Raleigh, North Carolina Building Permit Cost Calculator
Estimates permit cost in Raleigh from the city's own published fee schedule — not a national average. Every figure is computed from a rule quoted verbatim from that document, and rules that cannot be computed honestly are shown as the published text instead of a number.
217 jurisdictions with fee schedules on file
Total cost of work, labor and materials
Used by cities that price per square foot
Fences and retaining walls
Electrical permits priced by the ampere
Building Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
New residential building permit · add-on 0.38% of calculated construction value — select the permit fee line above to calculate | see rule |
New residential electrical permit · add-on 49.00% of calculated building permit — select the permit fee line above to calculate | see rule |
New residential plumbing permit · add-on 34.00% of calculated building permit — select the permit fee line above to calculate | see rule |
New residential mechanical permit · add-on 28.00% of calculated building permit — select the permit fee line above to calculate | see rule |
New residential plan review fee · add-on 57.00% of calculated building permit — select the permit fee line above to calculate | see rule |
Technology surcharge · add-on 4% of subtotal of all other fees — select the permit fee line above to calculate | see rule |
○Minimum trade permit fee Flat fee $124.00 | $124.00 |
○Conditional service fee, residential Flat fee $157.00 | $157.00 |
Temporary certificate of occupancy, single-family/duplex units $200.00 per unit ($208.00 with surcharge) | see rule |
○Partial certificate of occupancy Flat fee $313.00 | $313.00 |
○Demolition of a building or structure Flat fee $150.00 | $150.00 |
○Re-inspection fee Flat fee $122.00 | $122.00 |
○After hours inspections (residential) Flat fee $90.00 | $90.00 |
○Commercial and residential re-review fee Flat fee $139.00 | $139.00 |
○Zoning permit fee, 1 and 2 family dwellings, existing structures Flat fee $261.00 | $261.00 |
How this jurisdiction calculates the fee
The building permit for new residential construction is 0.38 percent of calculated construction value. The other permits are then charged as a percentage of that calculated building permit: electrical 49 percent, plumbing 34 percent, mechanical 28 percent and the plans review fee 57 percent. A 4 percent technology surcharge is added on top, and no fee falls below the minimum permit fee of $124.00 per trade. The residential electrical share fell from 54 percent in the prior year to 49 percent in the current guide. Re-verified 2026-09-14 from the cited PDF, and the document at that stable blob URL has been REPLACED SINCE THIS ROW WAS FIRST WRITTEN: it now heads COMPREHENSIVE GUIDE FOR RALEIGH DEVELOPMENT FEES, Development Fee Guide July 1, 2026 - June 30, 2027. The guide states that for Fiscal Year 2027 the department is not recommending new fees, and every figure stored in this row was confirmed present in the FY27 edition, so nothing moved. TRAP WORTH KEEPING: this guide prints TWO amount columns per row, the prior year and FY27, so a single-column read silently picks the wrong year. The stored values are the FY27 (right-hand) column throughout, and several differ from the left column: minimum trade permit fee $123.00 then $124.00, residential re-review $128.00 then $139.00, after hours inspections $82.00 then $90.00 per hour, zoning permit for 1 and 2 family dwellings $253.00 then $261.00, new residential building permit 0.35% then 0.38% of calculated construction value, new residential electrical 54.00% then 49.00% of the calculated building permit. The re-inspection fee moved the other way, $123.00 then $122.00, which is also what this row stores. The 4% technology surcharge is printed as 4% in both columns and the "with surcharge" figures in this row are that 4% applied to the FY27 amounts. RE-VERIFIED 2026-09-28 (lane B, pipeline run 98). The Raleigh Development Fee Guide (57 pages) was downloaded and read in full with pdftotext -layout. It is headed for the period "July 1, 2026 - June 30, 2027" and states that for "Fiscal Year 2027 (FY27), the department is not recommending" new fee increases, so this is the current fiscal-year edition and the figures held over deliberately. EVERY stored figure and percentage across all Raleigh rows re-reads verbatim, including the 0.38 percent new-residential building permit, the $124.00 minimum trade permit fee and its $129.00 surcharged counterpart, the 4 percent technology surcharge, the $122.00/$127.00 re-inspection fee, the $261.00/$271.00 and $278.00/$289.00 zoning permit fees, the 49/34/28/57 percent trade and plan-review percentages, the 28/50/75 percent alteration levels with the 55 percent alterations plan review, the $157.00/$163.00 conditional service fee, the $200.00/$208.00 temporary and $313.00/$326.00 partial certificates of occupancy, the $150.00/$156.00 demolition fee, the $90.00/$94.00 after-hours residential rate, the $139.00 re-review fee, the commercial $224.00/$233.00 appliance and $133.00/$138.00 plumbing utility inspection fees, and the street-construction and tree-conservation table amounts ($26.19, $785.00, $153.00) that are carried with explicit not-a-permit-fee labels. SCHEDULED SUPERSESSION: 2027-07-01, with Raleigh's fiscal year.
