502.04 Method of Measurement.
502.05 Basis of Payment.
503.01 Description.
The work under this Section shall cover preparing foundations for bridges, box culverts and other miscellaneous structures. These foundations shall be built in accordance with the details shown on the plans and the provisions provided in this Section.
503.02 Materials.
Materials used in the work required under this Section shall conform to the applicable requirements provided elsewhere in these Specifications. Members designated as mass concrete shall meet the applicable requirements found in Section 510.
503.03 Construction Requirements.
503.04 Method of Measurement.
503.05 Basis of Payment.