9 PAYMENT
9-1.01 General
9-1.02 Measurement
9-1.02A General
The Department determines bid item quantities under US customary units . Except for final pay item quantities, the Engineer measures quantities for payment.
9-1.02B Weighing Equipment and Procedures
9-1.02B(1) General
Measure material quantities for payment with devices that comply with:
9-1.02B(2) Equipment
Each scale must be long enough to fit an entire vehicle or a combination vehicle on the scale deck. The Department allows you to weigh a combination vehicle separately if you disconnect the vehicles. Construct s cale undersupports:
9-1.02B(3) Procedures
Each day weigh empty vehicles used to haul material paid for by weight. Each vehicle must have a legible identifi cation mark. The Department may verify a material weight by having an empty and loaded vehicle weighed on any scale the Engineer designates. If imported topsoil , soil amendment , wood m ulch, or compost is measured by volume:
9-1.02C Final Pay Item Quantities
The Department shows a bid item quantity as a final pay item for pay ment purposes only. For a final pay item, accept payment based on the Bid Item List quantity, regardless of the actual quantity used unless dimensions are changed by the Engineer.
9-1.02D Quantities of Aggregate and Other Roadway Materials
The Engineer de termines the weights of aggregate and other roadway material that are being paid for by weight as shown in the following table and does not include the deducted weight of water in their pay ment quantities: Determination of Quantities of Aggregate and Other Roadway Materials Material Quantity determination Aggregate or other roadway material except as otherwise shown in this table By deducting the weight of water in the materiala in excess of 3 percent of the dry weight of the material from the weight of the material Imported borrow, imported topsoil, AB By deducting the weight of water in the materiala in excess of 6 percent of the dry weight of the material from the weight of the material Straw By deducting the weight of water in the materiala in excess of 15 percent of the dry weight of the material from the weight of the material Fiberb Engineer do es not deduct the weight of water AB and aggregate for CTBs As specified in section 26 and section 27 NOTE: Percentage of water is determined by California Test 226. aAt the time of weighing . bWeight of water in the fibera must not exceed 15 percent of the dry weight of the fiber.
9-1.03 Payment Scope
The Department pays you for furnishing the resources and activities required to complete the work. The Department's payment is full compensation for furnishing the resources and activities, including:
9-1.04 Force Account
9-1.04A General
For work paid by force account , the Engineer compares the Department's records to your daily force - account work report. When you and the Engineer agree on the contents of the daily force -account work reports, the E ngineer accepts the report and the Department pays for the work. If the records differ, the Department pays for the work based only on the information shown on the Department's records. The Tentative Daily Extra Work Agreement form is used to identify the labor, materials, and equipment used on change order work paid at force account. Signatures on this form do not constitute final agreement regarding payment. If a subcontractor performs work at force account, accept an additional 10 percent markup to the t otal cost of that work paid at force account, including markups specified in section 9 -1.04, as reimbursement for additional administrative costs. The markups specified for labor, materials, and equipment include compensation for all delay costs, overhead costs, and profit. If an item's unit price is adjusted for work -character changes, the Department excludes your cost of determining the adjustment. Payment for owner -operated labor and equipment is made at the market -priced invoice submitted. For nonsubcon tracted work paid by force account for a contract with a TRO bid item, the markups are those shown in the following table instead of those specified in sections 9 -1.04B –D: Cost Percent markup Labor 30 Materials 10 Equipment rental 10
9-1.04B Labor
Labor payment is full compensation for the cost of labor used in the direct performance of the work plus a 35 percent markup. Force -account labor payment consists of:
9-1.04C Materials
Material payment is full comp ensation for materials you furnish and use in the work. The Engineer determines the cost based on the material purchase price, including delivery charges, except:
9-1.04D Equipment Rental
9-1.04D(1) General
Equipment rental payment is full compensation for:
9-1.04D(2) Equipment On the Job Site
For equipment on the job site at the time required to perform work paid by force account, the time paid is the time:
9-1.04D(3) Equipment Not On the Job Site and Not Required for Original -Contract Work
For equipment not on the job site at the time required to perform work paid by force account and not required for the ori ginal Contract work, the time paid is the time the equipment is operated to perform work paid by force account and the time to return the equipment to its source when the work paid by force account is completed. The minimum total time paid is:
9-1.04D(4) Equipment Not On the Job Site and Required for Original -Contract Work
For equipment not on the job site at the time required to perform work paid by force account and required for the original Contract work, the time paid is the time:
9-1.04D(5) Non -Owner-Operated Dump Truck Rental
Submit the rental rate for a non -owner -operated dump truck. The Engineer determines the payment rate. Payment for the rental of a non-owner -operated dump truck is for the cost of renting a dump truck, including its driver. For the purpose of markup payment only, the non -owner -operated dump truck is rental equipment and the owner is a subcontractor.