Source: published fee schedule · Verified 11/12/2026
Deck Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
New residential building permit · add-on 0.38% of calculated construction value — select the permit fee line above to calculate | see rule |
Level 1 alteration · add-on 28.00% of calculated building permit — select the permit fee line above to calculate | see rule |
Level 2 alteration · add-on 50.00% of calculated building permit — select the permit fee line above to calculate | see rule |
Level 3 alteration · add-on 75.00% of calculated building permit — select the permit fee line above to calculate | see rule |
Alterations and repairs plan review fee · add-on 55.00% of calculated building permit — select the permit fee line above to calculate | see rule |
○Minimum trade permit fee Flat fee $124.00 | $124.00 |
Technology surcharge · add-on 4% of subtotal of all other fees — select the permit fee line above to calculate | see rule |
○Re-inspection fee Flat fee $122.00 | $122.00 |
How this jurisdiction calculates the fee
Raleigh publishes no deck specific permit fee. A screened porch, deck or balcony is permitted as residential building work and priced from calculated construction value. Where the job is treated as an alteration, the charge is a percentage of the calculated building permit: 28 percent at Level 1, 50 percent at Level 2 and 75 percent at Level 3, with an alterations and repairs plans review fee of 55 percent. Minimum permit fees per trade apply, so nothing falls below $124.00 per trade, or $129.00 once the 4 percent technology surcharge is added. Re-verified 2026-09-14 from the cited PDF, and the document at that stable blob URL has been REPLACED SINCE THIS ROW WAS FIRST WRITTEN: it now heads COMPREHENSIVE GUIDE FOR RALEIGH DEVELOPMENT FEES, Development Fee Guide July 1, 2026 - June 30, 2027. The guide states that for Fiscal Year 2027 the department is not recommending new fees, and every figure stored in this row was confirmed present in the FY27 edition, so nothing moved. TRAP WORTH KEEPING: this guide prints TWO amount columns per row, the prior year and FY27, so a single-column read silently picks the wrong year. The stored values are the FY27 (right-hand) column throughout, and several differ from the left column: minimum trade permit fee $123.00 then $124.00, residential re-review $128.00 then $139.00, after hours inspections $82.00 then $90.00 per hour, zoning permit for 1 and 2 family dwellings $253.00 then $261.00, new residential building permit 0.35% then 0.38% of calculated construction value, new residential electrical 54.00% then 49.00% of the calculated building permit. The re-inspection fee moved the other way, $123.00 then $122.00, which is also what this row stores. The 4% technology surcharge is printed as 4% in both columns and the "with surcharge" figures in this row are that 4% applied to the FY27 amounts.
