certification re-roof which carries a permit fee only and no plan check fee. A flat permit issuance fee applies per permit, and all plan check and permit fees carry a 10% General Plan Maintenance surcharge and a 4% Technology surcharge. Community Economic Development Department, Building and Safety fee schedule effective July 1, 2026.
Source: published fee schedule · Verified 11/2/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Retaining Walls 100 LF or less - charged as plan check fee and again as permit fee Flat fee $102.50 | $102.50 |
○Retaining Walls, for each additional 100 LF - each Flat fee $45.00 | $45.00 |
○Site Improvements 3,000 SF or less - each Flat fee $652.00 | $652.00 |
○Permit issuance, each Flat fee $41.00 | $41.00 |
California Building Standards fee $1.00 per every $25,000 or portion thereof, in construction valuation | see rule |
General Plan Maintenance surcharge on all plan check and permit fees 10% | see rule |
Technology surcharge on all plan check and permit fees 4% | see rule |
How this jurisdiction calculates the fee
Retaining walls are charged a flat fee for the first 100 linear feet plus a flat increment for each additional 100 linear feet, and the schedule publishes the same amount as both the plan check fee and the permit fee, so both are charged. A flat permit issuance fee applies per permit, and all plan check and permit fees carry a 10% General Plan Maintenance surcharge and a 4% Technology surcharge. Community Economic Development Department, Building and Safety fee schedule effective July 1, 2026.
Source: published fee schedule · Verified 11/4/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○(U) Accessory Structures, 400 SF min & 3,000 SF max - charged as plan check fee and again as permit fee Flat fee $0.40 | $0.40 |
○Minimum charge for a Group U accessory structure (400 SF minimum x $0.40), as plan check fee and again as permit fee Flat fee $160.00 | $160.00 |
○Structures Other Than Buildings (flat fee) - each Flat fee $225.00 | $225.00 |
○Permit issuance, each Flat fee $41.00 | $41.00 |
California Building Standards fee $1.00 per every $25,000 or portion thereof, in construction valuation | see rule |
General Plan Maintenance surcharge on all plan check and permit fees 10% | see rule |
Technology surcharge on all plan check and permit fees 4% | see rule |
How this jurisdiction calculates the fee
A shed is a Group U accessory structure and is priced per square foot under the schedule's Miscellaneous Structures line, with a 400 SF minimum and a 3,000 SF maximum - so a shed smaller than 400 SF is charged at the 400 SF minimum. The schedule publishes the same amount as both the plan check fee and the permit fee, so both are charged. A flat permit issuance fee applies per permit, and all plan check and permit fees carry a 10% General Plan Maintenance surcharge and a 4% Technology surcharge. Community Economic Development Department, Building and Safety fee schedule effective July 1, 2026.
Source: published fee schedule · Verified 11/2/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Water heater up to 100,000 BTU, each Flat fee $18.50 | $18.50 |
○Water heater 100,001-1,000,000 BTU, each Flat fee $28.50 | $28.50 |
○Water heater 1,000,001+ BTU, each Flat fee $51.50 | $51.50 |
○Water heater gas vent, each Flat fee $9.00 | $9.00 |
○Water piping, each Flat fee $3.50 | $3.50 |
○Water service, each Flat fee $33.00 | $33.00 |
○Pressure regulator, each Flat fee $12.00 | $12.00 |
○Solar or hydronic systems, each Flat fee $108.50 | $108.50 |
○Dwellings re-pipe, full, each Flat fee $59.00 | $59.00 |
○Other fixtures or apparatus, not specified, each Flat fee $35.00 | $35.00 |
○Permit issuance, each Flat fee $41.00 | $41.00 |
How this jurisdiction calculates the fee
Plumbing work is charged a flat fee for each fixture or item installed, and the schedule publishes the same amount as both the plan check fee and the permit fee. A permit issuance fee applies to each permit, and all plan check and permit fees carry a 10% General Plan Maintenance surcharge and a 4% Technology surcharge.
Source: published fee schedule · Verified 11/4/2026
See the full write-up: Riverside building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.