9-1.05 Extra Work Performed By Spe Cialists
If the Engineer determines that you or your subcontractors are not capable of performing specialty extra work , a specialist may be used. Itemize the labor, material, and equipment rental costs unless it is not the special service industry's established practice to provide itemization, in which case, the Engineer accepts current market -priced invoices for the work. The Engineer may accept an invoice as a specialist billing for work performed at an off –job site manufacturing plant or machine shop. The Engineer determines the cost based on the specialist invoice price minus any available or offered discounts plus a 10 percent markup.
9-1.06 Changed Quantity Payment Adjustments
9-1.06A General
The unit price s specified in section 9 -1.06 are adjusted under section 9 -1.04.
9-1.06B Increases of More Than 25 Percent
If the total bid item quantity exceeds 125 percent of the quantity shown on the Bid Item List and if no approved Change Order addresses payment for the quantity exceeding 125 percent, the Engineer may adjust the unit price for the excess quantity under section 9 -1.04 or the following:
9-1.06C Decreases of More Than 25 Percent
If the total item pay quantity is less than 75 percent of the quantity shown on the Bid Item List and if no approved Change Order addresses payment for the quantity less than 75 percent, you may request a unit price adjustment. The Engineer may adjust the unit price for the decreased quantity under section 9 -1.04 or the followin g:
9-1.06D Eliminated Items
If the Engineer eliminates an item , the Engineer notifies you and the Department pays your costs incurred before the notification date. If you order authorized material for an eliminated item before the notification date and the order cannot be canceled, either of the following occurs:
9-1.07 Payment Adjustments for Price Index Fluctuations
9-1.07A General
Section 9 -1.07 applies to asphalt contained in materials for pavement structures and pavement surface treatments such as HMA, tack co at, asphaltic emulsions, bituminous seals, asphalt binders, and modified asphalt binders placed in the work . Section 9-1.07 does not apply if you opted out of payment adjustments for price index fluctuations at the time of bid. The Engineer adjusts payment whenever the California statewide crude oil price index for the month the material is placed is more than 5 percent higher or lower than the price index at the time of bid. The Department determines the California statewid e crude oil price index each month on or about t he 1st business day of the month using the average of the posted prices in effect for the previous month as posted by Chevron, ExxonMobil, and ConocoPhillips for the Buena Vista and Midway Sunset fields. If a company discontinues posting its prices for a field, the Department determines the index from the remaining posted prices. The Department may include additional fields to determine the index. For the California statewide crude oil price index, go to the D epartment's Division of Construction website . If the adjustment is a decrease in payment, the Department deducts the amount from the monthly progress payment. The Department makes payment adjustments due to price index fluctuations for changed quantities u nder section 9 -1.06. If you do not complete the work within the Contract time , payment adjustments during the overrun period are determined using the California statewide crude oil price index in effect for the month in which the overrun period began. If the price index at the time of placement increases:
9-1.07B Asphalt Quantities
9-1.07B(1) General
Reserved
9-1.07B(2) Hot Mix Asphalt
