B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Calculators
All Calculators
Permits
Permit Fee
Egress
Occupant Load & Egress
Structural
Beam SpanConcrete VolumeExcavationDeck Footings
Electrical
Electrical LoadWire Size
Mechanical
HVAC Load
Fire Safety
Fire Resistance
General
Stair Layout
Elsewhere
Code LibraryDiagramsAssembliesChecklistsNeed a custom calculation? →
PricingLog in
Home / Calculators / Building Permit Fee Calculator

San Bernardino County, California Building Permit Cost Calculator

Estimates permit cost in San Bernardino County from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

R-3 custom home, 1,000 sq ft tier, type VA/VB (combined plan check and inspection)
$2,428 base plus $83.60 per additional 100 sq ft
see rule
R-3 custom home, 1,000 sq ft tier, type IIA/IIB/IIIA/IIIB/IV
$3,035 base plus $104.50 per additional 100 sq ft
see rule
U accessory, private garage, 200 sq ft tier, type VA/VB
$2,443 base plus $74.38 per additional 100 sq ft
see rule
○Intake processing fee
Flat fee $57.00
$57.00
○Plan review (trade permits: building, electrical, plumbing, mechanical)
Flat fee $244.00
$244.00
○AB 1379 Certified Access Specialist Program fee
Flat fee $4.00
$4.00
How this jurisdiction calculates the fee

San Bernardino County does not use a UBC-style valuation table. New buildings are priced from the Construction Fee Schedule adopted under County Code section 16.0204(a)(1), keyed to IBC occupancy group, construction type and square footage, with a base cost at each size threshold plus an incremental amount per additional 100 square feet; plan check and inspection are combined in that figure. Flat-fee trade and miscellaneous permits sit in the fee ordinance itself. SUPERSESSION 2026-09-10: the FY 2024/25 Construction Fee Schedule this row previously cited still returns HTTP 200 but is no longer linked from the county's Building and Safety pages; the current document is the FY 2026/27 Construction Fee Schedule (Board attachment ATT-CAO-040726), and County Code section 16.0204 was amended with rates effective July 1, 2026, July 1, 2027 and July 1, 2028. Every figure below is from the FY 2026/27 / July 1, 2026 columns and is roughly 3 to 7 percent above the amounts previously stored. A $57.00 intake processing fee is added to most permits. California state-mandated add-ons apply on top: the SB 1473 Building Standards Administration Special Revolving Fund fee, the SMIP (Strong Motion Instrumentation Program) fee, and the AB 1379 Certified Access Specialist Program fee; the amended ordinance leaves those cells blank as statutory pass-throughs, and the $4.00 AB 1379 amount below is the figure printed in the county's own master fee schedule.

Source: published fee schedule · Verified 9/15/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

U other - awning/canopy, deck, carport, patio cover, 50 sq ft tier, type VA/VB (combined plan check and inspection)
$691 base plus $59.22 per additional 100 sq ft
see rule
Same line, 250 sq ft tier, type VA/VB
$810 base plus $97.89 per additional 100 sq ft
see rule
Same line, 500 sq ft tier, type VA/VB
$1,054 base plus $76.31 per additional 100 sq ft
see rule
○Revision to a standard plan
Flat fee $146.00
$146.00
○Re-establishment of a standard plan
Flat fee $195.00
$195.00
○Intake processing fee
Flat fee $57.00
$57.00
○AB 1379 Certified Access Specialist Program fee
Flat fee $4.00
$4.00
How this jurisdiction calculates the fee

Decks, carports, patio covers, awnings and canopies are grouped in a single U-occupancy line of the county's Construction Fee Schedule (County Code section 16.0204(a)(1)), priced by size threshold with plan check and inspection combined. SUPERSESSION 2026-09-10: the previously stored row asserted no deck figure at all because the amounts sat in a schedule that had not been read; the FY 2026/27 Construction Fee Schedule (Board attachment ATT-CAO-040726) prints them explicitly, so real numbers are recorded here for the first time, and the FY 2024/25 edition previously relied on is no longer linked from the county's Building and Safety pages although it still returns HTTP 200. Using a county-approved Standard Plan reduces cost: a revision to a standard plan is $146.00 and re-establishing one is $195.00 under County Code section 16.0204 as amended effective July 1, 2026. The $57.00 intake processing fee applies, along with the SB 1473 and SMIP state surcharges and the $4.00 AB 1379 fee.

