52 REINFORCEMENT
52-1 General
52-1.01 General
52-1.01A Summary
Section 52 -1 includes general specifications for fabricating and placing reinforcement.
52-1.01B Definitions
affected zone: Any weld and the greater of 1 inch or 1 bar diameter adjacent to the weld, or portion of the reinforcing bar where any properties of the bar, including t he physical, metallurgical, or material characteristics, have been changed by either:
52-1.01C Submittals
52-1.01C(1) General
Reserved
52-1.01C(2) Shop Drawings
If a portion of an assemblage of bar reinforcing steel exceeds 20 feet in height and is not encased in concrete, submit shop drawings and design calculations for a temporary support system. Temporary support system shop drawings and calculations must be sealed and signed by an engineer who is registered as a civil engineer in the State. The temporary support system must be designed to:
52-1.01C(3) Certificates
Submit a certificate of compliance for each shipment of reinforcement. Submit the following:
52-1.01D Quality Assurance
Reserved
52-1.02 Materials
52-1.02A General
Reserved
52-1.02B Bar Reinforcement
Reinforcing bars must be deformed bars complying with ASTM A706/A706M, Grade 60, except you may use:
52-1.02C Welded Wire Reinforcement
Welded wire reinforcement must comply with ASTM A1064/A1064M. SECTION 52 REINFORCEMENT
52-1.02D Reinforcing Wire
Reinforcing wire must comply with the specifications for plain wire in ASTM A1064/A1064M.
52-1.02E Dowels
52-1.02E(1) General
Reinforcing steel dowels must be deformed bars complying with section 52 -1.02B. Threaded rods used as dowels must comply with sect ion 75 -1.02A.
52-1.02E(2) Dowels for Drill and Bond Dowel —Chemical Adhesive
Dowels for drill and bond dowel chemical -adhesive systems must be one of the following:
52-1.03 Construction
52-1.03A General
Reserved
52-1.03B Cleaning
Before concrete is placed, the reinforcement to be embedded must be free of mortar, oil, dirt, excessive mill scale and scabby rust, and other coatings that would destroy or reduce the bond.
52-1.03C Bending
Do not bend or straighten bars in a way that da mages the material. Do not use bars with kinks or improper bends. Hooks and bends must comply with the Building Code Requirements for Structural Concrete published by ACI.
52-1.03D Placing
Firmly and securely hold reinforcement in position by:
52-1.04 Payment
The payment quantity of bar reinforcing steel is the calculated weight of the reinforcing bars and wire. The payment quantity of bar reinforcing steel includes the lap of bars for lap splicing, including locations where you use a continuous bar instead of the splice shown. The payment quantities are based on the following: Bar Reinforcing Steel Quantities Deformed bar designation no. Weight (pounds per foot) Nominal diameter (inches) 3 0.376 0.375 4 0.668 0.500 5 1.043 0.625 6 1.502 0.750 7 2.044 0.875 8 2.670 1.000 9 3.400 1.128 10 4.303 1.270 11 5.313 1.410 14 7.650 1.693 18 13.600 2.257 NOTE: Bar numbers approximate the number of eighths of an inch included in the nominal diameter of the bars. The nominal diameter of a deformed bar is equal to the diameter of a plain round bar having the same weight per linear foot as the deformed bar. The cross -sectional area of reinforcing wire, in hundredths of square inches, is equal to its W -size number. The density of reinforcing wire is 0.2833 lb/cu in. The payment quantity of welded wire reinforcement is determined based on the measured area covered by the reinforcement and does not include laps. SECTION 52 REINFORCEMENT The payment quantity for bar reinforcing steel (bridge) includes diaphragm dowels and bolts in PC concrete members. If alternative transverse deck reinforcement placement details are sho wn, the payment quantities are based on the detail that shows truss bars. Bar reinforcing steel involved in bridge work is paid for as bar reinforcing steel (bridge) or bar reinforcing steel (epoxy coated)(bridge) unless it is included in a separate bid it em.
