232.04 Method of Measurement.
The actual area of the roadbed stabilized as ordered, for each specified compacted depth, completed to the thickness and cross-section shown on the plans or directed, will be measured in square yards {square meters}. All calculations of areas measured for payment shall be based on measurements made to the nearest 0.1 yard {0.1 meter} with areas calculated to the nearest square yard {square meter}. The length will be measured along the surface of the completed roadbed at its center point. The width will be the top surface width of the completed roadbed specified on the plans or directed, measured perpendicular to the center line of roadbed. Additional areas required for crossovers, turnouts, etc., shall be measured by length and width along the surface of area processed. Lime actually incorporated in the work will be measured by the ton {metric ton}. In cases where Pure Quicklime (CaO) is slaked on the jobsite to produce a lime slurry, the pay quantity for lime will be measured in tons {metric tons} of hydrated lime as calculated using the certified lime purity for each truckload as follows: TOTAL TONS {METRIC TONS} HYDRATED LIME PRODUCED = (A x B x 1.32) + A (1.0 - B) Where: A = tons {metric tons} of Quicklime delivered B = certified percent purity Note: 1.32 = ratio of Molecular weights {masses} for Hydrated Lime (74) and Pure Quicklime (56)
232.05 Basis of Payment.
235.01 Description.
The work under this Section shall cover the work of furnishing all materials, construction, maintenance, and removal (unless otherwise directed) of any temporary detour bridge structure at the approximate location shown on the plans or directed.
235.02 Materials.
All timber used shall be a minimum of dense No. 1 structure grade pine or equivalent grade of other wood. Steel or other types of bridging material may be used; however, the grade of material used must be approved by the Bridge Engineer. Other materials shall conform to the requirements noted elsewhere in these Specifications for the type of material used.
235.03 Construction Requirements.
Article 105 — 02 before beginning construction. Prior to submittal, all drawings shall be checked, stamped
approved, and signed by a Licensed Professional Engineer licensed in the State of Alabama and not employed by the Alabama Department of Transportation. The structure shall be designed to carry HS20 loading giving consideration to all vertical and lateral loads to be applied to the structure in accordance with the current edition of the AASHTO Standard Specifications for Highway Bridges using the Service Load Design Method. The Contractor, at his discretion, may exceed these requirements to reduce his maintenance or replacement expense. No work shall be performed on the structure until after distribution of the plans has been made to the Area, District, and Project Managers. The Contractor will be required to comply with the details of the plans as approved. The Contractor shall take full responsibility for the proper structural design, construction, and maintenance of the facility. The licensed Professional Engineer who signed the detour bridge submittal shall verify that the detour bridge as constructed meets all design criteria prior to any load being placed thereon. A signed statement from the licensed Professional Engineer covering the verification shall be furnished to the Project Manager by the Contractor.
235.04 Method of Measurement.
No direct measurement or payment will be made for a detour bridge unless it is listed in the pay items of the contract. The detour bridges listed in the proposal will be identified by the station number of its location and measured as a Lump Sum Unit.
235.05 Basis of Payment.
243.01 Description.
This section covers the installation of geosynthetic soil reinforcement for the reinforcement of soil slopes and for soft soil stabilization. A "geosynthetic soil reinforcement" material shall be any planar geosynthetic (geogrid or geotextile) material designed for the purpose of improving the shear strength of the soil matrix.
243.02 Materials.
The geosynthetic reinforcement (either geogrid or geotextile) shall be constructed of polyester, polypropylene, or polyethylene polymer, resistant to all naturally occurring alkaline and acidic soil conditions, resistant to heat, ultraviolet light, and to attack by bacteria and fungi in the soil. Applicable test methods for measuring strength and creep are: