Description
620.01 The Contractor shall furnish field offices, sanitary facilities and field laboratories when
called for on the plans or as directed. These units are to be maintained by the Contractor and shall be removed when the project is completed unless released earlier by the Engineer. Materials
620.02 Field Offices. Field offices, either Class 1 or Class 2 as designated on the plans, shall
substantially conform to the details shown on the plans and to the requirements of this section. The field office shall be equipped with a facsimile machine, copy machine, and telephone service that conform to the following:
620.03 Field Laboratories. Field laboratories, either Class 1 or Class 2 as designated on the
plans, shall substantially conform to the details shown on the plans and to the requirements of this section. Each laboratory shall be qualified per CP 10.
620.04 Commercial Plant Laboratory. The plant laboratory at the site of the commercial hot
mix plant shall consist of weatherproof, insulated, mobile house-type trailer or other approved structure having equipment meeting the following minimum requirements. 620-1 620.05 Each laboratory shall be qualified per CP 10.
620.05 Sanitary Facilities. Sanitary facilities shall consist of a portable chemical toilet
fabricated from steel, fiberglass or wood, meeting the following minimum requirements: Each facility shall be well ventilated, conform to State law, have a vented chemical tank, and a separate urinal. Construction Requirements
620.06 The Contractor shall furnish a suitable site for field facilities. The site may be
located within the right of way with approval of the Engineer. If located within the right of way, the Contractor shall be responsible for restoring the area. Facilities shall be on the project, leveled and ready for use before the start of any operations. Facilities shall be for the exclusive use of Department personnel. 620- 2 620.07 Sanitary facilities shall be placed at least 50 feet from the nearest State Water, in locations accessible for servicing, and not in low-lying areas subject to ponding. They shall be anchored to prevent movement or overturning. The Contractor shall provide replacement equipment due to breakdown, damage, or theft within five workdays.
620.07 Maintenance, Service and Utilities. The Contractor shall furnish the following:
Table 620-1 Maintenance, Service and Utilities Furnished by Contractor Fuel Adequate supply for heating and testing operations. A 3,000 watt, 115-125-volt AC facility for each field office and field laboratory. Independent generators shall be provided where Electricity commercial power is not available. Minimum flat rate services from nearest exchange for each field office Telephone and field laboratory, as directed. Sanitary facilities shall be serviced and maintained in a sanitary Sanitary condition. The Contractor shall provide and maintain suitable containers and shall Trash haul away as necessary. Method of Measurement and Basis of Payment
620.08 The various facilities complete with utilities, will be measured and paid for at the
contract unit price for each of the pay items listed below that appear in the bid schedule. Payment will be made under: Pay Item Pay Unit Field Office (Class______) Each Sanitary Facility Each Field Laboratory (Class______) Each Payment will be full compensation for Field Laboratory (Class1) or (Class 2), including all appurtenant items specified in the Contract. Restoration of the field facility areas will not be paid for separately but shall be included in the cost of the item. 620-3 620.08 This Page Intentionally Left Blank 620- 4 622.01
Field Facilities in other states
Get an email when 620 changes