629.01 629-1 SECTION 629 SURVEY MONUMENTATION DESCRIPTION
629.01 This work consists of locating, preserving, referencing, installing and restoring land
monuments, such as Primary Co ntrol monuments from which the r ight of way or any land boundary will be calculated, described or monumented, Public Land Survey System (PLSS) monuments, General Land Office (GLO) monuments, Bureau of Land Management (BLM) monuments, Mineral Survey (MS) monuments, Right- of-way (ROW) monuments, property boundary monuments, easement monuments, and other monuments that are required by law or regulation to be established and recorded by a Professional Land Surveyor (PLS), and the determination of any land boundary, shall be done per Section 629, under the supervision of a PLS who is experienced and competent in Right of Way and boundary surveying and licensed in the State of Colorado. All such monuments included in this section shall be established per the applicable and most recent editions of the Department of Interior’s Manual of Surveying Instructions (BLM Manual), Colorado Revised Statutes (CRS), Colorado State Board of Licensure for Professional Engineers and Land Surveyors (State Board) Rules and Policies, the Memorandum of Understanding (MOU) with the State Board and CDOT , and the CDOT Survey Manual, under the supervision of a PLS who is experienced and competent in Right of W ay and boundary surveying and licensed in the State of Colorado. The PLS shall be available to review work, resolve problems, and make decisions in a timely manner. Unless specified otherwise in the contract, all survey procedures shall be in conformance with the CDOT Survey Manual. MATERIALS AND EQUIPMENT
629.02 The Contractor shall furnish all personnel, survey equipment , safety equipment,
materials, and traffic control necessary to perform the required monumentation and related surveying. Monuments and monument boxes will be furnished by the Department. The various types of monuments and monument boxes shall be constructed according to the details shown on Standard Plan M -629-1. The Contractor shall furnish all labor, survey tools, equipment , and incidental materials such as but not limited to concrete , grout, asphal t caulk, glue, epoxy, nails, stakes, lath, and replacement monuments of the variety not included on the Standard Plan M -629-1. All surveying equipment , including Electronic Distance Measuring Instruments (EDM I), total stations, levels, rods, tapes, tripods, tribrachs, and Global Positioning System (GPS) receivers and equipment, shall be checked and calibrated per the Colorado Department of Transportation (CDOT) Survey Manual, Chapter 6, Section 6.1.10, and documented in the survey records before the start of work and every six months thereafter. EDMI and total stations shall be checked and calibrated on a National Oceanic and Atmospheric Administration/ National Geodetic Survey (NOAA / NGS) calibrated baseline per the CDOT Survey Manual, Chapter 2, Section 2.1 and 2.2, and documented in the survey records before the start of work and every six months thereafter. 629.03 629-2 GPS receivers and equipment shall be checked and calibrated on a NOAA / NGS calibrated baseline per the CDOT Survey Manual, Chapter 3, Section 3.3, and documented in the survey records before the start of work and every six months thereafter. Levels shall be checked and calibrated per the CDOT Survey Manual, Chapter 6, and Chapter 5, and documented in the survey records before the start of any level circuit. If any survey equipment is found to be functioning outside the manufacturer’s specified tolerance, certification from an approved repair facility showing that the instruments have been repaired, properly adjusted, or both if needed shall be included in the survey records and sub mitted to the Engineer before being used. Traffic control shall be per Section 630. CONSTRUCTION REQUIREMENTS
629.03 General. The Department will establish Primary horizontal and vertical control for
the project. All available information defining the extent of that control is provided on the plans per the CDOT Survey Manual Chapter 6, or is available from the Engineer and CDOT PLS Coordinator or Project Engineer . A Presurvey Conference – Construction Survey meeting be held per the CDOT Survey Manual Chapter 6, Section 6.1.6, before performing any surveying work under this section. The Engineer , Region Survey Coordinator and Plans Coordinator (or designee), Contractor ’s Superintendent, Contractor’s Surveyor (PLS) and Party Chief shall attend. A Presurvey Conference – Construction Survey Form shall be included per the CDOT Survey Manual Chapter 6. A surveying work schedule shall be submitted to the Engineer for review before the Presurvey Conference . The Contractor shall check all Department established Primary horizontal and vertical control points per the CDOT Survey manual Chapter 6, Section 6. 2, and verify and document in the survey records their horizontal accuracy tolerance per the CDOT Survey Manual Chapter 5, Section 5.5, and their vertical accuracy tolerance per the CDOT Survey Manual Chapter 6 .2, and Chapter 5 .9, for a CDOT Class A , Primary Survey before using them for monumentation and surveying control. Survey records shall be completed as the work is done. Field survey notes for monumentation, surveying and checking by the Contractor shall be recorded in survey records in conformance with the format given in the CDOT Survey Manual Chapter 6, Section 6.1. Survey field books shall be indexed per the Survey Manual Chapter 2, Section 2.4. The Contractor shall make all survey records generated available to the Engineer for inspection or reproduction at all times. The Contractor shall submit all survey records to the Engineer before Final Acceptance. All survey records are considered property of the Department. The responsible PLS or PE identified in subsection 629.01, shall electronically seal all survey records. The electronic format shall contain the information and format as required in the Survey Manual Chapter 6, Section 6.1 including stakeout data and the raw data from the actual placement of the monuments. Survey records shall include the requirements specified in the CDOT Survey Manual Chapter 6, Section 6.3, and Chapter 5, Section 5. 12, for any PLSS monument, GLO monument, BLM monument, or MS monument on the project. 629.04 629-3 Copies of any new Monument Records filed by the PLS with the State Board of Registration per the CDOT Survey Manual Chapter 6, Section 6.3, and Chapter 5, Section 5. 12, shall be submitted to the PLS Coordinator and Engineer , after filing with the State Board .