Source: published fee schedule · Verified 9/15/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Electrical, residential meter change/upgrade
Flat fee $195.00
$195.00
○Electrical, residential new wire/rewire
Flat fee $312.00
$312.00
○Electrical, non-residential new wire, 5,000 sq ft or less
Flat fee $312.00
$312.00
○Electrical, non-residential new wire, 5,001 sq ft and over
Flat fee $390.00
$390.00
○Electrical plan review
Flat fee $244.00
$244.00
○Photovoltaic 15KW or less, single family roof mount: plan review $215.00, permit fee
Flat fee $226.00
$226.00
○Intake processing fee
Flat fee $57.00
$57.00
How this jurisdiction calculates the fee

Electrical work is flat-rated by job type in County Code section 16.0204(b) rather than priced from valuation. Separate flat rates apply to a residential meter change or upgrade, a residential new-wire or rewire, and non-residential new wire split at the 5,000 square foot line. Electrical plan review, where required, is a flat charge. Photovoltaic systems have their own dedicated plan review and permit fees, capped by state law. SUPERSESSION 2026-09-10: the Building and Safety Division Master Fee Schedule effective July 1, 2025 that this row cited still returns HTTP 200 but is no longer linked from the county's Building and Safety pages; County Code section 16.0204 has been amended with rates effective July 1, 2026, July 1, 2027 and July 1, 2028, and every flat electrical amount rose about 3 percent. The $57.00 intake processing fee, the SB 1473 Building Standards fee, the SMIP fee and the $4.00 AB 1379 fee are added. SCHEDULED FUTURE INCREASE recorded 2026-09-12: the San Bernardino County Fee Ordinance amending Code section 16.0204 is a THREE-COLUMN schedule with already-adopted step-ups Effective July 1, 2026 / July 1, 2027 / July 1, 2028. Every figure stored here is the July 1, 2026 column, which is the column in force today. A pass after 2027-07-01 must re-read this row and move it to the next column; the document will not change, only the applicable column, so a reachability check will not catch it.

Source: published fee schedule · Verified 11/6/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Fencing, chain link/wood/wrought iron, residential
Flat fee $117.00
$117.00
○Fencing, all others
Flat fee $195.00
$195.00
Masonry or concrete fence, 250 sq ft tier, type VA/VB (Construction Fee Schedule)
$714 base plus $26.46 per additional 100 sq ft
see rule
○Intake processing fee
Flat fee $57.00
$57.00
○AB 1379 Certified Access Specialist Program fee
Flat fee $4.00
$4.00
How this jurisdiction calculates the fee

Fences are flat-rated in County Code section 16.0204(g)(3), with a lower rate for ordinary residential chain link, wood or wrought iron and a higher rate for everything else. This is a genuinely flat charge with no square-foot or linear-foot math. A masonry or concrete fence is instead priced from the referenced Construction Fee Schedule, which now prints the amount explicitly. SUPERSESSION 2026-09-10: the Building and Safety Division Master Fee Schedule effective July 1, 2025 that this row cited still returns HTTP 200 but is no longer linked from the county's Building and Safety pages; County Code section 16.0204 has been amended with rates effective July 1, 2026, July 1, 2027 and July 1, 2028, and the flat fencing amounts rose about 3 percent. The $57.00 intake processing fee is added, along with SB 1473 and SMIP state surcharges and the $4.00 AB 1379 fee. SCHEDULED FUTURE INCREASE recorded 2026-09-12: the San Bernardino County Fee Ordinance amending Code section 16.0204 is a THREE-COLUMN schedule with already-adopted step-ups Effective July 1, 2026 / July 1, 2027 / July 1, 2028. Every figure stored here is the July 1, 2026 column, which is the column in force today. A pass after 2027-07-01 must re-read this row and move it to the next column; the document will not change, only the applicable column, so a reachability check will not catch it.

Source: published fee schedule · Verified 9/15/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Re-roof, residential with detached or attached garage
Flat fee $234.00
$234.00
○Re-roof, accessory structures
Flat fee $234.00
$234.00
○Re-roof, all others
Flat fee $312.00
$312.00
○Additional re-inspection fee
Flat fee $234.00
$234.00
○Intake processing fee
Flat fee $57.00
$57.00
○AB 1379 Certified Access Specialist Program fee
Flat fee $4.00
$4.00
How this jurisdiction calculates the fee

Re-roofing is one of the flat-fee items in County Code section 16.0204(h). The county charges one flat amount for a residential re-roof including attached or detached garage, the same flat amount for an accessory structure re-roof, and a higher flat amount for everything else (commercial, multifamily and other occupancies). There is no square-foot or valuation math. SUPERSESSION 2026-09-10: the Building and Safety Division Master Fee Schedule effective July 1, 2025 that this row cited still returns HTTP 200 but is no longer linked from the county's Building and Safety pages; County Code section 16.0204 has been amended with rates effective July 1, 2026, July 1, 2027 and July 1, 2028, and every re-roof amount rose about 3 percent. The $57.00 intake processing fee is added, as are the state SB 1473 Building Standards fee, the SMIP fee, and the $4.00 AB 1379 Certified Access Specialist Program fee. SCHEDULED FUTURE INCREASE recorded 2026-09-12: the San Bernardino County Fee Ordinance amending Code section 16.0204 is a THREE-COLUMN schedule with already-adopted step-ups Effective July 1, 2026 / July 1, 2027 / July 1, 2028. Every figure stored here is the July 1, 2026 column, which is the column in force today. A pass after 2027-07-01 must re-read this row and move it to the next column; the document will not change, only the applicable column, so a reachability check will not catch it.

