652Placing Stockpiled topsoil

OH · 2023 (rev. 7/17/2026) Standard Specifications✓ Full text on BuildSpecBook pages 621–622 Save this section

Ask about Section 652

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

ITEM 652 PLACING STOCKPILED TOPSOIL

652.01 Description. This work consists of hauling and spreading topsoil from stockpiles and

preparing the surface.

652.02 Construction Requirements. Prepare the surface according to 653.03. Place and spread

the topsoil according to 653.03.

652.03 Method of Measurement. The Department will measure Placing Stockpiled Topsoil by

the number of cubic yards completed and accepted in place.

652.04 Basis of Payment. The Department will pay for accepted quantities at the contract price

as follows: Item Unit Description 652 Cubic Yard Placing Stockpiled Topsoil

Referenced in this section

Get an email when 652 changes

Ohio revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Construction and Material Specifications, 2023 (rev. 7/17/2026) Edition. Pages 621–622 of 892. View official source ↗

Ask about this section

Scoped to Ohio Construction & Material Specifications, Section 652 — Placing Stockpiled topsoil. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.