Source: published fee schedule · Verified 11/13/2026
Electrical Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
New residential electrical permit · add-on 49.00% of calculated building permit — select the permit fee line above to calculate | see rule |
○Minimum trade permit fee Flat fee $124.00 | $124.00 |
○Generators (electrical only), commercial Flat fee $396.00 | $396.00 |
○Service repair/replace, commercial Flat fee $198.00 | $198.00 |
○Parking lot lighting Flat fee $320.00 | $320.00 |
○Fixture replacement/retro-fit, 26-50 fixtures, commercial Flat fee $236.00 | $236.00 |
○Photovoltaic (solar), commercial Flat fee $543.00 | $543.00 |
Technology surcharge · add-on 4% of subtotal of all other fees — select the permit fee line above to calculate | see rule |
○Re-inspection fee Flat fee $122.00 | $122.00 |
○After hours inspections (residential) Flat fee $90.00 | $90.00 |
How this jurisdiction calculates the fee
Residential electrical work such as a service upgrade or adding circuits and outlets needs a permit. For new residential construction the electrical permit is 49 percent of the calculated building permit fee. Standalone residential electrical work has no dedicated amount in the fee guide, so it is charged at the minimum trade permit fee of $124.00, or $129.00 with the 4 percent technology surcharge. Every stand alone trade permit line that does carry a published amount is a commercial one. A failed or not ready inspection is $122.00 per inspection per trade. Re-verified 2026-09-14 from the cited PDF, and the document at that stable blob URL has been REPLACED SINCE THIS ROW WAS FIRST WRITTEN: it now heads COMPREHENSIVE GUIDE FOR RALEIGH DEVELOPMENT FEES, Development Fee Guide July 1, 2026 - June 30, 2027. The guide states that for Fiscal Year 2027 the department is not recommending new fees, and every figure stored in this row was confirmed present in the FY27 edition, so nothing moved. TRAP WORTH KEEPING: this guide prints TWO amount columns per row, the prior year and FY27, so a single-column read silently picks the wrong year. The stored values are the FY27 (right-hand) column throughout, and several differ from the left column: minimum trade permit fee $123.00 then $124.00, residential re-review $128.00 then $139.00, after hours inspections $82.00 then $90.00 per hour, zoning permit for 1 and 2 family dwellings $253.00 then $261.00, new residential building permit 0.35% then 0.38% of calculated construction value, new residential electrical 54.00% then 49.00% of the calculated building permit. The re-inspection fee moved the other way, $123.00 then $122.00, which is also what this row stores. The 4% technology surcharge is printed as 4% in both columns and the "with surcharge" figures in this row are that 4% applied to the FY27 amounts.
Source: published fee schedule · Verified 11/13/2026
Fence Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Zoning permit fee, 1 and 2 family dwellings, existing structures Flat fee $261.00 | $261.00 |
○Zoning permit fee, commercial Flat fee $278.00 | $278.00 |
○Minimum trade permit fee Flat fee $124.00 | $124.00 |
Technology surcharge · add-on 4% of subtotal of all other fees — select the permit fee line above to calculate | see rule |
○Other tree disturbing activities or tree fence, per permit/parcel (tree conservation fee, not a fence permit) Flat fee $153.00 | $153.00 |
How this jurisdiction calculates the fee
A zoning permit is required whenever a fence is installed on any property in Raleigh. The Zoning Permit Fee for one and two family dwellings on existing structures is $261.00, or $271.00 with the 4 percent technology surcharge. There is no fence specific building permit line in the fee guide. Do not mistake the $153.00 charge for other tree disturbing activities or a tree fence, billed per permit or parcel, for a fence permit; that one belongs to tree conservation areas and protected buffers. Re-verified 2026-09-14 from the cited PDF, and the document at that stable blob URL has been REPLACED SINCE THIS ROW WAS FIRST WRITTEN: it now heads COMPREHENSIVE GUIDE FOR RALEIGH DEVELOPMENT FEES, Development Fee Guide July 1, 2026 - June 30, 2027. The guide states that for Fiscal Year 2027 the department is not recommending new fees, and every figure stored in this row was confirmed present in the FY27 edition, so nothing moved. TRAP WORTH KEEPING: this guide prints TWO amount columns per row, the prior year and FY27, so a single-column read silently picks the wrong year. The stored values are the FY27 (right-hand) column throughout, and several differ from the left column: minimum trade permit