The Engineer calculates the quantity of asphalt in HMA using the following formula: Qh = HMATT x Xa where: Qh = quantity in tons of asphalt used in HMA HMATT = HMA, total tons placed Xa = theoretical asphalt content from the job mix formula, expressed as a percentage of the total weight of HMA
9-1.07B(3) Rubberized Hot Mix Asphalt
The Engineer calculat es the quantity of asphalt in RHMA using the following formula: Qrh = RHMATT x 0.80 x Xarb where: Qrh = quantity in tons of asphalt in asphalt rubber binder used in RHMA RHMATT = RHMA, total tons placed Xarb = theoretical asphalt rubber binder content fro m the job mix formula, expressed as a percentage of the total weight of rubberized HMA
9-1.07B(4) Hot Mix Asphalt with Modified Asphalt Binder
The Engineer calculates the quantity of asphalt in HMA with modified asphalt binder using the following formula : Qmh = MHMATT x [(100 − Xam)/100] x Xmab where: Qmh = quantity in tons of asphalt in modified asphalt binder used in HMA MHMATT = modified asphalt binder HMA, total tons placed Xam = specified percentage of asphalt modifier Xmab = theoretical modified asphalt binder content from the job mix formula, expressed as a percentage of the total weight of HMA
9-1.07B(5) Hot Mix Asphalt Containing Reclaimed Asphalt Pavement
The Engineer ca lculates the quantity of asphalt in HMA containing RAP using the following formula: Qrap = HMARTT x Xaa where: Xaa = Xta – [(Xrap x Xra x(Xta – 100))/(100 x (Xra – 100))] and: Qrap = quantity in tons of asphalt used in HMA containing RAP HMARTT = HMA containing RAP, total tons placed Xaa = asphalt content of HMA containing RAP adjusted to exclude the asphalt content in RAP, expressed as a percentage of the total weight of HMA contai ning RAP SECTION 9 PAYMENT Xta = total theoretical asphalt content in HMA containing RAP from the job mix formula, expressed as a percentage of the total weight of HMA containing RAP Xrap = RAP percentage in HMA containing RAP from the job mix formula, expressed as a percen tage of the total dry weight of aggregate in HMA containing RAP Xra = average asphalt content of RAP from the job mix formula, expressed as percentage of total weight of RAP
9-1.07B(6) Tack Coat
The Engineer calculates the quantity of asphalt in tack coa t (Qtc) as either of the following:
9-1.07B(7) Asphalti c Emulsion
The Engineer calculates the quantity of asphalt in asphaltic emulsions, including fog seals and tack coat, using the following formula: Qe = AETT x (Xe/100) where: Qe = quantity in tons of asphalt used in asphaltic emulsions AETT = undiluted as phaltic emulsions, total tons placed Xe = minimum percent residue specified in section 94 based on the type of emulsion used You may determine Xe by submitting daily test results for asphalt residue for the asphaltic emulsion used. If you choose this option, you must:
9-1.07B(8) Slurry Seal
The Engineer calculates the quantity of asphalt in slurry seal s (Qss) by applying the formula in section 9 - 1.07B(7) to the quantity of asphaltic emulsion used in producing the slurry seal mix.
9-1.07B(9) Modified Asphalt Binder
The Engineer calculates the quantity of asphalt in modified asphalt binder using the foll owing formula: Qmab = MAB TT x [(100 − Xam)/100] where: Qmab = quantity in tons of asphalt used in modified asphalt binder MABTT = modified asphalt binder, total tons placed Xam = specified percentage of asphalt modifier The quantity of extender oil is in cluded in the quantity of asphalt.
9-1.07B(10) Other Materials
For materials containing asphalt not covered in sections 9 -1.07B(1) through 9 -1.07B(9), the Engineer determines the method for calculating the quantity of asphalt ( Qo).
