509.01 Description.
This Section shall cover the work of furnishing, preparing, and erection of timber or lumber of the stress values, grade, size, and dimensions designated by the plans or proposal. The timber may be treated or untreated as specified by the plans and may require painting if so specified. It shall also include all structural steel, iron, casting, other metal parts, and all hardware required by the Specifications and plans. The type of preservative used shall be the type called for in the plans and/or proposal form. Where more than one type of preservative is included in the contract, each type shall be used as indicated by the plans.
509.03 Construction Requirements.
a.Handling and Storage. Timber and lumber shall be carefully handled without dropping, breaking of outer fibers, bruising, or penetrating the outer surface with tools. Tongs, cant hooks, peavys, hooks, pike poles, or other equipment likely to break the surface shall not be used.
b.Workmanship. Only competent carpenters shall be employed and all framing shall be true and exact. Nails and spikes shall be driven with just sufficient force to set the heads flush with the surface of the wood. Deep hammer marks in wood surfaces shall be considered evidence of poor workmanship and sufficient cause for the removal of workmen causing them. Any metal work required in conjunction with timber construction shall conform to the requirements of Section 508. c.Holes for Bolts, Dowels, Rods, and Lag Screws. Holes for round drift bolts and dowels shall be bored with a bit 1/16 inch {1.6 mm} less in diameter than the bolt or dowel to be used. The diameter of holes for square drift bolts or dowels shall be equal to the least dimension of the bolt or dowel. Holes for machine bolts shall be bored with a bit of the same diameter as the bolt. Holes for rods shall be bored with a bit 1/16 inch {1.6 mm} greater in diameter than the rod. Holes for lag screws shall be bored with a bit 1/16 inch {1.6 mm} less in diameter than the nominal diameter and for a depth not greater than 1/2 the length of the lag screws being used. Countersinking shall be done wherever smooth faces are required. Recesses formed for countersinking shall be painted with hot creosote oil, and after the bolt or screw is in place, shall be filled with an asphalt base roofing patch.
d.Bolts and Washers for Timber Construction. One washer of the size and type specified shall be used under all bolt heads and nuts which would otherwise come in contact with wood. Cast iron washers shall have a thickness equal to the diameter of the bolt, and a diameter of four times the thickness. For malleable or plate washers, the diameter or side size of the square shall be equal to four times the diameter of the bolt, and the thickness of the washers shall be equal to one-half the diameter of the bolt. Cast iron washers shall be used when the timber is in contact with the earth . All bolts shall be checked after the nuts have been finally tightened. Bolts shall be of such length that not more than 1 inch {25 mm} will protrude beyond the nut when finally tightened.
e.Additional Details. Additional requirements for timber construction will be listed under the type work for which the timber is used, including but not limited to Sections 503, 505, 510, 630, 631, 635, 636, and 637. 509.04 Method of Measurement.
The quantity to be measured shall be the number of thousand feet board measure {cubic meters} of lumber and timber, complete in place and accepted. Measurements of lumber and timber will be computed using the nominal width and thickness, and the actual length of each piece shown on the plans, unless changes in such dimensions have been authorized in writing. The nominal size dimensions shall be used in the computations even though the actual size be scant in the amount provided above. The SECTION 510 BRIDGES measurements of timber will include only such timber as is a part of the completed and accepted work, and will not include timber used for erection purposes, such as falsework, bracing, sheeting, etc.
510.03 Construction Requirements.
1.Bridges shall be constructed in accordance with lines, grades, dimensions, and other details shown on the plans and in conformity with these specifications.
2.Construction requirements of Sections 215, 501, 502, 503, 505, 507, 508, 509, 512, 513, 517, 520, and 521 shall also apply to this Section. 3.Concrete tolerances except for bridge deck riding surfaces shall be as follows: Width and depth dimensions of girders, barrier rails, and columns shall not vary more than 1/8 inch per foot {10 mm/m} and not more than 1/4 inch {6 mm} total from plan dimensions. For barrier rail, overhang, and curb, horizontal and vertical alignment shall not vary more than 1/8 inch in 10 feet {3 mm/3 m} and not more than 1/4 inch {6 mm} total from that shown on the plans. The finished concrete shall be free from objectionable projections, swells, ridges, depressions, waves, holes, and other defects.