fee $123.00 then $124.00, residential re-review $128.00 then $139.00, after hours inspections $82.00 then $90.00 per hour, zoning permit for 1 and 2 family dwellings $253.00 then $261.00, new residential building permit 0.35% then 0.38% of calculated construction value, new residential electrical 54.00% then 49.00% of the calculated building permit. The re-inspection fee moved the other way, $123.00 then $122.00, which is also what this row stores. The 4% technology surcharge is printed as 4% in both columns and the "with surcharge" figures in this row are that 4% applied to the FY27 amounts. RE-VERIFIED 2026-09-28 (lane B, pipeline run 98). The Raleigh Development Fee Guide (57 pages) was downloaded and read in full with pdftotext -layout. It is headed for the period "July 1, 2026 - June 30, 2027" and states that for "Fiscal Year 2027 (FY27), the department is not recommending" new fee increases, so this is the current fiscal-year edition and the figures held over deliberately. EVERY stored figure and percentage across all Raleigh rows re-reads verbatim, including the 0.38 percent new-residential building permit, the $124.00 minimum trade permit fee and its $129.00 surcharged counterpart, the 4 percent technology surcharge, the $122.00/$127.00 re-inspection fee, the $261.00/$271.00 and $278.00/$289.00 zoning permit fees, the 49/34/28/57 percent trade and plan-review percentages, the 28/50/75 percent alteration levels with the 55 percent alterations plan review, the $157.00/$163.00 conditional service fee, the $200.00/$208.00 temporary and $313.00/$326.00 partial certificates of occupancy, the $150.00/$156.00 demolition fee, the $90.00/$94.00 after-hours residential rate, the $139.00 re-review fee, the commercial $224.00/$233.00 appliance and $133.00/$138.00 plumbing utility inspection fees, and the street-construction and tree-conservation table amounts ($26.19, $785.00, $153.00) that are carried with explicit not-a-permit-fee labels. SCHEDULED SUPERSESSION: 2027-07-01, with Raleigh's fiscal year.
Source: published fee schedule · Verified 9/28/2026
Reroof Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum trade permit fee Flat fee $124.00 | $124.00 |
Level 1 alteration · add-on 28.00% of calculated building permit — select the permit fee line above to calculate | see rule |
Alterations and repairs plan review fee · add-on 55.00% of calculated building permit — select the permit fee line above to calculate | see rule |
Technology surcharge · add-on 4% of subtotal of all other fees — select the permit fee line above to calculate | see rule |
○Re-inspection fee Flat fee $122.00 | $122.00 |
○After hours inspections (residential) Flat fee $90.00 | $90.00 |
How this jurisdiction calculates the fee
Roofing is listed among the alterations and repairs that need a permit but do not need plans. Raleigh publishes no re-roof specific fee. The guide states that any fee not specifically listed as an individual fee is charged at the minimum permit fee, which is $124.00 per trade, or $129.00 with the 4 percent technology surcharge. Where the work is instead priced as an alteration, a Level 1 alteration covering removal and replacement of existing covering is 28 percent of the calculated building permit. A failed or not ready inspection is $122.00 per inspection per trade. Re-verified 2026-09-14 from the cited PDF, and the document at that stable blob URL has been REPLACED SINCE THIS ROW WAS FIRST WRITTEN: it now heads COMPREHENSIVE GUIDE FOR RALEIGH DEVELOPMENT FEES, Development Fee Guide July 1, 2026 - June 30, 2027. The guide states that for Fiscal Year 2027 the department is not recommending new fees, and every figure stored in this row was confirmed present in the FY27 edition, so nothing moved. TRAP WORTH KEEPING: this guide prints TWO amount columns per row, the prior year and FY27, so a single-column read silently picks the wrong year. The stored values are the FY27 (right-hand) column throughout, and several differ from the left column: minimum trade permit fee $123.00 then $124.00, residential re-review $128.00 then $139.00, after hours inspections $82.00 then $90.00 per hour, zoning permit for 1 and 2 family dwellings $253.00 then $261.00, new residential building permit 0.35% then 0.38% of calculated construction value, new residential electrical 54.00% then 49.00% of the calculated building permit. The re-inspection fee moved the other way, $123.00 then $122.00, which is also what this row stores. The 4% technology surcharge is printed as 4% in both columns and the "with surcharge" figures in this row are that 4% applied to the FY27 amounts.
