624.01 624-1 SECTION 624 DRAINAGE PIPE DESCRIPTION
624.01 This work consists of furnishing and installing pipe defined by class for culverts (cross
drains), side drains, and storm sewers per these specifications and in conformity with the lines and grades shown on the plans or established. MATERIALS
624.02 Materials shall meet the requirements in the Contract and in the following subsections.
Abbreviation Description Subsection CSP Corrugated Steel Pipe 707.02 Bit. Co. CSP Bituminous Coated Corrugated Steel Pipe 707.03
624.03 Installation shall conform to the requirements of Section 603 or Section 510 as
applicable. Installation for Aluminized Corrugated Steel Pipe Type 2 shall conform to all requirements for Corrugated Steel Pipe (CSP) including the fill height tables and requirements in Standard Plan M - 603-1. Joining and installation of plastic pipe shall conform to ASTM D2321 and the manufacturer's recommendations. METHOD OF MEASUREMENT
624.04 Drainage pipe will not be measured but will be the net length of pipe called for on the
plans, except when field changes are ordered or when there are errors on the plans. In case of exceptions, the quantity to be measured shall be the actual net length of conduit measured along the bottom centerline of the installed pipe. The net length shall include end sections when required. BASIS OF PAYMENT
624.05 The accepted quantities of drainage pipe will be paid for at the contract unit price per
linear foot for the specified size and class. Payment will be made under: Pay Item Pay Unit _____Inch Drainage Pipe (Class__) Linear Foot 624.05 624-4 Structure excavation and structure backfill will be measured and paid for per Section 206. 624.05 624-5 THIS PAGE INTENTIONALLY LEFT BLANK 625.01 625-1 SECTION 625 CONSTRUCTION SURVEYING DESCRIPTION
625.01 This work consists of the construction surveying, calculating, and staking necessary for
the construction of all elements of the project. The work shall be done under the supervision of a Professional Land Surveyor (PLS) or Professional Engineer (PE) who is experienced and competent in road and bridge construction surveying and licensed in the State of Colorado. Locating, preserving, referencing, installing and restoring land monuments such as Primary Co ntrol monuments from which the r ight of way or any land boundary will be calculated, described or monumented, Public Land Survey System (PLSS ) monuments, General Land Office (GLO) monuments, Bureau of Land Management (BLM) monuments, Mineral Survey (MS) monuments , Right -of-way (ROW ) monuments, property boundary monuments, easement monuments, and other monuments that are required by law or regulation to be established by a PLS, and the determination of any land boundary, shall be done per Section 629, under the supervision of a Professional Land Surveyor (PLS) who i s experienced and competent in Right of W ay and boundary surveying and licensed in the State of Colorado. The PLS shall be available to review work, resolve problems, and make decisions in a timely manner. Unless specified otherwise in the Contract, all survey procedures shall be in conformance with the CDOT Survey Manual. If the Revision of Section 102 Project Plans and Other Data states 3D modeling data is available, the Contractor may choose to perform 3D Engineered Construction Surveying (3DECS). 3DECS is the use of global positioning and or robotic instruments to guide construction equipment operations by comparing 3D model information in real time. For 3DECS, either the construction equipment is fed modeling information and makes automatic adju stments (machine control ), or the equipment operator is fed the information and makes physical adjustments. Adobe Sign software shall be used for electronic seals by the Contractor’s Engineer, a Professional Engineer, or a Professional Land Surveyor. Electronic signatures and seals shall comply with the requirements of the Architects, Professional Engineers, and Professional Land Surveyors Rules and Regulations, 4 CCR 730 -1. MATERIALS AND EQUIPMENT
625.02 The Contractor shall furnish all personnel, survey equipment , safety equipment,
materials, and traffic control necessary to perform the required construction surveying and staking. All surveying equipment , including : Total stations, LiDAR scanners, levels, rods, tapes, tripods, tribrachs, and Global Positioning System (GPS) receivers and equipment , shall be checked and calibrated per the CDOT Survey Manual, Chapter 6, Section 6.1.10, and documented in the survey records before the start of work and every six months thereafter. Electronic Distance Measuring Instruments ( EDMI) and total stations shall be checked and calibrated on a National Oceanic and Atmospheric Administration/ National Geodetic Survey