36 GENERAL
36-1 General
36-1.01 General
36-1.01A Summary
Section 36 includes general specifications for constructing surfacings and pavements.
36-1.01B Definitions
Reserved
36-1.01C Submittals
Reserved
36-1.01D Quality Assurance
36-1.01D(1) General
Reserved
36-1.01D(2) Preconstruction Meetings
At least 3 business days before the start of surfacing and pavement operations, hold a preconstruction meeting with the Engineer and your:
6.Traffic control foreman
7.Subcontractors ' foremen Meeting attendees must sign an attendance sheet provid ed by the Engineer. The Engineer retains the attendance sheet. Discuss the project specifications and the processes for producing materials and constructing each item of work, including:
1.Quality assurance: 1.1. Quality control 1.2. Department acceptance
2.Placement of materials: 2.1. Training 2.2. Checklists 2.3. Test sections or trial slabs
4.Issues specific to the project, including: 4.1. Weather 4.2. Alignment and geometrics 4.3. Traffic control issues 4.4. Haul distances 4.5. Presence and absence of shaded areas 4.6. Other local issues Do not place trial slabs, construct test strips, or start paving activities until the listed personnel have attended the meeting.
36-1.02 Materials
Not Used SECTION 36 GENERAL
36-1.03 Construction
Not Used
36-2 Base Bond Breaker
36-2.01 General
36-2.01A Summary
Section 36 -2 includes specifications for applying or placing a base bond breaker between a base and concrete pavement.
36-2.01B Definitions
Reserved
36-2.01C Submittals
Submit a certificate of compliance for each shipment of base bond breaker material delivered.
36-2.01D Quality Assurance
Reserved
36-2.02 Materials
The base bond breaker must be one of the following: Base bond breaker no. Description 1 PG asphalt binder, Grade PG 64 -10 2 Curing compound no. 3 3 White opaque polyethylene film under ASTM C171 except the minimum thickness must be 6 mils 4 White curing paper under ASTM C171 5 Geosynthetic bond breaker
36-2.03 Construction
36-2.03A General
Before applying or placing a base bond breaker, remove foreign and loose materials from the base. Do not place a base bond breaker until the base has cured. Pave over the base bond breaker within 72 hours of placing it.
36-2.03B Applying and Placi ng Base Bond Breaker
Select a bond breaker to apply or place over the base material as shown in the following table: Base material Bond breaker no. LCB 1, 2, 5 Concrete base LCB rapid setting 3, 4, 5 RSC base CTPB Existing base Apply base bond breaker no. 1 in a single application at a uniform rate from 0.09 to 0.15 gal/sq yd over the entire surface of the base . Cure for at least 4 hours before paving. SECTION 36 GENERAL Mix base bond breaker no. 2 as specified for mixing curing compound for concrete. Apply t he bond breaker in 1 or more applications to achieve a coverage rate of at least 0.12 gal/sq yd over the entire surface of the base. Cure for at least 4 hours before paving. Place base bond breakers no. 3 and 4 without wrinkles. Overlap adjacent sheets a m inimum of 6 inches in the same direction as the concrete pour. Tape or bond the sheets together as needed to prevent the sheets from folding or wrinkling. Secure the bond breaker such that it remains in place during concrete placement. Ensure that no concr ete gets under the bond breaker. Place base bond breaker no. 5 without wrinkles. Overlap adjacent sheets a minimum of 8 inches in the same direction as the concrete pour. Overlap no more than 3 layers at any location. Secure the base bond breaker to the ba se with pins or nails punched through galvanized washers or discs from 2 to 2.75 inches in diameter. Place fasteners less than 3 feet apart along the edges and 6 feet apart elsewhere. If the bond breaker moves or wrinkles during concrete pavement placement , use more fasteners at a smaller spacing. Ensure that no concrete gets under the bond breaker.
36-2.04 Payment
The payment quantity for base bond breaker does not include the quantity used for overlaps.
36-3 Pavement Smoothness
36-3.01 General
36-3.01A Summary
Section 36 -3 includes specifications for measuring the smoothness of pavement surfaces.
36-3.01B Definitions
Area of Localized Roughness: Continuous moving average of the 25-foot International Roughness Index values for each wheel path using a 25-foot continuous interval and a 250-mm filter. Mean Roughness Index : 0.1-mile International Roughness Index values for the left and right wheel paths for the same traffic lane using a 250-mm filter. Profile Viewer and A nalyzer: An engineering software application that allows users to view and analyze pavement profiles . wheel paths: Pair of parallel lines 3 feet left and right of the center of a traffic lane. Left and right wheel paths are based on the direction of travel .