629.04 Locating Monuments . This work consists of field locating all survey monumentation
that is in place because of a Government (Federal, State , County or Municipal) survey or resurvey as shown on original PLSS, GLO, BLM, or MS plats, notes, or other survey monumentation documented in the public record per the CDOT Survey Manual Chapter 6, Section 6.3. A diligent search of construction zones and project limits shall be performed by the PLS per the Survey Manual Chapter 5, Section 5. 12, to locate any survey monumentation of the public record. An electronic magnetic field sensor or locator shall be used in this search. The responsible PLS shall document the search, and time spent searching, in the survey records using a narrative form. The survey records shall include the procedures used to make the diligent search, a description of each monument searched for, and the actions taken to reference and preserve the location of the monument per subsection 629.05.
629.05 Preserving and Referencing Monuments . This work consists of field surveying,
establishing, installing, and making measurements to reference monuments that will facilitate the installation of a replacement monument in the event the construction activity disturbs a monument of the public reco rd as listed in subsection 629.04. Referencing of monuments for possible replacement requires the use of correct replacement methods so the stated precision of the monument in question is not degraded. When a construction activity is planned that will disturb an existing PLSS, GLO, B.L.M., or MS monument, the monument shall be referenced and the survey records shall include the information required in subsection 629.03, and the monument shall be upgraded by the PLS and a new Monument Record filed w ith the State Board per the Survey Manual Chapter 5, Section 5.12, when the following conditions are met:
629.07 Monument Box . This survey work shall consist of installing or adjusting monument
boxes included on the plans. When it is necessary to set a monument within a monument box per Title 38 CRS and State Board Rules and Policies, the work shall be done per Standard Plan M -629-1. If the monument meets the physical standard as stated by the State Board and is situated within the finished roadway, a monument box shall be installed as shown on Standard Plan M -629-1. When an existing monument box, due to construction, will no longer meet the physical standard set by the State Board, the box shall be replaced or adjusted to meet those standards. METHOD OF MEASUREMENT
629.08 Survey Monuments, Monument Boxes, and Adjust Monument Boxes will be measured
by the actual number of the various types installed and accepted by the Engineer . Measurement for locating survey monuments will be by the hour as approved by the Engineer. BASIS OF PAYMENT
629.09 The accepted quantities will be paid for at the contract unit price for each of the
pay items listed below that appear in the bid schedule. No payments will be made before the proposed work schedule is submitted. Legible signed and sealed copies of survey records per subsection 629.03 shall be submitted on a monthly basis to the Engineer for completed work before payment is made for that pay item. 629.09 629-7 Before final payment is made, the following three items shall be completed, bear the seal and signature of the responsible PLS identified in subsection 629.01, and have copies submitted to the Engineer for review before being deposited with the county per Title 38 CRS, Property – Real and Personal, State Board Rules and Policies, MOU, and the CDOT Survey Manual:
630.01 This work consists of furnishing, installing, moving, maintaining, and removing
temporary traffic signs, advance warning arrow panels, flashing beacon (portable) , barricades , channelizing devices, delineators , temporary traffic signals, temporary portable rumble strips , mobile pavement marking zones , temporary emergency pull -off areas , masking and unmasking existing signs in construction zones, concrete barriers , and Automated Flagging Assistance Devices (AFAD) as required by the Manual on Uniform Traffic Control Devices for Streets and Highways and the Colorado Supplement thereto, per the Contract. Devices shall comply with the performance criteria contained in NCHRP Report 350 (only applicable for devices developed before 2011) or Manual for Assessing Safety Hardware ( MASH ) (acceptable for all devices). Devices temporarily not in use shall, as a minimum, be removed from the shoulder area. Moving will include devices removed from the project and later returned to use. This work also includes Traffic Control Management , flagging, and pilot car operation . This work consists of providing traffic pacing operation to motorists within the project area, as shown on the plans. It includes locating traffic related incidents, providing roadside assistance, and clearing the traffic related incidents. The use of law enforcement officers shall be integrated into the Rolling Roadblock operations. MATERIALS
630.02 Signs and Barricades . Construction traffic sign and barricade materials shall conform
to the applicable portions of Section 614 with the following exception: Sign panels may be fabricated from plywood, aluminum, steel, or other suitable materials provided they are stable and durable enough to meet the other requirements of Section 614. Traffic control devices deemed inadequate by the Engineer shall not be used and shall be removed from the project site. Temporary sign support assembly shall be timber, perforated square metal tubing inserted into a larger base post or slip base, or perforated metal U -channel with a slip base. The temporary sign support assembly shall conform to NCHRP (only applicable for sign support assemblies developed before 2011) or MASH (acceptable for all sign support assemblies), and AASHTO requirements regarding temporary sign supports during construction. If U-Channel posts with a slip base are selected, they shall be used only in multi- post applications, as shown on Standard Plan S -630-4. Retro -reflective sheeting shall conform to the requirements of subsection 713.04. Retro -reflective sheeting types shall be as defined in the CDOT Retroreflective Sheeting Materials Guide. Retro -reflective sheeting shall be one of the types specified for the particular application in Table 630- 1. Retro -reflective sheeting for all signs requiring an orange background shall be Fluorescent.