628.01 Description. This item consists of furnishing and placing
topsoil on completed slopes and ditches according t o these specifications and at locations shown on the plans or as directed by the Engineer.
628.02 Materials. Topsoil may be obtained from sources outside
the right-of-way limits or from areas within the pr oject limits that will be occupied by cuts and/or embankments. When topsoil is furnished from sources outside the right-of-way, th e Contractor shall be responsible for locating and obtaining the mater ial and for performing all work, including erosion control, pre vention of water pollution, and restoration, according to the specif ications. The cost of such work will be considered included in the con tract unit price bid for Topsoil Furnished and Placed. At the reque st of the Engineer, the Contractor shall furnish copies of ag reements with the property owners. Topsoil from all sources shall be the surface layer of soil with no admixture of refuse or any material toxic to plant growth and shall be reasonably free from subsoil and stumps, roots, brush, stone, clay lumps, or similar objects larger than 2" (50 mm) in greatest diameter. In no case shall topsoil be excavated mo re than 12" (300 mm) from the original ground level. Brush and other vegetation that will not be incorporated with the s oil during handling operations shall be cut and removed. Ordinary sods and herbaceous growth, such as grass and weeds, shall not be remov ed but shall be thoroughly broken up and intermixed with the soil d uring handling operations. Topsoil may contain a reasonable amoun t of waste from clearing operations, such as small twigs and roots, that can be expected to reach early decay.
628.03 Construction Operations. (a) Removing, Stori ng, and
Handling Topsoil. Topsoil stripped from within the project shall be moved to areas on the right-of-way, or other approv ed locations, and stockpiled. When measurement is to be by the cross section method, 508 the stockpiles shall be uniformly shaped and suscep tible to ready measurement by the cross section method. Stockpile s shall be located so that they will not interfere with any pr oposed construction nor constitute drainage, traffic, or other hazards, either to the project, the general public, or adjacent property. Storage should be in such locations that will afford easy access for loading, hauling, and replacement. The stored topsoil shall be protected from contamination. If the condition of the soil is unsuitable due to e xcessive moisture, frost, or other conditions, the Contracto r shall cease work under this item until the soil is in a suitable con dition. Topsoil stripped from within the project limits sha ll be removed prior to the taking of original cross sections. Th e Contractor shall schedule the work in coordination with the Resident Engineer so as to minimize any delay between the stripping of the topsoil, the taking of original cross sections, and the beginnin g of excavation and/or embankment construction. Failure of the Con tractor to properly schedule the work will not be considered a s grounds for extension of time nor for additional payment due to any resulting delays.
628.04 Method of Measurement. Topsoil furnished from
outside the right-of-way will be measured by the cu bic yard (cubic meter) in vehicles at the point of delivery for use on the project. Topsoil obtained from within the project limits wil l be measured by the cubic yard (cubic meter) either in stockpiles b y the cross section method or in vehicles at the point of delivery for spreading. No adjustment will be made for swell.
628.05 Basis of Payment. Work completed and accepted and
measured as provided above will be paid for at the contract unit price bid per cubic yard (cubic meter) for Topsoil Furnished and Placed, which price shall be full compensation for furnishing, hauling, stockpiling, moving, and placing topsoil; and for all labor, equipment, tools, and incidentals necessary to comp lete the work. Payment will be made under: Pay Item Pay Unit Topsoil Furnished and Placed Cubic Yard (Cubic Mete r) 510 SECTION 629 GABIONS
629.01 Description. This item shall consist of the construction
of interconnected rectangular wire-mesh baskets fil led with coarse nondegradable stone to be used as retaining walls a ccording to these specifications and conforming to the lines, grades, dimensions, locations, and design shown on the plans, or as dir ected.
629.02 Materials. (a) All wire for gabion baskets shall meet the
requirements of Subsection 106.01. Wire for gabion baskets shall be 11 gage (3.0 mm), or equivalent, with a tensile str ength between 60,000 to 85,000 psi (415 and 585 MPa). The minimu m zinc coating of the wire shall be 0.80 oz./sq. ft (245 g /sq m) of uncoated wire surface complying with AASHTO T 65. Lacing wi re shall comply with the same specifications as wire used in the mesh and shall be 13½ gage (2.2 mm). All perimeter edges (m esh edge and selvage rod wires) of the mesh forming the gabion s hall be securely selvaged with wire of 9 gage (3.8 mm) or greater. The wire mesh shall be fabricated in such a manner as to be nonra veling as defined by the ability to resist pulling apart at any of th e twists or connections forming the mesh when a single wire in a section of mesh is cut. Openings of the mesh shall be approxi mately 4½" (115 mm) in the longest dimension by approximately 3¼" (80 mm).
629.03 Construction Requirements. (a) Excavation. The
existing material shall be excavated to the require d depth. Soft and yielding material shall be removed and replaced wit h suitable material and the entire subgrade shall be thoroughl y compacted.
629.04 Method of Measurement. Gabions will be measured by
the cubic yard (cubic meter) of gabion baskets in p lace using the specified dimensions.
629.05 Basis of Payment. Work completed and accepted under
this item and measured as provided above will be pa id for at the 512 contract unit price bid per cubic yard (cubic meter ) for Gabions, which price shall be full compensation for furnishi ng materials; for assembling and securing baskets; for placing stone in baskets; and for all equipment, tools, and incidentals necessary to complete the work. Excavation, material for backfill, and filte r fabric will be paid for under other appropriate contract items. Payment will be made under: Pay Item Pay Unit Gabions Cubic Yard (Cubic Meter)