9-1.07C Payment Adjust ments
The Engineer includes payment adjustments for price index fluctuations in progress estimates. If material containing asphalt is placed within 2 months during 1 estimate period, the Engineer calculates 2 separate SECTION 9 PAYMENT adjustments. Each adjustment is calcul ated using the price index for the month in which the quantity of material containing asphalt subject to adjustment is placed in the work. The sum of the 2 adjustments is used for increasing or decreasing payment in the progress estimate. The Engineer calc ulates each payment adjustment using the following formula: PA = Qt x A where: PA = payment adjustment in dollars for asphalt contained in materials placed in the work for a given month Qt = sum of all quantities of asphalt ( Qh + Qrh + Qmh + Qrap + Qtc + Qe + Qss + Qmab + Qo) A = adjustment in dollars per ton of asphalt used to produce materials placed in the work rounded to the nearest $0.01 where: A = [(Iu/Ib) − 1.05] x Ib x [1 + ( T/100)] for an increase in the crude oil price index exceeding 5 percent A = [(Iu/Ib) − 0.95] x Ib x [1 + ( T/100)] for a decrease in the crude oil price index exceeding 5 percent and: Iu = California statewide crude oil price index for the month in which the quantity of asphalt subject to adjustment was placed in the work Ib = California statewide crude oil price index for the month in which the bid opening for the project occurred T = Sales and use tax rate expressed as a percent currently in effect in the tax jurisdiction where the material is placed. If the tax rate information is not submitted timely, the statewide sales and use tax rate is used in the payment adjustment calculations until the tax rate information is submitted.
9-1.08 9-1.10 Reserved
9-1.11 Time -Related Overhead
9-1.11A General
Section 9 -1.11 applies if a bid item for time -related overhead is incl uded in the Contract. If a bid item for time-related overhead is included, you must exclude the time -related overhead from every other bid item price.
9-1.11B Payment Quantity
The TRO quantity does not include the number of working days to complete plant establishment or permanent erosion control establishment work. For a contract with a TRO lump sum quantity on the Bid Item List, the Department pays you based on the following conversions:
9-1.11C Payment Inclusions
Payment for the TRO bid item includes payment for time -related field -and home -office overhead for the time required to complete the work. The field office overhead includes time -related expenses associated with the normal and recurring construction activities not directly attributed to the work, including:
9-1.11D Payment Schedule
For progress paymen ts, the total work completed for the TRO bid item is the number of working days shown for the pay period on the Weekly Statement of Working Days form. For progress payments, the Department pays a unit price equal to the lesser of the following amounts:
9-1.11E Payment Adjustments
The overhead adjustment specified in section 9 -1.17C does not apply. The Department does not adjust the unit price for an inc rease or decrease in the TRO quantity except as specified in section 9 -1.11E. Section 9 -1.17D(2)(b) does not apply to TRO except as specified for the audit report below. If the TRO bid item quantity exceeds 149 percent of the quantity shown on the Bid Item List or as converted under section 9 -1.11B, the Engineer may adjust or you may request an adjustment of the unit price for the excess quantity. For the adjustment, submit an audit report within 60 days of the Engineer's request. The report must be prepare d as specified for an audit report for an overhead claim in section 9 - 1.17D(2)(b). SECTION 9 PAYMENT Within 20 days of the Engineer's request, make your financial records available for an audit by the State for the purpose of verifying the actual rate of TRO described in yo ur audit. The actual rate of TRO described is subject to the Engineer's authorization. The Department pays the authorized actual rate for TRO in excess of 149 percent of the quantity shown on the Bid Item List or as converted under section 9 -1.11B. The Dep artment pays for 1/2 the cost of the report; the Contractor pays for the other 1/2. T he cost is determined under section 9 -1.05 except no markup is allowed.
9-1.12 9-1.14 Reserved
9-1.15 Work -Character Changes
The Departmen t adjusts a bid item unit price based on the difference between the cost to perform the work as planned and the cost to perform the work as changed. The Engineer determines the payment adjustment under section 9 -1.04. The Department adjusts payment for onl y the work portion that changed in character.
9-1.16 Progress Payments
9-1.16A General
The Department pays you based on Engineer -prepared monthly progress estimates . Each estimate reflects:
9-1.16B Schedule of Values
Section 9 -1.16B applies to a lump sum bid item for which a schedule of values is specified to be submitted. The sum of the amounts for the work units listed in the schedule of values must equ al the lump sum price bid for the bid item. Obtain authorization for a schedule of values before you perform work shown on the schedule. The Department does not process a progress payment for the bid item without an authorized schedule of values. Accept pr ogress payments for overhead, profit, bond costs, and other fixed or administrative costs as distributed proportionally among the items listed except that for a contract with a bid item for mobilization, accept progress payments for bond costs as included in the mobilization bid item. For changed quantities of the work units listed, the Department adjusts payments in the same manner as specified for changed quantities of bid items under section 9 -1.06.