4.The requirements for curing and finishing the concrete are given in Section 501. 5.Attention is directed to the requirements of Article 107.01 concerning safety. 1.Foundations. Foundations shall be prepared in accordance with the plans and Section 503. 2.Concrete and Steel Substructures. See construction requirements of Sections 501, 502, and 508. 3.Piling. See Section 505. 4.Drilled Shafts. See Section 506. 1.General. No superstructure load shall be placed upon finished piers or abutments until directed. Moreover, before any superstructure load is placed on concrete portions of a substructure, one of the following shall be accomplished: (1) A minimum time of 14 days, exclusive of days where four hours or more the temperature is below 40 °F {5 °C}, shall be allowed for the hardening of concrete, or (2) the concrete shall indicate a development of minimum compressive strength of 2800 psi {19 MPa} from cylinders prepared in conformity with AASHTO T 23. SECTION 510 BRIDGES
2.Bearings and Anchorage. See Item 508.03(d)2. 3.Steel Girders. See Section 508. 4.Prestressed Concrete Bridge Members. See Section 513. 5.Cast-in-Place Concrete Girders, See Sections 501 and 502. Camber due to dead load and vertical curvature shall be put into the falsework and formwork as required to produce the finished lines and grades shown on the plans. 6.Reinforced Concrete Bridge Decks.
a.Pre-Pour Conferences. Pre-pour conferences shall be held between the Contractor and Project Manager prior to placing any bridge deck concrete. As a minimum, this conference shall include a discussion of the rate of pour, personnel and equipment to be used, type of finish, and curing details.
b.Placing Concrete. In addition to the requirements given in Section 501, the following shall also apply. The rate of pour shall be controlled so that all concrete between construction joints can be placed and compacted in a continuous operation before initial set takes place in contiguous portions of the concrete. In case of breakdown of equipment or other reasons necessitating suspension of placing and compacting the concrete for a period in excess of 45 minutes for mixes without retarders or 60 minutes for retarded concrete, and part of the work involved is such that a construction joint will not be permitted, all of the previously placed concrete in that section shall be removed and replaced by the Contractor without extra compensation. A deck pour shall not be started when it is raining or threatening rain. Should inclement weather develop during the pour, it will be the Contractor's responsibility to protect the plastic concrete so that placing and finishing operations can be satisfactorily completed without damage to the concrete or concrete surface. Should damage occur, the concrete shall be removed and replaced at the Contractor's expense. The placing of skin patches (the scabbing on of the concrete or grout) on a bridge deck will not be permitted. All concrete deck slabs shall be placed full thickness in one operation. Unless otherwise shown on the plans, on R.C.D.G. spans, concrete in the girders and slab shall be placed in one operation. Webwalls may be poured and allowed to set up prior to pouring the bridge deck. If a longitudinal screed is to be used for finishing the concrete in the bridge deck, the concrete for the bridge deck shall not be placed until the webwall concrete has reached a minimum compressive strength of 2800 psi {19 MPa} as determined from the testing of cylinders. The deck pouring sequence will vary based on the span type: 1.Fully Continuous Spans (Steel girders and deck continuous over one or more adjacent supports.) On continuous spans, a pouring sequence will be shown on the plans. All lower numbered or lettered pours shall be made prior to proceeding to the next higher numbered or lettered pour. Adjacent pours shall not be made until after the previously placed concrete has reached an age of 24 hours. All requests for changes to the pouring sequences must be submitted in writing to the Construction Engineer for approval.
2.Simple Spans When the below requirements can be met, simple spans shall be constructed in one pour. For simple spans with continuous decks, all deck construction joints shown in the plans shall be required.
a.When using a longitudinal screed, simple spans can be poured up to 80 feet. For pours greater than 80 feet {25 m}, transverse slab construction joints will be required. Transverse slab construction joints shall be placed at approximately the quarter points of the span; after pouring the center portion of the span and when the concrete has reached a compressive strength of 2800 psi {19 MPa} by cylinder tests, or after four days, the end slab portions of the span may be poured.
b.When using a transverse screed, simple spans can be poured up to 170 feet {52m} while maintaining a minimum pour rate of 30 cubic yards {23 m³} per hour and an SECTION 510 BRIDGES approved retarder being required in the deck concrete. For pours greater than 170 feet {52m}, the Contractor shall submit a request in writing to the Construction Engineer for approval. During the placing operation, the concrete shall be placed in strips just ahead of the screed for the entire length or width of the pour, whichever applicable. A small roll of grout shall be kept on the leading edge of the screed so that all depressions ahead of the screed will be filled.
