6 CONTROL OF MATERIALS
6-1 General
6-1.01 General
Section 6 includes specifications related to the control of materials . Store materials and samples in a way that preserves the quality and facilitates prompt inspection. Material incorporated into the work must be new . Before the preconstruction conference, submit mate rial source information on a Notice of Materials to be Used form.
6-1.02 Department -Furnished Materials
Request Department -furnished materials except sign panels at least 15 days before their scheduled installation. Request sign panels at least 30 days before their scheduled installation. If the Department furnishes the material:
6-1.03 Local Materials
6-1.03A General
Local material must be rock, sand, gravel, earth, or mineral material other than local borrow, or selected material obtained or produced from a source in the work vicinity, specifically for use on the project. Local borrow must not be a material from an esta blished commercial source. Upon your request, the Department tests material for quality characteristics from an untested local source. If satisfactory material from that source is used in the work, the Department does not charge you for the tests; otherwise, the Department deducts the test costs.
6-1.03B Submittal s
Reserved
6-1.04 Buy America
6-1.04A General
Reserved
6-1.04B Crumb Rubber (Pub Res Code § 42703(d))
Furnish crumb rubber with a certificate of compliance. Crumb rubber must be:
6-1.04C Steel and Iron Materials
Steel and iron materials must be melted and manufactured in the United States except:
6-1.05 Specific Brand Or Trade Name and S Ubstitution
A reference to a specific brand or trade name establishes a quality standard and is not intended to limit competition. You may use a product that is equal to or better than the specified brand or trade name if authorized. Submit a substitution request with a time period that:
6-1.06 Buy Clean California Act
6-1.06A Summary
For projects with a total bid over $1 million and 175 or more original working days, the materials or products shown in the following table are subject to the Buy Clean Calif ornia Act (Pub Cont Code § 3500 et seq. ): Material or product Material specifications Carbon steel rebara Section 52 -1.02B, "Bar Reinforcement" and Section 99, "Building Construction." Includes uncoated or ungalvanized bar reinforcement used in epoxy -coated or galvanized reinforcement application s. Structural steelb Section 55 -1.02D(1), "General," – Structural Steel and Other Materials tables , Section 56 -2.02B(1), "General," Section 56 - 2.02F, "P ipe Posts," and Section 99, "Building Construction." For hot -rolled, plate or hollow materials. Flat glassc Section 99, "Building Construction" Mineral wool board insulationd Section 99, "Building Construction" aFor each mill providing 20,000 pounds or more on the project . bFor each mill providing 5,000 pounds or more on the project . cFor each manufacturer providing 2,000 square feet or more on the project . dFor each manufacturer providing 4,000 square feet or more on the project . An informal -bid contract is not subject to Buy Clean California Act requirements. For carbon steel rebar and structural steel materials subject to Buy Clean California Act, the source mill s must be on the Authorized Material List s for Buy Clean California Act compliant steel mills. Identify source mills on Notice of Materials to be Used form submittals. For flat glass and mineral wool board insulation subject to Buy Clean California Act, submit an environmental product declaration for each applicable material or product at least 15 days before the scheduled installation. The global warming potential of each applicable material or product as evidenced by its environmental product declaration must not exceed the maximum acceptable global warming potential values established by the Department of General Services. Do not install the applicable material or product until the submittal has been authorized. The maximum acceptable global warming potential for each category of material or product is published on the Depar tment of General Services website at: SECTION 6 CONTROL OF MATERIALS https://www.dgs.ca.gov / For product category rules for flat glass or mineral wool board insulation , go to the METS website. Use the product category rule in effect on the date of bid opening unless otherwise authorize d. An environmental product declaration for flat glass or mineral wool board is not required for either of the following conditions:
6-1.06B Definitions
environmental product declaration : Independently verified document created and verified under International Organization for Standardization (ISO) 14025 for Type III environmental declarations that identifies the global warming potential emissions of the facility -specific material or product through a product stage life cycle assessment . product category rule: Program operator established rule based on the science of life cycle assessment that gov erns the development of the environmental product declaration for the material or product. product stage: Boundary of the environmental product declaration that includes (1) raw material supply,
6-1.06C Submittals
You must register on the Department’s Data Interchange for Materials Engineering at least 15 days before submitting either of the following:
6-1.06D Quality Assurance
Reserved
6-1.07 Prohibitions On Materials, Equipment, and Services
6-1.07A General
Reserved
6-1.07B Telecommunications and Video Surveillance Equipment or Services
Do not enter into, extend, or renew a contract to procure or obtain telecommunications and video surveillance equipment or services as described in 2 CFR 200.216 and 2 CFR 200.471. Furnish telecommunications and video surveillance equipment with a certificate of compliance. The certifi cate must state telecommunications and video surveillance equipment was not procured or obtained from manufacturers identified in section 889 of the National Defense Authorization Act for Fiscal Year 2019 (Pub. L. 115 -232).