36-3.01C Submittals
36-3.01C(1) General
Reserved
36-3.01C(2) Inertial Profiler Data
At least 15 days before measuring pavement smoothness with an inertial profiler, register with the Department's secure file sharing system. To obtain information on th e registration process, send an e - mail with your contact information to asphalt.smoothness@dot.ca.gov for asphalt and concrete.smoothness@dot.ca.gov for concrete surfaces. Within 12 hours or on the same day of completing smoothness measurement, submit elec tronic copy of the raw profile data as a PPF file on an authorized data storage device, along with a coordinated video or images taken at intervals no greater than 52.8 feet for the existing and baseline profiles. Also, submit a hard copy or a PDF file lis ting the following:
1.Profile data collection time and date
2.Data collection software version used
4.Low-and high -pass filter used
5.0.1-mile MRI values Within 2 business days after each day of profiling, submit the profile i nformation to the Engineer and to the Department's secure file sharing system. After submitting the profile information to the Department 's SECTION 36 GENERAL file sharing system, send a notification of your electronic submittal to the Engineer and to the applicable e-mail address above with the names of the files submitted. For each surface subject to inertial profile smoothness requirements, the profile data information must include:
1.Raw profile data for each lane .
2.ProVAL ride quality analysis report for the MRI of ea ch lane in a PDF file. Report the following: 2.1. Listing of MRI values for 0.1 -mile segments or portions thereof 2.2. Input data including the specified MRI threshold and fixed segment length 2.3. Raw profile data name selections 2.4. Areas exempt from in ertial profile smoothness requirements
3.ProVAL ride quality analysis report for the IRI of the left and right wheel paths of each lane in a PDF file. Report the following: 3.1. Listing of ALR 3.2. Input data including the specified area of the localized roughness threshold and continuous segmen t length 3.3. Raw profile data name selections 3.4. Areas exempt from inertial profile smoothness
4.GPS data file for each lane. Submit the data file in GPS eXchange file format.
5.Manufacturer's recommended calibration and verification test results for the inertial profiler.
6.Inertial profiler's ca libration and verification test results, including results for bounce, block, and the distance measurement instrument.
7.Completed Pavement Smoothness Inertial Profiler Submittal Record form. Submit Asphalt Concrete Pavement Smoothness Corrections Inform ation form or Concrete Pavement Smoothness Corrections Information form with your final profile data information submittal. Submit the raw profile data in an unfiltered PPF file. Use the following file naming convention: YYYYMMDD_TTCCCRRR_EA_D_L_W_B_E_X_PT .EXT where: YYYY = year MM = month, leading zero DD = day of the month, leading zero TT = district, leading zero CCC = county, 2 -or 3-letter abbreviation as shown in section 1 -1.08 RRR = route number with no leading zeros EA = contract number, excluding the district identification number, expressed as 6 characters D = traffic direction, NB, SB, WB, or EB L = lane number from left to right in the direction of travel W = wheel path, L for left, R for right, or B for both B = beginning station to the nearest foot, such as 10+20 , or beginning postmile to the nearest hundredth, such as 25.06 with no leading zero E = ending station to the nearest foot, such as 14+20 , or ending postmile to the nearest hundredth, such as 28.06 with no leading zero X = profile operation, EXIST for existing pavement, BASELINE for existing pavement after performing repairs , PAVE for after paving, and FINAL for completed pavement documentation of compliance PT = project type profiled, such as Type A HMA , RHMA -G, OGFC , JPCP , CRCP , or Grind EXT = PPF for raw profile data file extension If you are submitting multiple inertial profiler data files, compress the files into a .ZIP file format and submit them using the file -naming convention TT_EA_X_YYYYMMDD.zip .