52-2 Epoxy -Coated Reinforcement and Epoxy -Coated Prefabricated
52-2.01 General
52-2.01A General
52-2.01A(1) Summary
Section 52 -2.01 includes general specifications for fabricating and placing epoxy -coated reinforcement and epoxy -coate d prefabricated reinforcement. The substitution of welded wire reinforcement for bar reinforcement specified in 52 -1.02B is not allowed for epoxy -coated bar reinforcement or epoxy -coated prefabricated bar reinfor cement.
52-2.01A(2) Definitions
Reserved
52-2.01A(3) Submittals
52-2.01A(3)(a) General
Reserved
52-2.01A(3)(b) Samples
52-2.01A(3)(b)(i) General
Reserved
52-2.01A(3)(b)(ii) Patching Material Test Samples
Submit a test sample, from each batch of patching material to be used to repair epoxy coating on reinforcement, to METS. Each test sample must be:
52-2.01A(3)(b)(i ii) Test Sam ples
Submit test samples of epoxy -coated reinforcement and epoxy -coated prefabricated reinforcement to METS.
52-2.01A(4) Quality Assurance
Reserved
52-2.01B Materials
Except for field welding of butt splices, complete welding of the reinforcement before epoxy coating. If a part of a bar or wire is described to be epoxy coated, coat the entire bar unless the bar or wire is spliced outside the limits of epoxy coating, in which case epoxy coating is not required on the part of the bar or wire beyond the spli ce. Do not store reinforcement within 1,000 feet of ocean or tidal water for more than 2 months. Patching material and the patching process must be suitable for field application. Epoxy powder must be on the Authorized Material List for fusion bonded epoxy powders. SECTION 52 REINFORCEMENT Corrosion protection covering for splices must be on the Authorized Material List for corrosion protection coverings.
52-2.01C Construction
Except for lap splices, cover splices of reinforcement with a corrosion protection covering. Install cov ering under the manufacturer 's instructions.
52-2.01D Payment
The weight of epoxy coating is not included in the weight of reinforcement. Bar or wire reinforcement extending beyond the limits for epoxy -coated reinforcement shown is paid for as bar reinforcing steel (bridge).
52-2.02 Epoxy -Coated Reinforcement
52-2.02A General
52-2.02A(1) Summary
Section 52 -2.02 includes specifications for fabricating and placing epoxy -coated reinforcement. In a freeze -thaw area, epoxy coat the following:
52-2.02A(2) Definitions
Reserved
52-2.02A(3) Submittals
52-2.02A(3)(a) General
Reserved
52-2.02A(3)(b) Test Samples
For each shipment of epoxy -coated reinforc ement to the job site or PC plant, submit two 30 -inch-long test samples from each size of reinforcement. Before transporting test samples:
52-2.02A(3)(c) Certificates
Submit a certificate of compliance for each shipment of epoxy -coated reinforcement. Include the following with the submittal:
52-2.02A(4) Quality Assurance
52-2.02A(4)(a) General
Perform qualification testing and certifications required by ASTM A775/A775M and ASTM A884/A884M at an authorized laboratory .
52-2.02A(4)(b) Department Acceptance
Test samples must comply with the requirements for coating thickness specified in ASTM A775/A775M for bar reinforcement or ASTM A884/A884M Class A, Type 1 for wire reinforcement, as follows:
52-2.02B Materials
Epoxy -coated reinforcement must comply with:
52-2.02C Construction
If damage to the coating occurs during field bending, patch the area immediately. Job site and PC plant practices must comply with sections X1.3.1 through X1.3.15 of appendix X1 of ASTM A884/A884M for wire reinforcement, except replace should with must .
52-2.02D Payment
Not Used
52-2.03 Epoxy -Coated Prefabricated Reinforcement
52-2.03A General
52-2.03A(1) Summary
Section 52 -2.03 includes specifications for fabricating and placing epoxy -coated prefabricated reinforcement.
52-2.03A(2) Def initions
Reserved
52-2.03A(3) Submittals
52-2.03A(3)(a) General
Reserved
52-2.03A(3)(b) Test Samples
For each shipment of epoxy -coated prefabricated reinforcement to the job site or PC plant, submit two 30 - inch-long test samples from each size of reinfo rcement. Before transporting test samples: SECTION 52 REINFORCEMENT
52-2.03A(3)(c) Certificates
Submit a certificate of compliance for each shipment of epoxy -coated reinforcement. Include with the submittal:
52-2.03A(4) Quality Assurance
52-2.03A(4)(a) General
Perform qualification testing and certification required by ASTM A934/A934M and ASTM A884/A884M at an authorized laboratory.