6-1.07C 6-1.07G Reserved
6-2 Quality Assurance
6-2.01 General
6-2.01A General
Quality assurance includes all activities used to (1) provide an overall level of quality for the project and
6-2.01B Authorized Facility Audit Lists
Section 6 -2.01B applies where a facility is specified to be on an Authorized Facility Audit List . SECTION 6 CONTROL OF MATERIALS An audit authorized by the Department not more than 3 years before completion of the fabrication process is acceptable if the Departmen t determines the audit was for the same type of work to be performed. For procedures to be included on an Authorized Facility Audit List, go to the Authorized Facility Audit List website .
6-2.01C Authorized Material Lists
Section 6 -2.01C applies where a m aterial is specified to be on an Authorized Material List . The material must be on an Authorized Material List before it is incorporated into the work. For procedures to be included on an Authorized Material List, go to the Authorized Material List website .
6-2.01D Authorized Material Source Lists
Section 6 -2.01D applies where a material is specified to be on an Authorized Material Source List . The material source must be on an Author ized Material Source List before the item from the source is incorporated into the work. For procedures to be included on an Authorized Material Source List, go to the Authorized Material Source List website .
6-2.01E Material Source Inspection and Testing
Section 6 -2.01E applies if a material is to be inspected or tested at the source . Submit an inspection request form:
6-2.01F Test Samples
Section 6 -2.01F applies where a test sample is specified or if a test sample is requested. Notify the Engineer 10 days before taking a sample. Submit material to be tested with a Sample Identification Card. For the card, go to the METS website . Restore work immediately after sampling. If requested, obtain the Department's authorization for the material before incorporating the material represented by the test sample into the work.
6-2.01G 6-2.01K Reserved
6-2.02 Quality Control
6-2.02A General
Material production and testing equipment must measure accurately and precisely. SECTION 6 CONTROL OF MATERIALS
6-2.02B Quality Control Program
Develop, implement, and maintain a QC program. Prepare and maintain QC records, including:
6-2.02C Quality Control Manager
The QC manager must be responsible directly to you for the quality of the work, including materials and workmanship performed by you and your subcontractors. Assign the QC manager before the start of the affe cted work. The QC manager must be the sole individual responsible for:
6-2.02D Quality Control Plans
Submit 7 copies of each authorized QC plan. Make 1 copy available at each location where work is performed.
6-2.03 Department Acceptance
6-2.03A General
The Department may use multiple acceptance methods for a material. Specifications in sections titled "Department Acceptance" do not include all requirements on which the Department makes its acc eptance. The Department may inspect, sample, and test materials for compliance with the Contract at any time. Allow the Department to record, including photograph and video, to ensure a material is produced to comply with the Contract. You may examine the records and reports of tests the Department performs. SECTION 6 CONTROL OF MATERIALS Schedule work to allow time for the Department's inspection, sampling, and testing. The Department deducts testing costs for work that does not comply with the Contract. The Department may retest materi al previously tested and authorized for use . If the Department notifies you of a retest, furnish resources for retesting.
6-2.03B Job Site Inspection and Testing
Section 6 -2.03B applies if a material is to be inspected or tested at the job site. The material must be authorized for use before it is incorporated into the work.
6-2.03C Certificates of Compliance
Section 6 -2.03C applies (1) where a certificate of compliance is specified or (2) if any material is produced outside the United States. Submit a certificate of compliance: