Division 600 — Incidental Construction

653Topsoil Furnished and Placed

OH · 2023 (rev. 7/17/2026) Standard Specifications✓ Full text on BuildSpecBook pages 622–623 Save this section

Ask about Section 653

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

ITEM 653 TOPSOIL FURNISHED AND PLACED

653.01 Description. This work consists of furnishing and spreading topsoil and preparing the

subgrade.

653.02 Materials. Furnish topsoil consisting of loose, friable, loamy material without admixture

of subsoil or refuse. For topsoil to be considered loamy, ensure that the fraction passing the No. 10 (2.00 mm) sieve does not contain more than 40 percent clay. Furnish topsoil consisting of not less than 4 percent and not more than 20 percent organic matter as determined by loss on ignition of samples oven dried to constant weight at 212 F. Test topsoil according to AASHTO T 267. Furnish topsoil that is free of grass, brush, and, roots.

653.03 Construction Requirements. Before placing any topsoil, prepare all areas to be covered

with topsoil according to 659.10. Place the topsoil according to 659.11. When seeding is specified, open the topsoil up to receive the seed.

653.04 Method of Measurement. The Department will measure compacted Topsoil Furnished

and Placed by the number of cubic yards accepted in place.

653.05 Basis of Payment. The Department will pay for accepted quantities at the contract price

as follows: Item Unit Description 653 Cubic Yard Topsoil Furnished and Placed

Referenced in this section

Get an email when 653 changes

Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Construction and Material Specifications, 2023 (rev. 7/17/2026) Edition. Pages 622–623 of 892. View official source ↗