106 ALASKA 2020 SECTION 206
206-1.01 DESCRIPTION. Construct a layer of specified material in conformance to the plan
dimensions and elevations.
206-2.01 MATERIALS. Use materials that conform to the following:
Filter Blanket Subsection 703- 2.08
206-3.01 CONSTRUCTIO N REQUIREMENTS. Construct Filter Blanket in an even,
homogeneous layer, avoiding contamination by the underlying material. Place the layer to full thickness in on e application or end- dump and spread by tracked equipment.
206-4.01 METHOD OF MEASUREMENT. See Section 109, by volume in final position or by
weight.
206-5.01 BASIS OF PA YMENT. The contract price includes excavating, processing, hauling,
spreading and lev eling of the filter blanket layer. Payment will be made under: PAY ITEM Item Number Item Description Unit 206.0001.____ Filter Blanket CY 206.0002.____ Filter Blanket TON 107 ALASKA 2020 DIVISION 300 –BASES SECTION 301 AGGREGATE BASE AND S URFACE COURSE
301-1.01 D ESCRIPTION. Construct an aggregate base course or aggregate surface course on
an approved foundation, as shown on the Plans.
301-2.01 MATERIALS. Use aggregate conforming to Subsection 703- 2.03.
Crushed glass may be combined with soil -aggregate material to be used in base course construction. Meet 703- 2.15 requirements. CONSTRUCTION REQUIREMENTS
301-3.01 PLACING. Place material in layers not exceeding 8 inches in depth.
Maintain the roadway surface to drain freely at all times. When paving is specified in the Contract, schedule the work so that any base course placed will be covered prior to winter shutdown. Place surfacing material over all soil -aggregate bases containing glass cullet. Do not place base course soil -aggregate containing glass cullet:
301-3.02 MIXING. Mix the aggregate, incorporating any specif ied additives. Add water, as
needed, to provide the approximate optimum moisture content for compaction. Mix the aggregate by one of the following methods:
301-3.03 SHAPING AND COMPACTION. The maximum density and optimum moisture will be
determined by ATM 207 or ATM 212. Spread and shape the material to the required grade and section. Water or aerate as necessary to provide the approximate optimum moisture content for compaction. Compact each layer to a density of not less than 98 percent of the maximum density. Acceptance densities will be determined by ATM 213 and ATM 214. Maintain the surface of each layer during the compaction operations in such manner that a uniform texture is produced and the aggregates firmly keyed.