36-3.01C(3) Smoothness Corrective Grinding Plan
At least 2 business days before performing corrective grinding for areas that do not meet the smoothness requirements , submit a corrective grinding plan as an information al submittal. The corrective grinding plan must include: SECTION 36 GENERAL
2.Grinder wheelbase in feet, measured from the front centerline to the back centerline of the single wheel or tandem wheel spread
3.Grinder head position in feet, measured relative to the centerline of the front single wheel or the front tandem wheel spread
4.Tandem wheel spreads in feet
5.Tabular listing of the planned corrective grinding, including: 5.1. Begin and end locations in stationing to the nearest foot 5.2. Width of grind, such as left half lane, right half lane, or full -width lane 5.3. Corresponding grinder head depths to the nearest 0.01 inch 5.4. Direction of grind such as forward, reverse, forward -forward, reverse -reverse, forward -reverse, reverse -forward
6.Forecasted improvement in terms of the MRI and ALR values
36-3.01C(4) Straightedge Measurements
Within 2 business days of measuring smoothness with a straightedge, submit a list of the areas requiring smoothness correction or a report stating there are no areas requiring smoothness correction. Identify the areas requiring smoothness correction by:
2.District -County -Route
3.Beginning station or postmile to the nearest 0.01 mile
4.For correction areas within a traffic lane: 4.1. Lane direction, NB, SB, EB , or WB 4.2. Lane number from left to right in the direction of travel 4.3. Wheel path, L for left, R for right, or B for both
5.For correction areas not within a traffic lane: 5.1. Identify the pavement area, such as shoulder, weigh station, or turnout 5.2. Direction and distance from the centerline, L for left or R for right
6.Estimated size of correction area
36-3.01C(5) Smoothness Quality Control Plan
Submit a written smoothness quality control plan to the Engine er at or before preconstruction meeting, except the layout plan. Submit the layout plan as an addendum to the smoothness quality control plan no later than 3 days after the EXIST profile is collected. The plan must include:
1.Organization: Contact names, organizational chart, telephone numbers, current certifications and titles, and roles and responsibilities of personnel for monitoring smoothness, collecting profile data, submitting data, pay adjustment requests and reports, and implementing corrective ac tions.
2.Inertial profiler certification: 2.1. Inertial profiler certification issued by the Department 2.2. Operator certification for the inertial profiler issued by the Department 2.3. Manufacturer's instructions and test procedures for calibration and verification of the inertial profiler
3.Schedule: The methods and timing used for monitoring or testing ride quality or both throughout the placement operation process. Indicate the approximate timing of acceptance testing for the profile operations defi ned in section 36 -3.01C(6)(b) in relation to placement operations.
4.Layout plan: 4.1. Establish semipermanent reference points at the beginning and end of the project based on the plans. For each profile run, define additional semipermanent reference poi nts for the begin and end position of each run. Show the position and name of each semipermanent reference point. These reference points must be located outside of the traveled way , perpendicular to the beginning position of each lane. Where beginning positions are adjacent to each other but staggered, use separate beginning positions. Semipermanent reference points used to establish the beginning position of a profile run must be labeled in the field and in the pavement profiles using the following naming convention: XXX-D-L-STA-VAL SECTION 36 GENERAL where: XXX = Beg for the beginning of each profile run, End for the end of each profile run, ExB for the beginning point of the areas excluded from inertial profiler testing and ExE for the end point of the areas excluded from inertial profiler testing D = traffic direction, NB, SB, WB, or EB L = lane number from left to right in the direction of travel, such as 1, 2, or 3 STA = station to the nearest foot, such as 10+20 . Do not use postmiles VAL = use INC where the value of stationing in the PPF file will increase in the direction of travel. Use DEC where the absolute value of the stationing in the PPF file will decrease in the direction of travel Use the same label name regardless of the stage of the pro file. 4.2. For each semipermanent reference point, include a KMZ file with: 4.2.1 . Color photographs clearly displaying the physical label used to define the semipermanent reference points 4.2.2 . Listing of GPS coordinates Semipermanent reference points, wherever possible, must be recorded by inertial profilers using electronic eye readings of reflectors.
36-3.01C(6) Smoothness Payment Adjustment Request
36-3.01C(6)(a) General
Smoothness payment adjustment request must include a ProVAL project file and a payment adjustment spreadsheet for each lane.
36-3.01C(6)(b) ProVAL Project File
After completing final corrections, submit an electronic ProVAL project file for each lane using the same naming convention listed in section 36 -3.01C(2), except:
1.B = use the common beginning station found in all profiles included in the ProVAL project file followed by the postmile to the nearest tenth of a mile, such as 675+84 (12.83) for station 675+84 and post mile 12.83
2.E = use the ending station f ound in the FINAL profile followed by the postmile to the nearest tenth of a mile
4.EXT = PVP for ProVAL project file extension Use a single ProVAL project file for each lane. Each ProVAL project file must contain the PPF files from the pro file operation shown in the following table: Profiles Needed by Smoothness Table Profile HMA pavement constructed on existing pavements New HMA pavement alignment or new realignments Concrete pavement target 60/67.5/75 Grind concrete pavement percent improvement EXIST X -- -- X BASELINE X -- -- X PAVE X X X -- FINAL X X X X Establish and maintain stationing to allow for direct comparison of smoothness data between you and the Engineer in subsequent tests. The profiles must:
1.Align with each other in ProVAL.
