ITEM 651 TOPSOIL STOCKPILED
651.01 Description. This work consists of stripping topsoil from areas shown on the plans or
from within the Right -of-Way limits, transporting, and stockpiling topsoil at locations shown on the plans or at locations selected by the Contractor with project approval.
651.02 Construction Requirements. Remove all heavy grass, weeds, or other vegetation over
the areas before stripping. Keep the topsoil separate from other excavated materials. Remove topsoil before beginning the regular excavation or embankment work in the area. Strip the topsoil to the depth shown on the plans or as directed by the Engineer.
651.03 Method of Measurement. The Department will measure Topsoil Stockpiled by the
number of cubic yards completed and accepted, measured from the removal areas.
651.04 Basis of Payment. The Department will not pay for any removal of topsoil beyond the
directed depth. The Department will pay for accepted quantities at the contract price as follows: Item Unit Description 651 Cubic Yard Topsoil Stockpiled