Source: published fee schedule · Verified 11/13/2026
Retaining Wall Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
New residential building permit · add-on 0.38% of calculated construction value — select the permit fee line above to calculate | see rule |
○Minimum trade permit fee Flat fee $124.00 | $124.00 |
Technology surcharge · add-on 4% of subtotal of all other fees — select the permit fee line above to calculate | see rule |
○Re-inspection fee Flat fee $122.00 | $122.00 |
○Retaining wall installation, keystone brick, per square foot (street construction cost table, not a permit fee) Flat fee $26.19 | $26.19 |
○Retaining wall installation, pour-in-place, per cubic yard (street construction cost table, not a permit fee) Flat fee $785.00 | $785.00 |
How this jurisdiction calculates the fee
Raleigh publishes no retaining wall permit fee. A retaining wall is permitted as residential building work and priced from calculated construction value at 0.38 percent, subject to the minimum permit fee of $124.00 per trade, or $129.00 with the 4 percent technology surcharge. Watch the Retaining Wall Installation entries in the fee guide, at $26.19 per square foot for keystone brick and $785.00 per cubic yard for pour in place: those sit in the street and infrastructure construction cost table used to price public improvements, and they are not permit fees. Re-verified 2026-09-14 from the cited PDF, and the document at that stable blob URL has been REPLACED SINCE THIS ROW WAS FIRST WRITTEN: it now heads COMPREHENSIVE GUIDE FOR RALEIGH DEVELOPMENT FEES, Development Fee Guide July 1, 2026 - June 30, 2027. The guide states that for Fiscal Year 2027 the department is not recommending new fees, and every figure stored in this row was confirmed present in the FY27 edition, so nothing moved. TRAP WORTH KEEPING: this guide prints TWO amount columns per row, the prior year and FY27, so a single-column read silently picks the wrong year. The stored values are the FY27 (right-hand) column throughout, and several differ from the left column: minimum trade permit fee $123.00 then $124.00, residential re-review $128.00 then $139.00, after hours inspections $82.00 then $90.00 per hour, zoning permit for 1 and 2 family dwellings $253.00 then $261.00, new residential building permit 0.35% then 0.38% of calculated construction value, new residential electrical 54.00% then 49.00% of the calculated building permit. The re-inspection fee moved the other way, $123.00 then $122.00, which is also what this row stores. The 4% technology surcharge is printed as 4% in both columns and the "with surcharge" figures in this row are that 4% applied to the FY27 amounts. RE-VERIFIED 2026-09-28 (lane B, pipeline run 98). The Raleigh Development Fee Guide (57 pages) was downloaded and read in full with pdftotext -layout. It is headed for the period "July 1, 2026 - June 30, 2027" and states that for "Fiscal Year 2027 (FY27), the department is not recommending" new fee increases, so this is the current fiscal-year edition and the figures held over deliberately. EVERY stored figure and percentage across all Raleigh rows re-reads verbatim, including the 0.38 percent new-residential building permit, the $124.00 minimum trade permit fee and its $129.00 surcharged counterpart, the 4 percent technology surcharge, the $122.00/$127.00 re-inspection fee, the $261.00/$271.00 and $278.00/$289.00 zoning permit fees, the 49/34/28/57 percent trade and plan-review percentages, the 28/50/75 percent alteration levels with the 55 percent alterations plan review, the $157.00/$163.00 conditional service fee, the $200.00/$208.00 temporary and $313.00/$326.00 partial certificates of occupancy, the $150.00/$156.00 demolition fee, the $90.00/$94.00 after-hours residential rate, the $139.00 re-review fee, the commercial $224.00/$233.00 appliance and $133.00/$138.00 plumbing utility inspection fees, and the street-construction and tree-conservation table amounts ($26.19, $785.00, $153.00) that are carried with explicit not-a-permit-fee labels. SCHEDULED SUPERSESSION: 2027-07-01, with Raleigh's fiscal year.
