B
HomeLibrariesCode AISearchProjectsBookmarksAddress
FeedbackHelp Desk
Libraries
Estimate & calculate
CalculatorsChecklists
PricingLog in
Division 500 — Structures

574Edgedrains

GA · 2021 Standard Specifications✓ Full text on BuildSpecBook pages 933–935 Save this section

Ask about Section 574

Get a cited answer from the section text. Click the citation to check it.

One cited answer a day is free. Start a 14-day trial for unlimited, no card required.

574.1 General Description

This work includes constructing edgedrains with perforated pipe according to the specifications and to the details, lines, and grades shown in the plans, or as directed by the Engineer.

574.1.01 Definitions

General Provisions 101 through 150.

574.1.02 Related References

A. Standard Specifications Section 400—Hot Mix Asphaltic Concrete Construction Section 800—Coarse Aggregate Section 839—Corrugated Polyethylene Underdrain Pipe Section 840—Corrugated Aluminum Alloy Pipe Section 843—Concrete Pipe Section 881—Fabrics B. Referenced Documents GDT 59 QPL 28

574.1.03 Submittals

General Provisions 101 through 150.

574.2 Materials

Ensure that materials meet the requirements of the following Specifications. Use pipe specified below unless the Plans state otherwise. Use only one type of pipe in each continuous, interconnecting line. Material Section Corrugated Aluminum Alloy Underdrain Pipe 840.2.02 Concrete Underdrain Pipe 843.2.03 Corrugated Polyethylene Underdrain Pipe 839 Drainage Aggregate Backfill, Size No. 78 800.2.01 Asphaltic Concrete 400 Plastic Filter Fabric (Non-woven) 881.2.05

574.2.01 Delivery, Storage, and Handling

General Provisions 101 through 150.

574.3 Construction Requirements

574.3.01 Personnel

General Provisions 101 through 150.

574.3.02 Equipment

General Provisions 101 through 150.

574.3.03 Preparation

Before placing edgedrains, pressure grout and cure pavement slabs in the immediate area. Do not begin work until the Engineer determines that pavement slabs are stable.

574.3.04 Fabrication

General Provisions 101 through 150.

574.3.05 Construction

Complete any opened trenches, including the asphalt cap, each working day. Install edgedrains with other operations on the Project to prevent conflict, damage, or improper infiltration of other materials. A. Excavating Excavate according to the details and elevations shown on the plans or as directed by the Engineer. B. Placing Filter Fabric Place filter fabric according to plan details. If the drainage aggregate or the filter fabric become contaminated or the filter fabric is damaged during the backfilling operation, remove the contaminated or damaged materials and replace them at no additional cost to the Department. C. Laying Pipe Lay pipe according to the plan details, with perforations on the underside of the pipe, unless otherwise directed by the Engineer. 1. Lay bell and spigot and tongue and groove pipe with the bell or grooved end upstream and the bells embedded in the foundation material. 2. Firmly connect the joints. 3. Connect butt joint pipes securely using the appropriate size and type of band or coupling. 4. Install the following miscellaneous Items according to the plans or as otherwise specified: • Pipe screens • Caps • Plugs • Covers • Ells • Wyes • Tees • Markers D. Backfilling After laying the pipe, place the additional backfill material in 6 in. (150 mm) layers. 1. Before compacting, establish the target density as 1.18 times the average of 5 dry-density determinations made on the material in the trench. Space the 5 determinations over at least 500 ft. (150 m) and determine them using the 6-in. (150 mm) direct transmission density mode according to GDT 59. 2. Thoroughly compact each layer to 100 percent of the target density and complete to the depth shown on the Plans, details, or as directed by the Engineer. 3. Do not disturb the pipe alignment or damage the filter fabric. 4. Place a compacted asphaltic concrete cap on the trench as shown in the Plan details or as directed by the Engineer. E. Marking Mark each outlet end of the drainage system according to plan details. F. Protecting from Contamination Protect the backfill material from contamination by foreign matter. If aggregates become contaminated, remove the contaminated portion and replace it with clean material before placing succeeding layers.

574.3.06 Quality Acceptance

General Provisions 101 through 150.

574.3.07 Contractor Warranty and Maintenance

General Provisions 101 through 150.

574.4 Measurement

The quantity of edgedrain pipe, including backfill material and filter fabric, complete in place and accepted is measured in linear feet (meters) along each line or lateral, from center to center of junctions and fittings.

574.4.01 Limits

General Provisions 101 through 150.

574.5 Payment

Each size of edgedrain pipe will be paid for at the Contract Price per linear foot (meter). Payment for pipe under this Item includes: • Preparation • Excavation • Backfilling • Specified backfill materials and filter fabric • Disposal of surplus material • Screens, tees, wyes, and ells • The asphaltic concrete cap over the trench Payment will be made under: Item No. 574 Edgedrain pipe, including backfill material and filter fabric ___ in (mm) Per linear foot (meter)

574.5.01 Adjustments

General Provisions 101 through 150.

Get an email when 574 changes

Georgia revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for Construction of Transportation Systems, 2021 Edition. Pages 933–935 of 2,050. View official source ↗

Ask about this section

Scoped to Georgia 2021 Standard Specifications, Section 574 — Edgedrains. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.