1.General Screed Requirements. All screeds shall be mechanically operated. Screeds and screed supports shall be designed so that they may be pre-set to provide the finish grade and cross-section of the concrete deck surface shown on the plans. They shall be of substantial construction so that the proper settings will be maintained throughout the pour. Screed supports shall be placed and adjusted to properly provide for the deflection of forms, falsework, and structural supporting members which will occur during the placement of concrete. Immediately before concreting operations are started, the screed shall be operated over the full length and width of the bridge segment to be paved. This test run shall be made with the screed adjusted to its finishing position. While operating the screed during this test, all aspects of the screed and supports shall be checked for proper adjustments. After the Contractor has satisfied himself that the finishing equipment has been adjusted to conform with plan and specification requirements, another test run shall be made for the Engineer for the purpose of recording slab thickness and steel clearance measurements prior to the pour being made.
2.Longitudinal Screeds. Longitudinal screeds shall be supported at the ends by transverse headers or by a section of slab previously poured. Screeds must be long enough to span the entire pour as required by the plans and specifications. Intermediate screed supports between approved construction joints will not be permitted. Screeding shall be accomplished by working the longitudinal screed parallel to the centerline of the road (from low side to high side on superelevated curves) in such a manner that laitance, surplus water, and inert materials are removed from the surface.
3.Transverse Screeds. Transverse screeds shall be of sufficient weight {mass} to strike off the plastic concrete placed in front of the screed without "riding up" on the concrete. Transverse screeds shall be supported by vertically adjustable rails set a sufficient distance from the gutter line to allow free movement of the screed from gutter line to gutter line. Supports for the screed rail shall be located a maximum of 18 inches {450 mm}, center-to-center, with the slab overhang support brackets located a maximum of 24 inches {600 mm}, center-to-center. Exceptions to the maximum allowable screed rail and support bracket spacing will be considered if the increased spacing is adequately addressed in the design calculations that are required as a part of the Working Drawings (for falsework). Satisfactory means of load distribution with minimum rail deflection shall be provided. The screed rails for any deck pour shall be completely in place for the full length of the pour and shall be firmly secured prior to making test runs and subsequently placing deck concrete. In making the test runs, a "tell-tale" device attached to the screed carriage may be used to check the proper clearance on the top mat of the reinforcing steel.
4.Work Bridges. Portable work bridges shall be provided and used to perform finishing and inspection work on the bridge deck after the screeding operation. Surface tolerance as described in Subitem 510.03(c)6.d shall be accomplished before grooving the deck surface. 5.Final Finishing. The final finish behind longitudinal screeds shall be obtained by wood floating or by broom finish. The final finish behind transverse screeds shall be obtained by either wood floating, broom finish or burlap drag. Brooms for broom finishing shall have medium to stiff nylon bristles. The final texture shall be obtained by the cutting of transverse grooves in the cured concrete. The bridge decks shall be grooved perpendicular to the centerline. The grooving operation shall not be started until the bridge deck has been cured in accordance with the requirements given in Section 501. The grooves shall be cut into the hardened concrete using a mechanical saw device which will leave grooves approximately 1/8 inches {3 mm} wide and 1/8 inches {3 mm} deep. The grooves shall be unevenly spaced and randomly varying between 5/8 inches {15 mm} and 1.125 inches {30 mm}. The grooved finish shall be at right angles to the centerline of the bridge deck, regardless SECTION 510 BRIDGES of skew, and shall extend across the roadway from 2 feet {600 mm} inside the face of the curb or barrier rail to 2 feet {600 mm} inside the face of the opposite curb or barrier rail. Each pass of the grooving machine shall be adjacent to the previous pass without overlapping. All residue, slurry and other waste resulting from the grooving operation shall be continuously removed from the bridge deck so that there is never a build-up of these waste materials. Upon approval by the Engineer, these waste materials may be disposed in earthwork when earthwork is a part of the bridge construction project. The waste materials may be tilled into the earthwork so that water run-off will not transport these materials from the construction site. If the Engineer does not approve of the disposal of the waste material on the construction site, the Contractor shall remove the waste material from the project and dispose of it in accordance with all applicable laws and ordinances for disposal. d.Surface Tolerance. The floor shall be constructed to correct elevation, including vertical curvature, within a tolerance of 1/8 inch {3 mm}, except that camber in spans 100 feet {30 m} and longer may exceed the designated amount by 1/4 inch {6 mm} at the midpoint of span. A slight excess of camber is preferred. As soon as the surface has set sufficiently, it shall be straight-edged by the Contractor under the direction of the Engineer and all areas exceeding 1/8 inch in 10 feet {3 mm in 3 m} from the longitudinal and transverse lines shown on the plans shall be marked and corrected by approved methods. The 10 foot {3 m} straight-edge shall be lapped at least 5 feet {1.5 m} over the prior 10 foot {3 m} check.