Source: published fee schedule · Verified 9/28/2026
Shed Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Zoning permit fee, 1 and 2 family dwellings, existing structures Flat fee $261.00 | $261.00 |
New residential building permit · add-on 0.38% of calculated construction value — select the permit fee line above to calculate | see rule |
○Minimum trade permit fee Flat fee $124.00 | $124.00 |
Technology surcharge · add-on 4% of subtotal of all other fees — select the permit fee line above to calculate | see rule |
○Re-inspection fee Flat fee $122.00 | $122.00 |
How this jurisdiction calculates the fee
A permit is required for a shed or accessory structure in Raleigh whatever its size. A structure under 12 feet in every direction is handled as a zoning permit, and one that exceeds 12 feet in any direction needs a building permit. The Zoning Permit Fee for one and two family dwellings on existing structures is $261.00, or $271.00 with the 4 percent technology surcharge. Where a building permit is required the fee is 0.38 percent of calculated construction value, subject to the minimum permit fee of $124.00 per trade. Re-verified 2026-09-14 from the cited PDF, and the document at that stable blob URL has been REPLACED SINCE THIS ROW WAS FIRST WRITTEN: it now heads COMPREHENSIVE GUIDE FOR RALEIGH DEVELOPMENT FEES, Development Fee Guide July 1, 2026 - June 30, 2027. The guide states that for Fiscal Year 2027 the department is not recommending new fees, and every figure stored in this row was confirmed present in the FY27 edition, so nothing moved. TRAP WORTH KEEPING: this guide prints TWO amount columns per row, the prior year and FY27, so a single-column read silently picks the wrong year. The stored values are the FY27 (right-hand) column throughout, and several differ from the left column: minimum trade permit fee $123.00 then $124.00, residential re-review $128.00 then $139.00, after hours inspections $82.00 then $90.00 per hour, zoning permit for 1 and 2 family dwellings $253.00 then $261.00, new residential building permit 0.35% then 0.38% of calculated construction value, new residential electrical 54.00% then 49.00% of the calculated building permit. The re-inspection fee moved the other way, $123.00 then $122.00, which is also what this row stores. The 4% technology surcharge is printed as 4% in both columns and the "with surcharge" figures in this row are that 4% applied to the FY27 amounts. RE-VERIFIED 2026-09-28 (lane B, pipeline run 98). The Raleigh Development Fee Guide (57 pages) was downloaded and read in full with pdftotext -layout. It is headed for the period "July 1, 2026 - June 30, 2027" and states that for "Fiscal Year 2027 (FY27), the department is not recommending" new fee increases, so this is the current fiscal-year edition and the figures held over deliberately. EVERY stored figure and percentage across all Raleigh rows re-reads verbatim, including the 0.38 percent new-residential building permit, the $124.00 minimum trade permit fee and its $129.00 surcharged counterpart, the 4 percent technology surcharge, the $122.00/$127.00 re-inspection fee, the $261.00/$271.00 and $278.00/$289.00 zoning permit fees, the 49/34/28/57 percent trade and plan-review percentages, the 28/50/75 percent alteration levels with the 55 percent alterations plan review, the $157.00/$163.00 conditional service fee, the $200.00/$208.00 temporary and $313.00/$326.00 partial certificates of occupancy, the $150.00/$156.00 demolition fee, the $90.00/$94.00 after-hours residential rate, the $139.00 re-review fee, the commercial $224.00/$233.00 appliance and $133.00/$138.00 plumbing utility inspection fees, and the street-construction and tree-conservation table amounts ($26.19, $785.00, $153.00) that are carried with explicit not-a-permit-fee labels. SCHEDULED SUPERSESSION: 2027-07-01, with Raleigh's fiscal year.
Source: published fee schedule · Verified 9/28/2026
Water Heater Permit
These lines are alternatives, not a running bill. Pick the one that describes your project and any percentage-based add-ons will be calculated from it.
