GEOSYNTHETICS FOR SLOPE AND SOFT SOIL REINFORCEMENT All construction shall be consistent with the requirements for the type of work involved as noted in other portions of these Specifications.
Article 105 — 02 before beginning construction. Prior to submittal, all drawings shall be checked, stamped
approved, and signed by a Licensed Professional Engineer licensed in the State of Alabama and not employed by the Alabama Department of Transportation. The structure shall be designed to carry HS20 loading giving consideration to all vertical and lateral loads to be applied to the structure in accordance with the current edition of the AASHTO Standard Specifications for Highway Bridges using the Service Load Design Method. The Contractor, at his discretion, may exceed these requirements to reduce his maintenance or replacement expense. No work shall be performed on the structure until after distribution of the plans has been made to the Area, District, and Project Managers. The Contractor will be required to comply with the details of the plans as approved. The Contractor shall take full responsibility for the proper structural design, construction, and maintenance of the facility. The licensed Professional Engineer who signed the detour bridge submittal shall verify that the detour bridge as constructed meets all design criteria prior to any load being placed thereon. A signed statement from the licensed Professional Engineer covering the verification shall be furnished to the Project Manager by the Contractor.
235.04 Method of Measurement.
No direct measurement or payment will be made for a detour bridge unless it is listed in the pay items of the contract. The detour bridges listed in the proposal will be identified by the station number of its location and measured as a Lump Sum Unit.
235.05 Basis of Payment.
243.01 Description.
This section covers the installation of geosynthetic soil reinforcement for the reinforcement of soil slopes and for soft soil stabilization. A "geosynthetic soil reinforcement" material shall be any planar geosynthetic (geogrid or geotextile) material designed for the purpose of improving the shear strength of the soil matrix.
243.02 Materials.
The geosynthetic reinforcement (either geogrid or geotextile) shall be constructed of polyester, polypropylene, or polyethylene polymer, resistant to all naturally occurring alkaline and acidic soil conditions, resistant to heat, ultraviolet light, and to attack by bacteria and fungi in the soil. Applicable test methods for measuring strength and creep are:
243.03 Receipt, Inspection and Certification.
Reinforcement geosynthetics delivered to ALDOT projects shall be packaged, identified, stored, and handled in accordance with the requirements given in ASTM D 4873 "Standard Guide for Identification, Storage, and Handling of Geosynthetic Rolls and Samples". Each roll of delivered material shall be individually marked to permit direct correlation with the applicable production Lot Number. Delivered material shall be accompanied by a manufacturer certified copy of test results (ASTM D 4595 for Geotextiles or ASTM D 6637 for Geogrids) verifying the ultimate strength of the Lot(s) from which delivered rolls of reinforcement were obtained. Deliveries of reinforcement that are improperly packaged, marked and/or lack manufacturer certified Lot test results (ASTM D 4595 for Geotextiles or ASTM D 6637 for Geogrids) will not be accepted by the Project Manager. One sample per reinforced slope shall be taken in accordance with Acceptance Sampling and Testing Schedule Section 605.
243.04 Construction Requirements.
All areas immediately beneath the installation area for the geosynthetic reinforcement shall be properly prepared as detailed on the plans, specified elsewhere within the specifications, or directed by the Engineer. In general, the reinforcement shall be installed in accordance with the manufacturer’s recommendations and shall be placed within the layers of the compacted soil as shown on the plans or directed. Only that amount of geosynthetic reinforcement required for immediately pending work shall be placed to prevent undue damage to the reinforcement. After a layer of geosynthetic reinforcement has been placed, suitable means such as pins, small piles of soil, or other fixation means as recommended by the manufacturer shall be used to hold the geosynthetic reinforcement in position until the subsequent soil layer can be placed. Under no circumstance shall a track-type vehicle be allowed on the reinforcement before at least 8 inches {200 mm} of soil have been placed on the reinforcement. Soil layers shall be constructed in accordance with Section 210. SECTION 250 REMOVAL OF UNDERGROUND STORAGE TANKS AND CONTAMINATED SOIL The overlapping of the geosynthetic reinforcement shall be as required by the plans. If a specific overlap is not required by the plans, individual pieces of reinforcement shall typically be installed side by side with the “machine direction” of the material oriented in the direction of required reinforcement. When the delivered width is greater than the width of geosynthetic reinforcement required, the reinforcement may be cut with a razor, knife, abrasion saw, or similar tool. As an alternate to cutting, the Contractor may be allowed to turn the excess portion of the reinforcement under, provided an acceptable installation is obtained. That portion of reinforcement cut off or turned under will not be measured for payment. If a geotextile is required in conjunction with one or more layers of geosynthetic reinforcement, it shall be installed as shown on the plans or directed by the Engineer.
243.05 Method of Measurement.
The quantity of geosynthetic soil reinforcement, measured for payment, will be the number of square yards {square meters} of material installed and acceptably placed. No measurement will be made for portions cut off, overlaps, or portions not needed but allowed to remain in the fill.
243.06 Basis of Payment.
250.01 Description.
This Section shall cover the removal and disposal of underground storage tanks for petroleum-based hydrocarbons and the removal and disposal of contaminated soil. The term underground storage tank (UST) includes the UST and all components (pump lines, vent lines, distribution lines, etc.) of the tank. This Section shall also cover the removal and disposal of the contents of the UST and the backfilling of the areas of removal. The approximate extent of the known contamination will be shown on the plans. The actual limits of contamination will be determined in the field with verification sampling at the time of UST removal. The treatment of groundwater after the removal of the USTs will be done under a separate contract.
250.02 Materials.
Material requirements are not given for the work required under this Section. The furnishing and placement of materials is covered under other Sections.
250.03 Construction Requirements.