e.Curing. The requirements for curing are given in Section 501. f.Drainage. Deck drains or scuppers shall be installed in the gutters at locations and in accordance with details shown on the plans.
g.Slab Overhang. The under surface of overhanging slabs shall be provided with a continuous "V" groove 3/4 of an inch {20 mm} in depth at a point not more than 6 inches {150 mm} from the outside face for the purpose of arresting the flow of water, and thus, preventing staining,
h.Expansion Joints. Plates, channels, or other structural shapes shall be accurately shaped, in the shop, to conform to the section of the concrete floor. The fabrication and painting shall conform to the requirements of these specifications and/or the plans covering those items. Care shall be taken to ensure that the surface in the finished plane is true and free from warp. Positive methods shall be employed in placing the joints to keep them in correct position during the placing of the concrete. Unless otherwise shown on the plans, the joint opening shown on the plans is the opening when the temperature of the structure is 70 °F {20 °C}. Special care shall be taken to ensure that all expansion joint devices and expansion joint openings are correctly set prior to pouring the concrete adjacent to the joint. Expansion joints shall be so constructed as to permit freedom of movement of the spans. Open joints shall be cleared of all mortar and other obstructions as soon as possible after pouring the spans. Sealing of joints, if required, shall be in accordance with plan details.
j.Barrier Rails Placed By Slip Forming. Bridge barrier rails constructed by the use of a slip form extrusion machine shall be well compacted dense concrete meeting all the requirements of Section 501, except for the requirement for fixed forms. The forming portion of the extrusion machine shall be readily adjustable vertically during the forward motion of the machine so that the top of the barrier can be maintained at the required grade. Open joints shall be located as required on the plans and Bridge Special Project Drawing series BBR. Longitudinal bars shall be cut at joint locations to provide for 2 inch {50 mm} end cover. The Contractor shall be responsible for marking these locations in advance of placement of concrete so that sawed joints will be properly located. The joints shall be sawed as soon as the concrete has hardened to the degree that tearing and raveling is not excessive, and before uncontrolled shrinkage cracking begins. This time may SECTION 510 BRIDGES be as short as four hours or even less in extremely warm weather, but not over 12 hours unless authorized by the Engineer. If extreme conditions exist which make it impractical to prevent uncontrolled cracking by early sawing, the procedure shall be revised immediately to adjust the sequence of sawing. A minimum saw cut width of 5/16 of an inch {8 mm} shall be maintained. On the inside of the barrier, the saw cut shall extend from the top to the bottom of the rail to the point of intersection with the bridge deck. On the outside of the barrier, the saw cut shall extend from the top to within 11 inches {280 mm} of the bottom of the rail. k.Placement of Cranes on Bridge Decks. A crane shall not be placed on a bridge deck until Working Drawings for the placement and operation of the crane are distributed by the Department. Working Drawing shall be submitted in accordance with the requirements given in Section 105. The Working Drawing submittal shall include: 1.Specifications of the crane and/or equipment to be placed on the structure.
2.Mobilization (wheel location) diagram of the crane (with respect to centerline of structure) as it is being mobilized for final positioning on the structure.