52-2.03A(4)(b) Department Acceptance
Test samples must comply with the requirements for coating thickness specified in ASTM A934/A934M for bar reinforcement or ASTM A884/A884M Class A, Type 2 for wire reinforcement, as follows:
52-2.03B Materials
Epoxy -coated prefabricated reinforcement must comply with:
52-2.03C Construction
Do not bend epoxy -coated prefabricated bar or wire reinforcement after coating application. Job site and PC plant practices must comply with sections X2.3.1 through X2.3.15 of appendix X2 of ASTM A934/A934M for bar reinforcement, except replace should with must .
52-2.03D Payment
Not Used
52-3 Galvanized Bar Reinforcement
52-3.01 General
Section 52 -3 includes specifications for fabricating and placing galvanized bar reinforcement.
52-3.02 Materials
Galvanize bar r einforcement under ASTM A767/A767M, Class 1, except chromating is not required. SECTION 52 REINFORCEMENT
52-3.03 Construction
Job site and PC plant practices must comply with sections X1.3.1 through X1.3.12 of appendix X1 of ASTM A767/A767M for bar reinforcement, except replace should with must .
52-3.04 Payment
Not Used
52-4 Reserved
52-5 Headed Bar Reinforcement
52-5.01 Gene Ral
52-5.01A Summary
Section 52 -5 includes specifications for fabricating headed bar reinforcement.
52-5.01B Definitions
lot: 150 count, or fraction thereof, of headed bar reinforcement fo r each:
52-5.01C Submittals
52-5.01C(1) General
If any part of the head is fabricated in the field, submit a prequalification report as specified under section
52-6 01C(6)(c).
52-5.01C(2) Samples
52-5.01C(2)(a) General
Rese rved
52-5.01C(2)(b) Test Samp les
Submit test samples to METS. Include copies of the certificates of compliance with the test samples.
52-5.01C(3) Test Reports
Submit a QC test report for each lot. Each test report must include:
52-5.01C(4) Certifi cates
Submit a certificate of compliance for each shipment of headed bar reinforcement. Include with the submittal copies of:
52-5.01D Quality Assura nce
52-5.01D(1) General
Section 11 -2 does not apply to headed bar reinforcement.
52-5.01D(2) Qualifications
If any part of the head is fabricated in the field, the operator and procedure must be prequalified as specified for service and ultimate butt spl ices under section 52 -6.01D(2). Welding, welder qualifications, and inspection of welding must comply with AWS C6.1.
52-5.01D(3) Test Samples
After completing fabrication of a lot of headed bar reinforcement, including preparation for any required epoxy coating, notify the Engineer that the lot is ready for testing. After receiving notification that lots are ready for QC testing, the Engineer randomly selects department acceptance test samples and places tamper -proof markings or seals on the test sa mples. Test samples must be removed from:
52-5.01D(4) Quality Control
52-5.01D(4)(a) General
Maintain a daily production log for t he fabrication of headed bar reinforcement for each production lot. The log must include:
52-5.01D(4)(b) Quality Control Testing
A QC test must consist of tensile testing 4 headed bar reinforcement test samples selected from each lot of completed headed bar reinforcement before shipping th e lot to the job site or PC plant. Headed bar reinforcement test samples are tested for necking under Necking Option I as specified in CT 670 and tensile tested:
52-5.01D(4)(c) Quality Control Test Report
The quality control test report must be (1) prepared by the laboratory performing the testing and (2) signed by an engineer representing the laboratory. The engineer must be registered as a civil engineer in the State.
52-5.01D(5) Department Acceptance
The Department tests headed bar reinforcement as specified for QC testing in section 52 -5.01D(4)(b). The Department will notify you of the Department accep tance test results for each bundle of 4 test samples of splices within 3 business days after METS receives the bundle unless more than 1 bundle is received on the same day, in which case allow 2 additional business days for each additional bundle received.
