B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Calculators
All Calculators
Permits
Permit Fee
Egress
Occupant Load & Egress
Structural
Beam SpanConcrete VolumeExcavationDeck Footings
Electrical
Electrical LoadWire Size
Mechanical
HVAC Load
Fire Safety
Fire Resistance
General
Stair Layout
Elsewhere
Code LibraryDiagramsAssembliesChecklistsNeed a custom calculation? →
PricingLog in
Home / Calculators / Building Permit Fee Calculator

Charlotte, North Carolina Building Permit Cost Calculator

Estimates permit cost in Charlotte from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.

217 jurisdictions with fee schedules on file

Total cost of work, labor and materials

Used by cities that price per square foot

Fences and retaining walls

Electrical permits priced by the ampere

Building Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Total construction permit value $1 to $3,000, projects not requiring plan review
$59.70 minimum fee
see rule
○Total construction permit value $3,001 to $50,000
$59.70 base plus $12.19 x 250 = $3,107.20
$3,107.20
○Total construction permit value $50,001 to $100,000
$632.57 base plus $5.49 x 250 = $2,005.07
$2,005.07
○Total construction permit value $100,001 to $150,000
$907.12 base plus $5.93 x 250 = $2,389.62
$2,389.62
○Total construction permit value $150,001 to $250,000
$1,203.52 base plus $4.59 x 250 = $2,351.02
$2,351.02
○Total construction permit value $250,001 to $1,000,000
$1,662.37 base plus $5.05 x 250 = $2,924.87
$2,924.87
○Renovation, alteration and upfit projects with a total construction permit value under $100,000
$79.61 x 2,000 = $159,220.00
$159,220.00
○Residential projects where the owner serves as the contractor and the value is less than $40,000, base permit fee
Flat fee $60.00
$60.00
○Residential owner-as-contractor plan review, if required
Flat fee $45.00
$45.00
○Residential owner-as-contractor inspections
Flat fee $45.00
$45.00
○Technology charge on all permits
Flat fee $3.00
$3.00
○Homeowner Recovery Fund
Flat fee $10.00
$10.00
○Certificate of Occupancy
Flat fee $10.00
$10.00
How this jurisdiction calculates the fee

Permit fees are set by the total construction permit value, which is the higher of the value determined by the owner or owner's agent or the value calculated from the department's building valuation data, and a $3.00 technology charge is added to every permit.

Source: published fee schedule · Verified 9/18/2026

Deck Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Minimum fee, total construction permit value $1 to $3,000, projects not requiring plan review
Flat fee $59.70
$59.70
○Total construction permit value $3,001 to $50,000
$59.70 base plus $12.19 x 250 = $3,107.20
$3,107.20
○Renovation/alteration projects under $100,000 total construction permit value
$79.61 x 2,000 = $159,220.00
$159,220.00
○Residential owner-as-contractor, value under $40,000, base permit fee
Flat fee $60.00
$60.00
○Residential owner-as-contractor plan review, if required
Flat fee $45.00
$45.00
○Residential owner-as-contractor inspections
Flat fee $45.00
$45.00
○Technology charge on all permits issued
Flat fee $3.00
$3.00
How this jurisdiction calculates the fee

Building permits in Charlotte are issued by Mecklenburg County Code Enforcement, not the City, so the governing fee document is the Mecklenburg County Land Use and Environmental Services (LUESA) Fee Ordinance, most recently revised July 1, 2026. The ordinance carries no deck line item; a deck is priced from the general schedule on Total Construction Permit Value, which is the higher of the value declared by the owner or agent and the value from the department's building valuation data. Small residential renovation and alteration work is instead charged per trade plus a per-square-foot rate, and homeowners acting as their own contractor on projects under $40,000 use a separate flat per-trade structure. A technology charge is added to every permit.

Source: published fee schedule · Verified 9/15/2026

Electrical Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Minimum fee, total construction permit value $1 to $3,000, projects not requiring plan review
Flat fee $59.70
$59.70
○Commercial permits not requiring plan review, charged per trade
Flat fee $59.70
$59.70
○Commercial permits requiring plan review, charged per trade
Flat fee $79.61
$79.61
○Renovation/alteration and upfit projects under $100,000, electrical trade
$79.61 x 2,000 = $159,220.00
$159,220.00
○Residential owner-as-contractor, value under $40,000, base permit fee
Flat fee $60.00
$60.00
○Residential owner-as-contractor inspections
Flat fee $45.00
$45.00
Appliance/equipment change-out requiring 2 trade permits, issued through Trades Internet Permitting
Total permit fee (both trade permit fees combined) of 1.5 x the minimum permit fee
see rule
○Temporary utilities, initial inspection and placard issuance
Flat fee $100.00
$100.00
○Technology charge on all permits issued
Flat fee $3.00
$3.00
How this jurisdiction calculates the fee

Electrical permits in Charlotte are issued by Mecklenburg County Code Enforcement under the LUESA Fee Ordinance, most recently revised July 1, 2026. Electrical is one of the four trades (building, electrical, mechanical, plumbing - BEMP) the ordinance prices on a per-trade basis. Permits not requiring plan review are charged per trade at the minimum fee; renovation, alteration and upfit projects under $100,000 are charged per trade plus a per-square-foot rate for each involved trade; and homeowners acting as their own contractor on projects under $40,000 use a separate flat per-trade structure. A technology charge is added to every permit.