9-1.16C Materials On Hand
A material on hand but not incorporated into the work is eligible for a progress payment if:
9-1.16D Mobilizat ion
9-1.16D(1) General
Section 9 -1.16D applies if a bid item for mobilization is shown on the Bid Item List. Payments for mobilization made under section 9 -1.16D are in addition to the partial payments made under Pub Cont Code § 10261. Section 9 -1.16D(2) applies unless the Contract includes a special provision for section 9 -1.16D(1) that specifies section 9 -1.16D(3) applies.
9-1.16D(2) Mobilization for Projects Except for Those Over Water Requiring Marine Access
The Department makes partial payments for m obilization under Pub Cont Code § 10264(a) except the amount of work completed does not include the amount earned for mobilization. The partial payment amount is reduced by a prorated amount bid in excess of the maximum allowed under Pub Cont Code § 10264( a)(5). The Department pays the item total for mobilization in excess of the maximum allowed under Pub Cont Code § 10264(a)(5) in the 1st payment after Contract acceptance.
9-1.16D(3) Mobilization for Projects Over Water Requiring Marine Access
The Departm ent makes partial payments for mobilization under Pub Cont Code § 10264(b) except the amount of work completed does not include the amount earned for mobilization. The partial payment amount is reduced by a prorated amount bid in excess of the maximum allo wed under Pub Cont Code § 10264(b)(6). The Department pays the item total for mobilization in excess of the maximum allowed under Pub Cont Code § 10264(b)(6) in the 1st payment after Contract acceptance.
9-1.16E Withholds
9-1.16E(1) General
The Departmen t may withhold payment for noncompliance . The Department returns the noncompliance withhold in the progress payment following the correction of noncompliance except as specified in section 9 -1.16E(3). Withholds are not retentions under Pu b Cont Code § 7107 and do not accrue interest under Pub Cont Code § 10261.5. Withholds are cumulative and independent of deductions. Section 9 -1.16E does not include all withholds that may be taken; the Department may withhold other payments as specified.
9-1.16E(2) Progress Withholds
The Department withholds 10 percent of a progress payment for noncompliant progress. Noncompliant progress occurs when:
9-1.16E(3) Performance Failure Withholds
During each estimate period you fail to comply with a Contract part, including the submittal of a document as specified, such as QC plans, schedules, traffic control plans and water pollution control submi ttals, the Department withholds a part of the progress payment except as specified below for the failure to submit a document during the last estimate period. For 1 performance failure, the Department withholds 25 percent of the progress payment but does not withhold more than 10 percent of the total bid. For multiple performance failures, the Department withholds 100 percent of the progress payment but does not withhold more than 10 percent of the total bid. During the last estimate period, if you fa il to submit a document as specified, the Department withholds $10,000 for each document. The Department returns the withhold within 30 days after receipt of the document.
9-1.16E(4) Stop Notice Withholds
The Department withhold s payments to cover claims filed under Civ Code § 9000 et seq. Stop notice information may be obtained from the Division of Accounting, Office of External Accounts Payable.
9-1.16E(5) Penalty Withholds
Penalties include fines and damages that are proposed, assessed, or levied again st you or the Department by a governmental agency or private lawsuit. Penalties are also payments made or costs incurred in settling alleged violations of federal, State, or local laws, regulations, requirements, or PLACs. The cost incurred may include the amount spent for mitigation or correcting a violation. If the Department is assessed a penalty, the Department may withhold the penalty amount until the penalty disposition has been resolved. The Department may withhold penalty amounts without notifying you. Instead of the withhold, you may provide a bond equal to the highest estimated liability for any disputed penalties proposed except you may not provide a bond for withholds related to labor compliance violations.
9-1.16E(6) 9-1.16E(10) Reserved
9-1.16F Retentions
The Department does not retain moneys from progress payments due to the Contractor for work performed.
