Division 200 — Earthwork

202Random Clearing and Grubbing

GA · 2021 Standard Specifications✓ Full text on BuildSpecBook pages 197–198 Save this section

Ask about Section 202

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

202.1 General Description

This work includes clearing and grubbing borrow and material pits. See Subsection 107.23. It also includes such ditch inlets, outlets, channel changes, and easement areas where clearing and grubbing are required but not shown on the plans.

202.1.01 Definitions

General Provisions 101 through 150.

202.1.02 Related References

A. Standard Specifications Section 107—Legal Regulations and Responsibility to the Public Section 201—Clearing and Grubbing Right-of-Way B. Referenced Documents General Provisions 101 through 150.

202.1.03 Submittals

General Provisions 101 through 150.

202.2 Materials

General Provisions 101 through 150.

202.2.01 Delivery, Storage, and Handling

General Provisions 101 through 150.

202.3 Construction Requirements

202.3.01 Personnel

General Provisions 101 through 150.

202.3.02 Equipment

General Provisions 101 through 150.

202.3.03 Preparation

General Provisions 101 through 150.

202.3.04 Fabrication

General Provisions 101 through 150.

202.3.05 Construction

Perform the work according to Section 201.

202.3.06 Quality Acceptance

General Provisions 101 through 150.

202.3.07 Contractor Warranty and Maintenance

General Provisions 101 through 150.

202.4 Measurement

The area of completed and accepted clearing and grubbing is measured in acres (hectares). Only the area cleared and grubbed as shown on the Plans or as designated by the Engineer is measured. The Department will make no separate payment for removing grass, weeds, debris, small underbrush, other vegetation from cultivated lands, and isolated trees or stumps. Include the cost for removing these items in the price bid for other Pay Items.

202.4.01 Limits

General Provisions 101 through 150.

202.5 Payment

The Department will pay for Clearing and Grubbing and Clearing at the Contract Unit Price per acre (hectare), which is full compensation for all work specified. Payment will be made under: Item No. 202 Clearing and grubbing Per acre (hectare) Item No. 202 Clearing Per acre (hectare)

202.5.01 Adjustments

General Provisions 101 through 150.

Random Clearing and Grubbing in other states

Get an email when 202 changes

Georgia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction of Transportation Systems, 2021 Edition. Pages 197–198 of 2,050. View official source ↗

Ask about this section

Scoped to Georgia 2021 Standard Specifications, Section 202 — Random Clearing and Grubbing. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.