52-5.02 Materials
Headed bar reinforcement must comply with ASTM A970/A970M. At fracture, headed bar reinforcement must comply with:
52-5.03 Construction
Reserved
52-5.04 Payment
The payment quantity for headed bar reinforcement is the quantity of heads. Reinforcing bar used for headed bar reinforcement is paid for as bar reinforcing steel. The length of bar used in calculating the weight of reinforcing bar is the entire length of the completed headed bar including the head thickness.
52-6 Splicing
52-6.01 General
52-6.01A Summary
Reinforcing bar splices consist of lap splices, service splices, or ultimate butt splices.
52-6.01B Definitions
Reserved
52-6.01C Submittals
52-6.01C(1) General
52-6.01C(2) Product Data
52-6.01C(2)(a) General
Rese rved
52-6.01C(2)(b) Radiographic Film Developing Process Records
If requested, submit records of radiographic film developing processes and any chemical changes to the developing processes.
52-6.01C(3) Samples
52-6.01C(3)(a) General
Rese rved
52-6.01C(3)(b) Test Samples
Submit service splice and ultimate butt splice test samples to METS. Include copies of the certificates of compliance with the test samples for mechanical splices and resistance -butt-welded splices.
52-6.01C(4) Test Reports
52-6.01C(4)(a) General
Reserved
52-6.01C(4)(b) Splicing Quality Control Test Report
Submit a QC test report for each lot of service splices and ultimate but t splices. Each QC test report must include:
52-6.01C(4)(c) Splice Rejection Mitigation Report
For a rejected lot of service splices or ultimate butt splices, submit a splice rejection mitigation report. Allow 3 business days for the Engineer's review.
52-6.01C(5) Certificates
Submit a certificate of compliance for each shipment of service splice or ultimate butt splice material. Include with the submittal:
52-6.01C(6) Qualification Statements
52-6.01C(6)(a) General
Reserved
52-6.01C(6)(b) Welder and Welding Procedures Qualifications
Submit welder and welding procedure qualifications as an informational submittal.
52-6.01C(6)(c) Splice Prequalification Report
For each bar size of each coupler model type of service splice or ultimate butt splice to be used in the work, submit a splice prequalification report that includes:
52-6.01C(6)( d) Weld Flash Removal Process
If specified, submit a proposed weld flash removal process. The submittal must show that the process produces a smooth profile that can be successfully epoxy coated under section 52 -2.
52-6.01D Quality Assurance
52-6.01D(1) General
Assign a splicing QC manager. Before starting service or ultimate butt splicing activities, select the lots that constitute each group for QA testing. Before testing resistance -butt-welded splice test samples of reinforcement to be epoxy coated, remove the weld flash using the authorized process for flash removal. SECTION 52 REINFORCEMENT Section 11-2 does not apply to resistance -butt-welded splices.
52-6.01D(2) Qualifications
52-6.01D(2)(a) General
Reserved
52-6.01D(2)(b) Operator and Procedure Prequalification
Before performing any service or ultimate butt splicing, obtain certifications from the fabricator for prequalification of the operators and the procedures to be used in the work. Each operator must p repare 4 prequalification splice test samples for each bar size of each splice coupler model type and position to be used. Splice test samples for operator and procedure prequalification must have been prepared and tested no more than 2 years before the su bmittal of the splice prequalification report. Splice test samples and testing must comply with the QC testing requirements specified in section 52 - 6.01D( 4)(b) for the type of splice to be used in the work.
52-6.01D(2)(c) Welder and Welding Procedure Qual ifications
Before performing any CJP butt welds, qualify welders and welding procedures under AWS D1.4. Qualify welders and welding procedures on splice test samples of the type to be used in the work.