Source: published fee schedule · Verified 11/2/2026

Fence Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Fence and wall certificate for a fence or wall along a city street, issued by Charlotte DOT in lieu of a permit
Flat fee $0.00
$0.00
How this jurisdiction calculates the fee

Unlike other construction work in Charlotte, fences and walls are handled by the City of Charlotte rather than Mecklenburg County Code Enforcement. Any fence or wall constructed along a city street requires a certificate from the Charlotte Department of Transportation in lieu of a permit, and the City states this certificate carries no cost. Fences located entirely within a back or side yard, away from city-maintained streets and sidewalks, are not covered by the certificate.

Source: published fee schedule · Verified 10/2/2026

Reroof Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Renovation/alteration projects under $100,000 total construction permit value, building trade
$79.61 x 2,000 = $159,220.00
$159,220.00
○Minimum fee, total construction permit value $1 to $3,000, projects not requiring plan review
Flat fee $59.70
$59.70
○Total construction permit value $3,001 to $50,000
$59.70 base plus $12.19 x 250 = $3,107.20
$3,107.20
○Residential owner-as-contractor, value under $40,000, base permit fee
Flat fee $60.00
$60.00
○Residential owner-as-contractor inspections
Flat fee $45.00
$45.00
○Technology charge on all permits issued
Flat fee $3.00
$3.00
How this jurisdiction calculates the fee

Re-roofing permits in Charlotte are issued by Mecklenburg County Code Enforcement under the LUESA Fee Ordinance, most recently revised July 1, 2026. The ordinance carries no roofing line item; a re-roof is a building-trade renovation/alteration, charged per trade plus a per-square-foot rate where the total construction permit value is under $100,000, or otherwise from the general schedule on Total Construction Permit Value. A technology charge is added to every permit.

Source: published fee schedule · Verified 11/2/2026

Retaining Wall Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Minimum fee, total construction permit value $1 to $3,000, projects not requiring plan review
Flat fee $59.70
$59.70
○Total construction permit value $3,001 to $50,000
$59.70 base plus $12.19 x 250 = $3,107.20
$3,107.20
○Total construction permit value $50,001 to $100,000
$632.57 base plus $5.49 x 250 = $2,005.07
$2,005.07
○Renovation/alteration projects under $100,000 total construction permit value
$79.61 x 2,000 = $159,220.00
$159,220.00
○Residential owner-as-contractor, value under $40,000, base permit fee
Flat fee $60.00
$60.00
○Technology charge on all permits issued
Flat fee $3.00
$3.00
How this jurisdiction calculates the fee

Retaining wall permits in Charlotte are issued by Mecklenburg County Code Enforcement under the LUESA Fee Ordinance, most recently revised July 1, 2026. The ordinance carries no retaining wall line item; the wall is priced from the general schedule on Total Construction Permit Value, which is the higher of the value declared by the owner or agent and the value from the department's building valuation data and includes all labor, materials, contractor fees and design professional fees. A technology charge is added to every permit, and additional land development and zoning fees may apply.

Source: published fee schedule · Verified 11/2/2026

Shed Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

○Minimum fee, total construction permit value $1 to $3,000, projects not requiring plan review
Flat fee $59.70
$59.70
○Total construction permit value $3,001 to $50,000
$59.70 base plus $12.19 x 250 = $3,107.20
$3,107.20
○Residential owner-as-contractor, value under $40,000, base permit fee
Flat fee $60.00
$60.00
○Residential owner-as-contractor plan review, if required
Flat fee $45.00
$45.00
○Residential owner-as-contractor inspections
Flat fee $45.00
$45.00
○Technology charge on all permits issued
Flat fee $3.00
$3.00
How this jurisdiction calculates the fee

Shed and accessory building permits in Charlotte are issued by Mecklenburg County Code Enforcement under the LUESA Fee Ordinance, most recently revised July 1, 2026. The ordinance carries no shed line item in its Code Enforcement permit fees; a detached accessory building is priced from the general schedule on Total Construction Permit Value, which is the higher of the value declared by the owner or agent and the value from the department's building valuation data. A technology charge is added to every permit, and additional land development and zoning fees may apply.

Source: published fee schedule · Verified 11/2/2026

Water Heater Permit

These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.

Appliance or equipment change-out issued through Trades Internet Permitting, covering hot water heaters limited to less than 50 gallons or 5,500 watts input for electric and 50 gallons or 55,000 BTU for gas
Total permit fee (both trade permit fees combined) of 1.5 X the minimum permit fee
see rule
Change-out permits issued by means other than Trades Internet Permitting
2 times the maximum permit fee
see rule
○Minimum permit fee, total construction permit value $1 to $3,000, projects not requiring plan review
Flat fee $59.70
$59.70
How this jurisdiction calculates the fee

Water heater change-outs in single-family, townhouse and multi-family residential units are charged as an appliance and equipment change-out, with the total fee set as a multiple of the minimum permit fee and depending on whether the permit is issued through the Trades Internet Permitting automated process.

Source: published fee schedule · Verified 9/24/2026

See the full write-up: Charlotte building permit cost