San Bernardino, California Building Permit Cost Calculator
Estimates permit cost in San Bernardino from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○New tract home, up to 1,200 sq ft (Table 1A permit fee) Flat fee $564.00 | $564.00 |
○New in-fill/custom home, up to 1,200 sq ft (Table 1B permit fee) Flat fee $1,461.00 | $1,461.00 |
○Residential addition without bath or kitchen $1.74 x 2,000 = $3,480.00 | $3,480.00 |
○Commercial/multifamily, $50,001-$51,000 valuation - building permit fee Flat fee $525.56 | $525.56 |
○Commercial/multifamily, $50,001-$51,000 valuation - plan review fee Flat fee $517.36 | $517.36 |
○Permit issuance fee, all permits Flat fee $60.00 | $60.00 |
How this jurisdiction calculates the fee
San Bernardino prices new residential work off flat square-footage tables rather than raw valuation. New tract homes (built in phases of five or more) use Table 1A and new in-fill or custom homes use Table 1B; both tables bundle the building, electrical, plumbing and mechanical inspection fees and a standard two-car garage, but exclude plan review and issuance. Residential additions are priced per square foot ($1.74/sq ft without a bath or kitchen, $1.92/sq ft with one) with a $375 floor and a $1,459 cap up to 1,200 sq ft. Commercial, industrial and multifamily work is valuation-based: the city assigns a valuation using the per-square-foot cost factors in Table 2 and then reads the permit and plan review fee out of Table 3. On top of the base permit you add a $60 permit issuance fee, plan review, SMIP (0.0001 x valuation residential, 0.00021 x valuation commercial/industrial), a 2% technology fee and a 2% general plan maintenance fee, both computed on plan review plus permit fees, plus archive fees ($1.25 per permit, $3.15 per plan sheet). Plan review for one- and two-family dwellings is billed at the hourly rate, set at 5 hours for a new dwelling or tract model and 3 hours for an addition. Schedule is the Building & Safety Division Schedule of Fees dated 07/2020, adopted with the city's master fee schedule (Council action May 20, 2020, effective July 19, 2020); no newer building schedule is posted.
Source: published fee schedule · Verified 9/15/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Patio/porch construction valuation factor $21.50 x 2,000 = $43,000.00 | $43,000.00 |
○Patio slab only with footing valuation factor $7.10 x 2,000 = $14,200.00 | $14,200.00 |
○Patio cover only valuation factor $14.40 x 2,000 = $28,800.00 | $28,800.00 |
○Minimum permit fee / permit issuance fee Flat fee $60.00 | $60.00 |
How this jurisdiction calculates the fee
The schedule has no line item labeled 'deck.' Decks are priced as valuation work using the closest published construction cost factors - patios/porches at $21.50 per sq ft, a patio slab with footing at $7.10 per sq ft, or a patio cover only at $14.40 per sq ft - with the resulting valuation run through the Table 3 permit and plan review columns and floored at the $60 minimum permit fee. The $60 issuance fee, SMIP, the 2% technology fee and the 2% general plan maintenance fee are added on top. Effective 07/2020.
Source: published fee schedule · Verified 9/15/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Electrical service up to 200 amps Flat fee $38.21 | $38.21 |
○Electrical service 200-1,000 amps Flat fee $77.86 | $77.86 |
○Electrical service 1,000 amps and over Flat fee $155.73 | $155.73 |
○Subpanel Flat fee $22.80 | $22.80 |
○Single-family residential rewire (plus service) $0.07 x 2,000 = $140.00 | $140.00 |
○Electrical minimum fee Flat fee $60.00 | $60.00 |
How this jurisdiction calculates the fee
Electrical permits are priced per unit of work off a dedicated electrical fee table (Table 4) rather than by valuation: a per-square-foot rate for whole-building rewires and then flat per-item charges for services, subpanels, temporary power, outlets, appliances and power apparatus. Every electrical permit is floored at a $60.00 minimum fee and carries the $60.00 permit issuance fee, plus the 2% technology fee and 2% general plan maintenance fee computed on plan review plus permit fees. Solar energy systems are listed at no charge. Effective 07/2020.