9-1.16G 9-1.16M Reserved
9-1.17 Payment After Contract Acceptance
9-1.17A General
Reserved
9-1.17B Payment Before Final Estimate
After Contract acceptance, the Department pays you based on the Engineer -prepared estimate that includes withholds and the balance due after the deduction of previous payments. SECTION 9 PAYMENT
9-1.17C Proposed Final Estimate
The Engineer estimates the amount of work completed and shows the amount payable in a proposed final estimate based on:
9-1.17D Final Payment and Claims
9-1.17D(1) General
If you accept the proposed final estimate or do not submit a claim statement within 30 days of receiving the est imate, the Engineer provides you the final estimate and the Department pays the amount due within 30 days. This final estimate and payment is conclusive except as specified in sections 5 -1.27, 5 - 1.47, and 9 -1.21. If you submit a claim statement within 30 d ays of receiving the Engineer's proposed final estimate, the Engineer provides you a semifinal estimate and the Department pays the amount due within 30 days. The semifinal estimate is conclusive as to the amount of work completed and the amount payable ex cept as affected by any claims or as specified in sections 5 -1.27, 5 -1.47, and 9 -1.21.
9-1.17D(2) Claim Statement
9-1.17D(2)(a) General
For each claim, submit a claim statement showing only the identification number that corresponds to the Full and Final Potential Claim Record form and the final amount of the additional payment requested except:
9-1.17D(2)(b) Overhead Claims
9-1.17D(2)(b)(i) General
The Department deducts an amount for field and home office overhead paid on added work from any claim for overhead. The home office overhead deduction equals 5 percent of the added work. The field office overhead deduction equals 5 -1/2 percent of the added work.
9-1.17D(2)(b)(ii) Definitions
actual daily overhead rates : The home office over head and field office overhead rates expressed per business day for the contract performance period. The home office overhead rate is calculated using the Eichleay Formula and is based on overhead cost pools and all allocation bases from Contract and compa ny revenues . added work: Equals the value of the work completed minus the total bid. contract performance period: The period from Contract approval to Contract acceptance.
9-1.17D(2)(b)(iii) Submittals
Submit the following for an overhead claim:
9-1.17D(2)(c) Declaration
Submit a declaration that includes the following language with the claim statement: I declare under penalty of perjury, acc ording to the laws of the State of California, that the foregoing claims, with specific reference to the California False Claims Act (Govt Code § 12650 et seq.) and to the extent the project contains federal funding, the US False Claims Act (31 USC § 3729 et seq.), are true and correct, and that this declaration was signed on ______(date)_______, 20__ at _________________, California.
9-1.17D(2)(d) Waiver
A claim is waived if:
9-1.17D(3) Final Determination of Claims
Failure to allow timely access to the supporting data for a claim when requested waives the claim. The Department's costs in revie wing or auditing a claim not supported by the Contractor's accounting or other records are damages incurred by the State within the meaning of the California False Claims Act. If the Engineer determines that a claim requires additional analysis, the Engine er schedules a Department management meeting. Meet with Department management and make a presentation supporting the claim. After the Engineer or Department management finishes reviewing the claim, the Department makes the final determination of claims and provides it to you. This final determination of claims is the final written decision by the Department on the claims under Pub Cont Code § 10240.1. The Engineer provides you a final estimate and the Department pays the amount due within 30 days. The final estimate is conclusive as to the amount of work completed and the amount payable except as specified in sections 5 -1.27, 5 -1.47, and 9 -1.21. Your failure to comply with the claim procedures is a bar to arbitration under Pub Cont C ode § 10240.2.
9-1.18 9-1.20 Reserved
9-1.21 Clerical Errors
For 3 years after Contract acceptance, estimates and payments are open to correction and adjustment for clerical errors. Either you or the Department pays to the other the amount due except for clerical errors resulting in an adjustment less than $200, in which case, no payment is made.
9-1.22 Arbitration
Pub Cont Code § 10240 through 10240.13 provides for the resolution of contract claims by arbitration . Start arbitration by filing a complaint with the Office of Administrative Hearings in Sacramento (1 CA Code Regs § 1350). File the arbitration complaint no later than 90 days after receiving the Department's final written decision on a claim (Pub Cont Code § 10240.1). The Department's final written decision on a claim is the final determination of claims as specified in section 9 -1.17D(3).