Source: published fee schedule · Verified 11/6/2026

Retaining Wall Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

R-3 masonry or concrete fences and retaining walls, 250 sq ft tier, type VA/VB (combined plan check and inspection)
$714 base plus $26.46 per additional 100 sq ft
see rule
Same line, 1,250 sq ft tier, type VA/VB
$979 base plus $12.41 per additional 100 sq ft
see rule
Same line, 250 sq ft tier, type IIA/IIB/IIIA/IIIB/IV
$892 base plus $33.08 per additional 100 sq ft
see rule
○Intake processing fee
Flat fee $57.00
$57.00
○Plan review (trade/flat-fee permits)
Flat fee $244.00
$244.00
○AB 1379 Certified Access Specialist Program fee
Flat fee $4.00
$4.00
How this jurisdiction calculates the fee

Masonry and concrete retaining walls are priced from the Construction Fee Schedule (County Code section 16.0204(a)(1)), which carries a dedicated R-3 line for masonry or concrete fences and retaining walls banded by size threshold, with plan check and inspection combined. SUPERSESSION 2026-09-10: the previously stored row asserted no wall-specific figure because the linked sub-schedule had not been read; the FY 2026/27 Construction Fee Schedule (Board attachment ATT-CAO-040726) prints it, so real numbers are recorded here for the first time. County Code section 16.0204(g) continues to send both residential and non-residential masonry/retaining walls to that referenced Construction Fee Schedule rather than a flat fee. The $57.00 intake processing fee applies, plus the SB 1473 Building Standards fee, the SMIP fee and the $4.00 AB 1379 fee. Grading of 100 cubic yards or more triggers a separate grading permit fee from the Land Development Master Fee Schedule.

Source: published fee schedule · Verified 9/15/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

U accessory, barn or shed, 200 sq ft tier, type VA/VB (combined plan check and inspection)
$3,091 base plus $77.84 per additional 100 sq ft
see rule
U accessory, private garage, 200 sq ft tier, type VA/VB
$2,443 base plus $74.38 per additional 100 sq ft
see rule
U accessory, agricultural building, 600 sq ft tier, type VA/VB
$4,956 base plus $47.02 per additional 100 sq ft
see rule
○Revision to a standard plan
Flat fee $146.00
$146.00
○Re-establishment of a standard plan
Flat fee $195.00
$195.00
○Intake processing fee
Flat fee $57.00
$57.00
How this jurisdiction calculates the fee

A shed over 120 square feet is permitted as a U-occupancy accessory building and priced from the Construction Fee Schedule adopted under County Code section 16.0204(a)(1), which combines plan check and inspection into a single figure keyed to occupancy, construction type and size tier, with a base cost plus an increment per additional 100 square feet. SUPERSESSION 2026-09-10: the FY 2024/25 schedule previously cited still returns HTTP 200 but is no longer linked from the county's Building and Safety pages; the figures below are from the FY 2026/27 Construction Fee Schedule (Board attachment ATT-CAO-040726) and are roughly 6 to 7 percent above the amounts previously stored. Standard-plan use reduces cost: revising a standard plan is $146.00 and re-establishing one is $195.00 under County Code section 16.0204 as amended effective July 1, 2026. Add the $57.00 intake processing fee plus the SB 1473, SMIP and $4.00 AB 1379 state fees.

Source: published fee schedule · Verified 9/15/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Plumbing, water heater
Flat fee $156.00
$156.00
○Plumbing, residential, 10 fixtures or less
Flat fee $156.00
$156.00
○Plumbing plan review
Flat fee $244.00
$244.00
○Mechanical, residential (HVAC change out, heating elements, other)
Flat fee $156.00
$156.00
○Solar water heating system: plan review $166.00, permit fee
Flat fee $213.00
$213.00
○Intake processing fee
Flat fee $57.00
$57.00
How this jurisdiction calculates the fee

County Code section 16.0204(c) charges a single flat fee for a water heater permit, sitting alongside flat residential plumbing fees banded by fixture count (10 or fewer, 11 to 25, 26 or more) and a flat plumbing plan review fee. There is no valuation calculation. SUPERSESSION 2026-09-10: the Building and Safety Division Master Fee Schedule effective July 1, 2025 that this row cited still returns HTTP 200 but is no longer linked from the county's Building and Safety pages; County Code section 16.0204 has been amended with rates effective July 1, 2026, July 1, 2027 and July 1, 2028. The water heater fee rose from $151.00 to $156.00 and plan review from $226.00 to $244.00; the solar water heating amounts did not change. The $57.00 intake processing fee applies, plus the SB 1473 Building Standards Administration fee, the SMIP fee and the $4.00 AB 1379 Certified Access Specialist Program fee. If the replacement involves gas line or venting changes, a mechanical permit may also apply at the residential mechanical flat rate. SCHEDULED FUTURE INCREASE recorded 2026-09-12: the San Bernardino County Fee Ordinance amending Code section 16.0204 is a THREE-COLUMN schedule with already-adopted step-ups Effective July 1, 2026 / July 1, 2027 / July 1, 2028. Every figure stored here is the July 1, 2026 column, which is the column in force today. A pass after 2027-07-01 must re-read this row and move it to the next column; the document will not change, only the applicable column, so a reachability check will not catch it.

Source: published fee schedule · Verified 11/6/2026

See the full write-up: San Bernardino County building permit cost

Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.