429.1 General Description

This work includes furnishing and placing rumble strips according to plan details and this specification.

429.1.01 Definitions

General Provisions 101 through 150.

429.1.02 Related References

A. Standard Specifications Section 400—Hot Mix Asphaltic Concrete Section 413—Bituminous Tack Coat B. Referenced Documents General Provisions 101 through 150.

429.1.03 Submittals

General Provisions 101 through 150.

429.2 Materials

Ensure that asphaltic concrete conforms to Section 400, Types 12.5 mm Superpave, or 9.5 mm Superpave mixes. Ensure that the tack coat conforms to Section 413.

429.2.01 Delivery, Storage, and Handling

General Provisions 101 through 150.

429.3 Construction Requirements

429.3.01 Personnel

General Provisions 101 through 150.

429.3.02 Equipment

A. Hand Rollers Use nonvibrating hand rollers to compact the strips. B. Forms Ensure the form confines and spaces the hot mix according to the plan details.

429.3.03 Preparation

General Provisions 101 through 150.

429.3.04 Fabrication

General Provisions 101 through 150.

429.3.05 Construction

Complete this procedure to install rumble strips: 1. Tack the entire 20 ft. (6 m) strip length. 2. Place the oiled form and ensure that the first strip coincides with the beginning of the first unit. 3. Place and level the plant mix. Roll the strips with the forms in place. 4. Remove the forms and compact the strips to the Engineer’s satisfaction. 5. Repeat this operation to install the entire 20 ft. (6 m) rumble strip. Install additional units as designated on the Plans using the same methods and procedures. NOTE: Do not place strips on wet or frozen pavement.

429.3.06 Quality Acceptance

General Provisions 101 through 150.

429.3.07 Contractor Warranty and Maintenance

General Provisions 101 through 150.

429.4 Measurement

Rumble strips are measured per each strip constructed.

429.4.01 Limits

General Provisions 101 through 150.

429.5 Payment

Rumble strips will be paid for per each strip completed and accepted. Payment is full compensation for furnishing materials and performing the work. Payment will be made under: Item No. 429 Rumble strips Per each

429.5.01 Adjustments

General Provisions 101 through 150.

Get an email when 429 changes

Georgia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction of Transportation Systems, 2021 Edition. Pages 499–500 of 2,050. View official source ↗

Ask about this section

Scoped to Georgia 2021 Standard Specifications, Section 429 — Rumble Strips. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.