52-6.01D(3) Test Samples
52-6.01D(3)(a) General
Prepare splice test samples under California Test 670. For splicing new reinforcement to existing reinforcement, make splice test samples using only reinforcement having the deformation pattern of the new reinforcement. Before transporting splice t est samples to an authorized laboratory and METS:
52-6.01D(3)(b) Ultimate Butt Splice
After completing the ultimate butt splices in a lot, including any required epoxy coating, notify the Engineer that the splices are ready for testing. The Engineer selects splice test samples at the job site or PC plant. For hoops, the Engineer selects splice test samples from the completed lot at the job site, PC plant, or fabrication plant. After being notified, the Engineer randomly selects t he 4 splice test samples to be removed and places tamper -proof markings or seals on the test samples. A test sample is rejected if the tamper -proof marking or seal is disturbed before testing. SECTION 52 REINFORCEMENT
52-6.01D(4) Quality Control
52-6.01D(4)(a) General
Reserved
52-6.01D(4)(b) Quality Control Testing
52-6.01D(4)(b)(i) General
QC testing includes total slip testing, service splice testing, and ultimate butt splice testing. Test QC splice test samples:
52-6.01D(4)(b)(ii) Total Slip Testing
Except for mechanical lap, welded, or hoop splices, test 1 of th e 4 splice test samples for total slip. If the splice test sample exceeds the total slip value specified in section 52 -6.02B(1), test the 3 remaining test samples for total slip. If any of the 3 remaining test samples exceed the specified total slip value, the Department rejects all splices in the lot.
52-6.01D(4)(b)(iii) Service Splice Testing
A service splice test consists of preparing and testing 4 splice test samples for each lot of completed splices. Prepare the test samples using the same splice mate rial, position, operators, location, equipment, and procedures to be used in the work. Splice test samples must comply with the requirements specified in section 52 -6.02B(2) as follows:
52-6.01D(4)(b)(iv) Ultimate Butt Splice Testing
An ultimate butt splice test consists of removing and testing 4 splice test samples from each lot of completed splices. At fracture, splice test samples must comply with the requirements specified in section 52 -6.02B(3) as follows:
52-6.01D(4)(c) Weld Flash Removal Process
Removal of the weld flash must produce a smooth profile free of any sharp edges that would prevent proper coating of the reinforcement such that:
52-6.01D(4)(d) Splicing Quality Control Test Report
The splicing quality control test report must be (1) prepared by the laboratory performing the testing and
52-6.01D(5) Department Acceptance
The Department tests and accepts service splic es and ultimate butt splices as specified for QC testing in section 52 -6.01D(4). If a Department acceptance test result does not comply with the material and QA requirements, the Department rejects all splices in the lot and the group. For the other lots i n the rejected group that pass QC testing, you may request the Engineer to perform additional Department acceptance testing for additional splice samples. If a Department acceptance splice test result complies with the material and QA requirements, the Dep artment accepts all splices in that lot. If a lot of splices is rejected, prepare a splice rejection mitigation report for that rejected lot as specified in section 52 -6.01D(4)(b)(i). If the QC and the Department acceptance test results have different comp liance determinations, the Department will sample and test all subsequent lots until QC and the Department acceptance test compliance determinations are consistent for 2 consecutive lots before r esuming sampling and testing of 1 lot from every group. The D epartment will notify you of the Department acceptance test results for each bundle of 4 test samples of splices within 3 business days after METS receives the bundle unless more than 1 bundle is received on the same day, in which case allow 2 additional b usiness days for each additional bundle received.
52-6.02 Materials
52-6.02A General
Reserved
52-6.02B Service Splices and Ultimate Butt Splices
52-6.02B(1) General
Section 52 -1.02B applies if service splices or ultimate butt splices are used in the work. The total slip must not exceed the values shown in the following table when tested under California Test 670: SECTION 52 REINFORCEMENT Total Slip Reinforcing bar no. Total slip (inch) 4 0.020 5 0.020 6 0.020 7 0.028 8 0.028 9 0.028 10 0.036 11 0.036 14 0.048 18 0.060 Mechanical couplers must be on the Authorized Material List for steel reinforcing couplers. Resistance welding fabricators must be on the Authorized Material List for resistance welding fabricators .
52-6.02B(2) Service Splices
Service splices must develop a minimum tensile strength of 80,000 psi.