2.Use the same beginning station position in all profile files and in a single ProVAL project file.
3.Use the same semipermanent reference points for the beginning and ending positions of each profile required by section 36 -3.01C(5). SECTION 36 GENERAL
4.For alignment purposes, the end station determined from the profiles distance measuring instrumentation of each sequentially numbered 0.1 -mile segment or portion thereof in the BASELINE , PAVE and FINAL profiles must be no greater than 20 feet in the first mile when compared to the same sequentially numbered segment end station in the EXIST profile. For locations more than 1 mile but less than 2.5 miles, the difference must be prorated from 20 feet to 50 feet. For locations more than 2.5 miles from the beginning position of the profile, the difference must be no greater than 50 feet. Where these differences create an additional sequentially numbered segment and when needed to bring the sequentially numbered segments back into alignment, the event de fining the ending position of the partial segment in the PPF file of the BASELINE , PAVE and FINAL profiles may be adjusted no more than 20 feet within the first 2.5 miles, and no more than 50 feet at all other locations. Include the same leave -out sections referenced to the same semipermanent reference points.
36-3.01C(6)(c) Payment Adjustment Spreadsheet
For each lane, submit payment adjustment spreadsheet using the Department -furnished worksheet. Data must be exported directly from the ProVAL project fi le Ride Quality module into the corresponding worksheet using the following settings:
1.Analysis Type set to Fixed Interval
2.Ride Quality Index set to MRI
3.Threshold using numeric value
4.Segment Length in feet set to 528.00 Obtain the worksheet from the following site: https://dot.ca.gov/programs/construction/pavement -smoothness When sequentially numbered segments are misaligned and adjustments are required as described in section 36 -3.01C(6)(b), make the adjustments within the ProVAL project file before exporting data to a worksheet and notify the Engineer.
36-3.01C(7) Inertial Profiler Verification Test
Within 2 business days after the annual cross -correlation testing, submit a ProVAL profiler certification analysis report for the te st results to the Engineer and to the e-mail address: smoothness@dot.ca.gov
36-3.01D Quality Assurance
36-3.01D(1) General
Reserved
36-3.01D(2) Certifications
The inertial profiler must display a current certification decal showing the expiration date. The operator must be certified for each model of inertial profiler operated. The certifications issued by the Department for the inertial profiler and operator must be current .
36-3.01D(3) Quality Control
36-3.01D(3)(a) General
Reserved
36-3.01D(3)(b) Smoothness Measurement
36-3.01D(3)(b)(i) General
Measure pavement smoothness using an inertial profiler . The following areas are excluded from MRI smoothness requirements but are subject to ALR:
1.Continuous pavement less than 1,000 feet in length
2.Ramps SECTION 36 GENERAL
4.Acceleration and deceleration lanes The following areas are excluded from smoothness measurement with an inertial profiler but are subject to the 12 -foot straightedge measurement:
1.Areas within 15 feet of manholes, weigh -in-motion, railroad crossing, ca ttle guards, bus pad, and transverse gutter pans
2.Sections of traffic lane immediately adjacent to edge of traveled way where the distance between edge of traveled way and the longitudinal gutter pan is less than or equal to 8 feet
3.Areas within 25 fee t of the beginning and 25 feet beyond the end of the intersection radius
4.Areas within 25 feet of the roundabout radius
6.Miscellaneous areas such as medians, gore areas, turnouts, and maintenance pullouts
7.Areas within 15 feet of the beg inning of an approach slab or bridge, and 40 feet beyond the end of a departure slab or bridge
8.Horizontal curves with a radius less than the following and within the superelevation transition of such curves: 8.1. 150 feet for asphalt pavements 8.2. 300 feet for concrete pavements
9.Pavement length less than 25 feet
10.Areas of HMA with a single opportunity within 20 feet of locations where localized roughness exceeds 160 inches per mile on the BASELINE profile after filtering the profile with the ProVA L Moving Average Low Pass filter with a 30 -foot short cutoff wavelength
11.HMA placed under concrete pavement Where measurement with inertial profiler is required:
1.Determine the pavement smoothness by obtaining the IRI for the left and right wheel pat hs on each traffic lane
2.Determine the MRI and ALR using ProVAL Where OGFC is required, test the pavement smoothness of the final asphalt or concrete pavement surface before and after placing OGFC.
