§ 62.175 — Notification of results; reporting requirements

General

(a)The mine operator must, within 10 working days of receiving the results of an audiogram, or receiving the results of a follow-up evaluation required under § 62.173 of this part, notify the miner in writing of:

(1)The results and interpretation of the audiometric test, including any finding of a standard threshold shift or reportable hearing loss; and

(2)The need and reasons for any further testing or evaluation, if applicable.

(b)When evaluation of the audiogram shows that a miner has incurred a reportable hearing loss as defined in this part, the mine operator must report such loss to MSHA as a noise-induced hearing loss in accordance with part 50 of this title, unless a physician or audiologist has determined that the loss is neither work-related nor aggravated by occupational noise exposure.

Public Domain: 30 CFR Part 62 (MSHA Occupational Noise Exposure) is a U.S. government publication and is not subject to copyright. Text extracted from the official source ↗. Figures are served from the eCFR; if one does not load, use the link in its place.