52-6.02B(3) Ultimate Butt Splices
Ultimate butt splice test samples must demonstrate necking as either of the following:
52-6.03 Construction
52-6.03A General
Butt-welded or mechanical splices not shown as requiring a service splice or an ultimate butt splice must comply with the specifications for service splices. Do not p lace splices at a location shown as a no -splice zone. Reinforcing bars may be continuous where splices are shown. If splice locations are not shown, determine splice locations using commercial lengths where practicable. Unless another option is shown, stag ger splices in adjacent reinforcing steel. The minimum distance between staggered lap splices or staggered mechanical lap splices must be the same as the length specified for a lap splice in the largest bar. The minimum distance between staggered butt spli ces must be 2 feet measured between the splice midpoints along a line centered between the axi s of the adjacent bars. For reinforcing bars where splice test samples were removed, replace either of the following:
52-6.03B Lap Splicing
Splices made by lapping must consist of placing reinforcing bars in contact and wiring them together while maintaining the alignment of the bars and the minimum clearances. Do not splice the following by lapping:
52-6.03C Service Splices and Ultimate Butt Splices
52-6.03C(1) General
Service splices and ultimate butt splices must be one of the following:
52-6.03C(2) Mechanical Splices
Perform service splicing and ultimate butt splicing of mechanical splices:
52-6.03C(3) Resistance -Butt-Welded Splices
If resistance -butt-welded bar reinforcement is to be epoxy coated, remove the weld flash using the authorized process for flash removal. SECTION 52 REINFORCEMENT
52-6.03C(4) Complete -Joint-Penetration Butt -Welded Splices
CJP butt -welded splices must comply with AWS D1.4. Use only the joint details and dimensions shown in Figure 3.2 of AWS D1.4 except do not use the Single - V-Groove Weld with Split Pipe Backing detail. Make butt welds with multiple w eld passes without an appreciable weaving motion using a stringer bead having a width at most 2.5 times the diameter of the electrode when using shielded metal arc welding. Remove slag between each weld pass. Weld reinforcement must not exceed 0.16 inch in convexity. Electrodes for welding must have a minimum CVN impact value of 20 ft -lb at 0 degrees F. For welding of bars complying with ASTM A 615/A 615M, Grade 40 or 60, the requirements of Table 7.2 of AWS D1.4 are superseded by the following: The minimum preheat and interpass temperatures must be 400 degrees F for Grade 40 bars and 600 degrees F for Grade 60 bars. Immediately after completing the welding, cover at least 6 inches of the bar on each side of the splice with insulated wrapping to control the rate of cooling. The insulated wrapping must remain in place until the bar has cooled below 200 degrees F. If welding different grades of reinforcing bars:
52-6.04 Payment
Not Used
52-7 Stray Current Protection
52-7.01 General
52-7.01A Summary
Section 52 -7 includes specifications for installing stray current protection. Stray current protection consists of one or a combination of the following:
52-7.01B Definitions
Reserved
52-7.01C Submittals
Reserved SECTION 52 REINFORCEMENT
52-7.01D Qual ity Assurance
52-7.01D(1) General
Reserved
52-7.01D(2) Prestressing Tendon Connection
Welding operators must be prequalified by satisfactorily completing a field qualification test weld. The operator must make qualification test welds in the presence of the Engineer using:
52-7.01D(3) 52-7.01D(5) Reserved
52-7.02 Materials
52-7.02A General
Reserved
52-7.02B Prestressing Tendon Connection
For prestressing tendon connections, the no. 6 steel wire must comply with ASTM A1064, A510, or A510M.
52-7.02C B ar Reinforcing Steel Connection
Reserved
52-7.02D Copper Cable to Bar Reinforcing Steel Connection
Materials for exothermic welding the copper cable to bar reinforcing steel connections must comply with the manufacturer's instructions for the following:
52-7.02E Pile and Concrete Epoxy Insulation
For pile and concrete epoxy insulation, epoxy must be:
52-7.02F Concrete Insulation Course
Concrete insulation course must comply with section 51 and contain at least 590 pounds of cementitious material per cubic yard of concrete.
52-7.02G Neoprene Sheet Insulation
Fabricate neoprene sheet in sulation from sheet neoprene complying with the specifications for neoprene in section 51 -2.04. The sheet must be at least 1/8 inch thick.
52-7.02H Joint Sealant Insulation
The joint sealant insulation must be a single -component, non -sag polyurethane seal ant complying with ASTM C 920. SECTION 52 REINFORCEMENT The primer and backing rod must comply with the joint sealant manufacturer's instructions.