3.Final positioning/usage diagram once the crane is on the structure showing the location of the outriggers, and timber mat requirements (i.e. mat thickness, width, orientation of mats), maximum load to be lifted for a particular positioning of the boom, etc.
4.A complete stress analysis (superstructure and substructure) on all components affected by loads resulting from the use of the crane and/or equipment on the structure. The analysis shall be provided in accordance with AASHTO Allowable Stress Design Method. Mobilization analysis (item 2) as well as final positioning/usage analysis (item 3) will be required. The results of the analysis shall be noted on the submittal by a written conclusion that the placement of the crane will not damage any part of the bridge .
7.Concrete Railings, Curbs, Sidewalks, and Parapets. In no case shall concrete railings, sidewalks, and parapets be placed until the falsework for the span has been released, rendering the span self-supporting. The surface of all bridge sidewalks shall have a wood-float finish. No other finish will be required.
8.Grounding. If grounding is required by the plans, each exterior girder of bridges or portions of the bridges using steel girders shall be made electrically continuous by means of copper bonding jumpers across each expansion joint. Jumpers shall be extra flexible copper conductor, No. 2 AWG or larger. They shall be exothermically welded on the inside of the web close to the bottom flange. Jumpers shall be sized to permit 10 inches {250 mm} movement between girders without straining the jumper or connections. Grounding fields shall be provided at each end of such bridges or portion of bridges. Where end of bridge terminates at an abutment, the field shall consist of one or more driven ground rods as required to give a resistance to ground not to exceed 25 ohms. Multiple grounds or sectional ground rods will be acceptable. Connections between ends of bridge and ground field shall be copper conductor, No. 6. or larger, protected against mechanical injury in all exposed portions by galvanized steel conduit. Resistance measurements shall not be made within 48 hours after a rain shower, or until the ground is reasonably dry after prolonged rainy weather. Where steel sections of bridges terminate at intermediate bents, the grounding field shall consist of No. 2/0 standard stranded copper conductor welded to steel piling or steel reinforcing rods, whichever extends to the lowest depth, and a 2 foot {600 mm} or longer section of copperweld grounding rod extended 4 inches {100 mm} above the bent cap adjacent to end of steel section. All welds shall be exothermic. Connection between ground rod and structure shall be a No. 2 AWG or larger, extra flexible electric copper conductor with provisions for not less than 12 inches {300 mm} horizontal movement of the structure at point of connection. Reference is made to Article 836.09 for additional material requirements. 1.Temperature Recording & Monitoring In-place concrete temperatures shall be monitored and recorded for a minimum period of 7 days after concrete placement, unless otherwise designated by the Engineer. Temperatures shall be electronically recorded automatically by a recorder furnished by the Contractor and shall be capable of continuously recording a minimum of one reading per hour SECTION 510 BRIDGES for the duration of the mass concrete temperature monitoring period. The sensors and recorder shall be accurate to within ± 2 °F {1 °C} within the temperature range of 40 °F {4 °C} to 200 °F {93 °C}. The proposed temperature sensors and recorder for the project shall be defined in the ThCP for approval by the State Materials and Tests Engineer. Sensors shall be installed in accordance with ALDOT-455. The concrete producer shall be responsible for controlling the concrete temperature at delivery, per ALDOT-352. The Contractor shall be responsible for controlling the concrete temperature thereafter.
2.Maximum In-Place Concrete Temperature. The maximum in-place concrete temperature limit for mass concrete shall be 160 °F [71 °C}. The maximum in-place concrete temperature limit may be raised to 185 °F {85 °C} if the project concrete mix design contains mineral admixtures at one of the following minimum substitution rates: Mineral Admixture Minimum Substitution Percentage Class F fly ash only 25% Class C fly ash only 35% GGBFS 35% Microsilica (with Class F fly ash) 5% microsilica, 20% Class F fly ash Microsilica (with GGBFS) 5% microsilica, 25% GGBFS
3.Maximum In-Place Concrete Temperature Differential. The maximum in-place concrete temperature differential is defined as the difference in measured temperature at the core of the member and the measured temperature at the surface. The maximum in-place concrete temperature differential for mass concrete shall be 35 °F {19 °C} Alternatively, the Contractor may, at his expense, determine the coefficient of thermal expansion (CTE) for the project concrete mix design, per AASHTO T 336, and develop an age- dependent maximum in-place concrete temperature differential, per ALDOT-456.