Source: published fee schedule · Verified 9/15/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Reroof valuation - composition shingles $180.00 x 20 = $3,600.00 | $3,600.00 |
○Reroof valuation - built-up $230.00 x 20 = $4,600.00 | $4,600.00 |
○Reroof valuation - shake or tile $350.00 x 20 = $7,000.00 | $7,000.00 |
○Reroof valuation - resheathing $107.00 x 20 = $2,140.00 | $2,140.00 |
○Minimum permit fee Flat fee $60.00 | $60.00 |
How this jurisdiction calculates the fee
There is no flat reroof permit fee in San Bernardino. The city converts the job into a valuation using the unit construction cost factors in the schedule's construction-cost table, which price roofing per 'square' (one square = 100 sq ft), and then reads the permit and plan review fee out of the valuation table (Table 3), subject to the $60 minimum permit fee. Add the $60 permit issuance fee, SMIP at 0.0001 x valuation for residential, the 2% technology fee and the 2% general plan maintenance fee. Effective 07/2020.
Source: published fee schedule · Verified 9/15/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
Block wall valuation - 4 ft high $33.00 per lineal foot | see rule |
Block wall valuation - 5 ft high $40.70 per lineal foot | see rule |
Block wall valuation - 6 ft high $48.40 per lineal foot | see rule |
○Block wall valuation - other configurations $8.10 x 2,000 = $16,200.00 | $16,200.00 |
○Minimum permit fee Flat fee $60.00 | $60.00 |
How this jurisdiction calculates the fee
The schedule does not set a flat retaining wall fee. Walls are valued from the published unit construction cost factors for block walls and then charged out of the valuation-based permit and plan review table (Table 3), with the $60.00 minimum permit fee applying to small jobs. The city's block wall factors are per lineal foot by wall height with a catch-all per-square-foot factor for other configurations; engineered walls also incur plan review at the hourly rate. The $60.00 issuance fee, SMIP, 2% technology fee and 2% general plan maintenance fee are added. Effective 07/2020.
Source: published fee schedule · Verified 9/15/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum permit fee Flat fee $60.00 | $60.00 |
○Permit issuance fee Flat fee $60.00 | $60.00 |
Valuation bracket $1-$1,000 - permit fee / plan review fee $60.00 / $30.00 | see rule |
Valuation bracket $9,001-$10,000 - permit fee / plan review fee $146.58 / $144.47 | see rule |
○Mobile home park accessory building with standard plans Flat fee $245.00 | $245.00 |
How this jurisdiction calculates the fee
San Bernardino publishes no dedicated residential shed or accessory-structure permit fee (the only accessory-building line in the schedule is for mobile home park accessory structures, at $245.00 with standard plans or valuation-based without). A shed over 120 sq ft is therefore valued using the Table 2 per-square-foot construction cost factors for the applicable occupancy and construction type and charged out of the Table 3 valuation table, subject to the $60.00 minimum permit fee, plus the $60.00 issuance fee, SMIP, 2% technology fee and 2% general plan maintenance fee. Effective 07/2020.
Source: published fee schedule · Verified 9/15/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Water heater, each (plumbing fee table) Flat fee $15.40 | $15.40 |
○Plumbing minimum fee Flat fee $60.00 | $60.00 |
○Permit issuance fee Flat fee $60.00 | $60.00 |
○Gas meter reset issued in conjunction with other work Flat fee $14.00 | $14.00 |
○Gas meter reset (gauge test required) Flat fee $50.00 | $50.00 |
How this jurisdiction calculates the fee
A water heater is charged as a per-item plumbing permit ($15.40 each) under the plumbing fee table (Table 5), but because every plumbing permit is subject to a $60.00 minimum fee and a $60.00 permit issuance fee, a standalone residential water heater change-out effectively costs the minimum plus issuance rather than the per-item rate. The 2% technology fee and 2% general plan maintenance fee also apply on top of plan review and permit fees, and a gas meter reset is a separate charge if one is needed. Effective 07/2020.
Source: published fee schedule · Verified 9/15/2026
See the full write-up: San Bernardino building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.