52-7.02I Membrane Insulation
Membrane insulation must comply with the specifications for dampproofing or preformed membrane waterproo fing in section 54.
52-7.02J Mortar Block Insulation
Mortar block insulation must contain at least 760 pounds of cementitious material per cubic yard. The blocks must be dense, homogeneous, and watertight.
52-7.02K Epoxy -Coated Reinforcing Steel Insulati on
Epoxy -coated reinforcing steel insulation must comply with section 52 -2. If a coupling nut is used at an attachment between an approach slab and an abutment, the nut must be epoxy coated either before or after fabrication.
52-7.02L Plastic End Cover In sulators
The plastic end cover insulators must be of the type commercially available to protect workers from protruding reinforcing bars. Bond the covers to the reinforcing bars with commercially available epoxy that is compatible with the plastic covers.
52-7.02M Pipe Wrapping Tape Insulation
For pipe wrapping tape insulation, the tape must be pressure -sensitive PVC or polyethylene tape with a nominal thickness of 20 mils. Use a primer as instructed by the manufacturer of the tape.
52-7.02N Epoxy for Ins ulation of Embedded Metal Materials
For insulation of embedded metal materials, epoxy must be:
52-7.03 Construction
52-7.03A General
Reserved
52-7.03B Prestressing Tendon Connection
Do not perform welding on the prestressing anchorage devices. Do not perform arc welding on the prestressing strand. Connect the collector wire to the prestressing strand by gas welding. Do not gas weld until the tendons are grouted and have cured for at least 24 hours. You may join 2 wire pigtail ends by gas welding at any stage of the work. Oxyacetylene welding must comply with the best standards of the industry. Use gas welding rods complying with Class RG45 (steel rods).
52-7.03C Bar Reinforcing Steel Connection
Weld bars and splices by the manual shielded metal -arc process before installing any prestressing strands. Use low -hydrogen electrodes complying with the specifications for E7016 electrodes in AWS A5.1/A5.1M .
52-7.03D Copper Cable to Bar Reinforcing Steel Connection
Fusion weld the copper cable to the bar reinforcing steel by an exothermic type welding process. SECTION 52 REINFORCEMENT Apply commercially available rubber splicing compound to the welded connection. Apply 2 layers of tape, e ach half lapped.
52-7.03E Pile and Concrete Epoxy Insulation
Abrasive blast clean concrete surfaces on which epoxy insulation is to be applied to the extent that clean aggregate is exposed. Apply the epoxy by brush or other means that will completely and uniformly cover the surfaces. Remove lifting anchors as specified for their removal in a corrosive environment in section 49 -2.04B(2).
52-7.03F Concrete Insulation Course
Excavate and backfill for concrete insulation course under section 19 -3. The joint b etween the concrete insulation course and the footing must comply with the specifications for horizontal construction joints in section 51 -1.03D(4), except abrasive blast cleaning is not required.
52-7.03G Neoprene Sheet Insulation
For neoprene sheet insu lation, lap each successive sheet securely to the preceding sheet by at least 6 inches.
52-7.03H Joint Sealant Insulation
Abrasive blast clean and prime concrete surfaces to receive joint sealant insulation.
52-7.03I Membrane Insulation
The exposed surfa ces of membrane insulation must be of uniform height above ground without unsightly bulges, depressions, or other imperfections. Membrane insulation must comply with the specifications for dampproofing or preformed membrane waterproofing in section 54.
52-7.03J Mortar Block Insulation
Reserved
52-7.03K Epoxy -Coated Reinforcing Steel Insulation
For a coupling nut which is epoxy coated after fabrication, apply the epoxy by brush or other means that will completely and uniformly cover the surfaces in cont act with concrete.
52-7.03L Plastic End Cover Insulators
Use enough epoxy to ensure that no voids exist between the plastic end cover insulators and the reinforcing bars.
52-7.03M Pipe Wrapping Tape Insulation
For pipe wrapping tape insulation, apply 1 l ayer of tape half lapped.
52-7.03N Epoxy for Insulation of Embedded Metal Materials
For embedded metals insulated with epoxy:
52-7.04 Payment
Not Used