4.Thermal Control Plan (ThCP) The Contractor shall submit a written ThCP to the State Materials and Tests Engineer for approval describing the procedures that will be used during the 7-day period following concrete placement, so that the maximum in-place concrete temperatures and maximum in-place concrete temperature differentials do not exceed the limits defined in Items 510.03(d)2 and 510.03(d)3. The ThCP shall be developed by a Professional Engineer, licensed in the State of Alabama, who shall be competent in the modeling, design, and temperature control of mass concrete. This Engineer shall be called the Thermal Control Plan (ThCP) Engineer. The ThCP shall list actions to take when any of the temperature limits set in Items 510.03(d)2 and 510.03(d)3 are exceeded or anticipated to be exceeded. The ThCP shall be submitted at least 30 calendar days before the first intended mass concrete placement. The Contractor shall not place concrete covered by this specification until the ThCP has been accepted for completeness in writing by the State Materials and Tests Engineer and the equipment and materials necessary to facilitate the plan are on site and ready for use. The ThCP shall include the following: Concrete mixture design per ALDOT-170. If the concrete mixture proportions are changed, then the ThCP shall be updated. The maximum in-place concrete temperature in accordance with Item 510.03(d)2 that shall be used for the project. The maximum in-place concrete temperature differential in accordance with Item 510.03(d)3 that shall be used for the project. If an age-dependent maximum concrete temperature differential is used, it shall be defined in tabular form, and the CTE shall be reported. SECTION 510 BRIDGES Calculated or measured adiabatic temperature rise of the mass concrete element. Proposed methods to control concrete temperature at time of placement, such as pre-cooling of raw materials or concrete. Proposed methods to control maximum concrete temperature during curing. A mechanical cooling system may be used to control the internal temperature of mass concrete during curing but shall be designed in conformance with the ThCP. If a mechanical cooling system is used, the plans for the cooling system operation and final grouting after cooling shall be submitted to the State Materials and Tests Engineer for approval. Maximum concrete temperature at time of placement used during the development of the Temperature Control Plan. Calculated maximum concrete temperature during curing based on expected conditions and methods used to control temperature. Proposed methods to control concrete temperature differentials during curing. Calculated maximum temperature differential based on expected conditions and methods used to control the temperature difference. Submit the thermal calculation model and/or computational software with the ThCP. Information on the temperature sensing and recording equipment to be used and drawings of locations of temperature sensors within each placement. Description of the format and frequency of providing temperature data. List of corrective measures to be taken to reduce excessive temperatures and temperature differences, if they occur. Description of curing methods and duration of curing. Description of formwork removal procedures and method to ensure that the temperature differences at exposed surfaces will not exceed the maximum concrete temperature differential. 5.Collection and Submittal of Measured Concrete Temperatures The ThCP Engineer must personally inspect and approve the installation of temperature monitoring devices and verify that the process for recording temperature readings is effective for the first placement of each size and type of mass concrete element. Submit to the Engineer for approval the qualification of all technicians employed to inspect or monitor mass concrete placements. For placements other than the first, designate an employee or employees approved by the ThCP Engineer, as qualified to inspect monitoring device installation, to record temperature readings, to be in contact at all times with the ThCP Engineer if adjustments must be made as a result of the maximum concrete temperature limit or maximum concrete temperature difference limit being exceeded, and to immediately implement adjustments to temperature control measures as directed by the ThCP Engineer. The Contractor shall notify the Engineer when the concrete temperature comes within 15 °F {8 °C} of the maximum in-place temperature limit or when the concrete temperature difference comes within 10 °F {6 °C} of the maximum in-place concrete temperature differential limit, and immediately take corrective measures to comply with the concrete temperature requirements of this specification. The Contractor shall submit to the Engineer within three (3) days of completion of monitoring of each mass concrete element a copy of all measured temperature readings and include the measured maximum concrete temperature and maximum concrete temperature difference.
Source: 2026 Standard Specifications for Highway Construction, 2026 Edition. Pages 368–378 of 826.