○Minimum trade permit fee Flat fee $124.00 | $124.00 |
○New or replacement HVAC/water heater/other appliance, commercial, per 1-3 co-located units per trade Flat fee $224.00 | $224.00 |
○Plumbing utility inspection Flat fee $133.00 | $133.00 |
Technology surcharge · add-on 4% of subtotal of all other fees — select the permit fee line above to calculate | see rule |
○Re-inspection fee Flat fee $122.00 | $122.00 |
How this jurisdiction calculates the fee
A water heater replacement needs a permit in Raleigh but does not need plans. The fee guide carries no residential water heater line. The only water heater amount published is the commercial one, New or replacement HVAC, Water Heater or other appliance for commercial work, at $224.00 per one to three co located units per trade, or $233.00 with the 4 percent technology surcharge; that figure fell by one dollar from the prior year. A residential water heater replacement is therefore charged at the minimum trade permit fee of $124.00, or $129.00 with the surcharge, because the guide charges anything not specifically listed at the minimum permit fee. Re-verified 2026-09-14 from the cited PDF, and the document at that stable blob URL has been REPLACED SINCE THIS ROW WAS FIRST WRITTEN: it now heads COMPREHENSIVE GUIDE FOR RALEIGH DEVELOPMENT FEES, Development Fee Guide July 1, 2026 - June 30, 2027. The guide states that for Fiscal Year 2027 the department is not recommending new fees, and every figure stored in this row was confirmed present in the FY27 edition, so nothing moved. TRAP WORTH KEEPING: this guide prints TWO amount columns per row, the prior year and FY27, so a single-column read silently picks the wrong year. The stored values are the FY27 (right-hand) column throughout, and several differ from the left column: minimum trade permit fee $123.00 then $124.00, residential re-review $128.00 then $139.00, after hours inspections $82.00 then $90.00 per hour, zoning permit for 1 and 2 family dwellings $253.00 then $261.00, new residential building permit 0.35% then 0.38% of calculated construction value, new residential electrical 54.00% then 49.00% of the calculated building permit. The re-inspection fee moved the other way, $123.00 then $122.00, which is also what this row stores. The 4% technology surcharge is printed as 4% in both columns and the "with surcharge" figures in this row are that 4% applied to the FY27 amounts. RE-VERIFIED 2026-09-28 (lane B, pipeline run 98). The Raleigh Development Fee Guide (57 pages) was downloaded and read in full with pdftotext -layout. It is headed for the period "July 1, 2026 - June 30, 2027" and states that for "Fiscal Year 2027 (FY27), the department is not recommending" new fee increases, so this is the current fiscal-year edition and the figures held over deliberately. EVERY stored figure and percentage across all Raleigh rows re-reads verbatim, including the 0.38 percent new-residential building permit, the $124.00 minimum trade permit fee and its $129.00 surcharged counterpart, the 4 percent technology surcharge, the $122.00/$127.00 re-inspection fee, the $261.00/$271.00 and $278.00/$289.00 zoning permit fees, the 49/34/28/57 percent trade and plan-review percentages, the 28/50/75 percent alteration levels with the 55 percent alterations plan review, the $157.00/$163.00 conditional service fee, the $200.00/$208.00 temporary and $313.00/$326.00 partial certificates of occupancy, the $150.00/$156.00 demolition fee, the $90.00/$94.00 after-hours residential rate, the $139.00 re-review fee, the commercial $224.00/$233.00 appliance and $133.00/$138.00 plumbing utility inspection fees, and the street-construction and tree-conservation table amounts ($26.19, $785.00, $153.00) that are carried with explicit not-a-permit-fee labels. SCHEDULED SUPERSESSION: 2027-07-01, with Raleigh's fiscal year.
Source: published fee schedule · Verified 9/28/2026
See the full write-up: Raleigh building permit cost
Estimate only.Fee schedules change, and building departments set the final valuation and decide which fees apply to your scope. Confirm with the jurisdiction before budgeting. Lines marked “see rule” could not be computed from the published wording and are shown verbatim rather than guessed.