36-3.01D(3)(b)(ii) Inertial Profiler Calibration and V erification Tests
Notify the Engineer at least 2 business days before performing calibration and verification testing of the inertial profiler. Conduct the following calibration and verification tests in the Engineer's presence each day before profiling:
1.Block test to verify the accuracy of the height sensor under California Test 387
2.Bounce test to verify the combined accuracy of the height sensor and accelerometer under California Test 387
3.Distance measurement instrument test to verify the accuracy of the distance measuring instrument under California Test 387
4.Manufacturer's recommended tests Conduct a cross -correlation verification test of the inertial profiler in the Engineer's presence before performing the initial profiling. A v erification test must be performed at least annually. Conduct 5 repeat ed runs of the inertial profiler on an authorized 0.1-mile test section. Calculate a cross -correlation to determine the repeatability of your device under California Test 387 using a Pro VAL profiler certification analysis with a 3 -foot maximum offset. The cross -correlation must be a minimum of 0.92.
36-3.01D(3)(b)(iii) Collecting and Analyzing Data
Operate the inertial profiler under the manufacturer's instructions . Collect profiling data under AASHTO R 57 at 1 -inch recording intervals using a minimum 4 -inch line laser sensor and analyze IRI using a 250 -mm filter. SECTION 36 GENERAL Establish semipermanent reference points for aligning inertial profiler runs and locating potential corrective gr inding. Maintain semipermanent reference points until Department acceptance testing is completed. While collecting the profile data to determine the IRI values, record semipermanent reference points at the beginning and end of the profile run and the begin ning and end of the following locations in the raw profile data:
3.Culverts visible on the roadway surface
7.Change in pavement type Profile the left a nd right wheel paths of each lane. Determine the MRI for 0.1 -mile fixed segments using the ProVAL ride quality analysis with a 250 -mm filter. Calculate the MRI of each lane. Segments less than 0.05 mile will not be evaluated for MRI but must comply with AL R requirement. Segments greater than or equal to 0.05 mile and less than or equal to 0.10 mile must comply with the MRI specifications for a 0.1 - mile segment. Pay adjustments for segments greater than or equal to 0.05 mile and less than or equal to 0.10 mile will be calculated based on a prorated length. Determine the ALR using ProVAL with the average IRI values for each wheel path using a 25 -foot continuous interval and a 250 -mm filter.
36-3.01D(4) Department Acceptance
36-3.01D(4)(a) General
The Departm ent accepts pavement surfaces for smoothness based on compliance with the smoothness specifications for the type of pavement surface specified. For areas that require pavement smoothness determined using a 12 -foot straightedge, the pavement surface must no t vary from the lower edge of the straightedge by more than:
1.0.01 foot when the straightedge is laid parallel with the traffic lane centerline
2.0.02 foot when the straightedge is laid perpendicular to the centerline and extends from edge to edge of a traffic lane
3.0.02 foot when the straightedge is laid within 24 feet of a pavement conform
36-3.01D(4)(b) Profile Verification
The Engineer may perform verification testing using the Department 's inertial profiler. The Engineer notifies you of the Department 's intention to perform verification testing. Your acceptance test results are considered acceptable and will be used for incentive and disincentive payments if your mean MRI is within 10 percent of the Department 's mean MRI obtained over the sam e selected project length. When your test results are not considered acceptable, the Department 's MRI values will be used in the calculation for incentive and disincentive payments for that evaluated length and the Department will have 15 days to complete an evaluation of both profiler certifications. You and the Engineer must work together to avoid potential conflicts and to resolve disputes regarding test result discrepancies. Notify the Engineer within 5 business days of receiving the verification test result if you will dispute it. An independent third party will perform referee testing over the same selected project length. Before the third party participates in a dispute resolution, their profiler and operator must be certified under the Department 's Profiler Certification Program. The independent third party must have no prior direct involvement with this Contract or no current direct involvement with you. The mean MRI value used in the calculation for incentive and disincentive payments will be from t he party whose mean MRI value is closer to the independent third party and the other party pays for the independent third party's testing.
36-3.02 Materials
Not Used SECTION 36 GENERAL
36-3.03 Construction
Notify the Engineer of the beginning location by station and start time at least 2 business days before each day of profiling. Before profiling, remove foreign objects from the pavement surface and mark the begin and end station on the pavement shoulder. The stationing must be the same when profiling more than 1 surface.
36-4 Residue Containing Lead From Paint and Thermoplastic
Reserved
36-5 36-15 Reserved
Source: California Standard Specifications, 2024 Edition. Pages 481–490 of 1,372.