for Highway Construction Page 87 of 715 SECTION 108 – PROSECUTION, PROGRESS, AND TERMINATION
108.01 Subletting of Contract .
108.02 Contract Time .
108.03 Project Schedule .
108.04 Preconstruction and Preoperational Conference s.
Meet with the Engineer for a preconstruction conference at a mutually agreed time. At or before the preconstruction conference, submit the following to the Engineer:
108.05 Limitation of Operations .
Do not start an operation impacting traff ic until traffic control devices are approved and completely installed. Perform the work in a manner and sequence that will ensure the least interference with traffic. The Contractor is responsible for the location of detour s and provisions for handling traffic. Access the project site only at existing interchange ramps, public road connections, or approaches. The Engineer may require the Contractor to finish a project section before starting on additional project sections if the section opening is essential for public convenience. Do not work on a roadway open to the traveling public, except for normal maintenance operations, during a 3-day holiday weekend or on July 3, 4, and 5. for Highway Construction Page 92 of 715 108.06 Methods, Equipment, and Character of Workers. Provide sufficient labor and equipment for completing the work i n a satisfactory manner and within the contract time. Employ workers with suf ficient skill and experience to properly perform the work assigned to them. If, as determined by the Engineer, a person employed by the Contractor or its subcontractor does not perform the work in a proper and skillful manner or is intemperate or disorderl y, the Engineer will issue a written direction for removal of the person. Do not employ the removed person in any fut ure work portions without approval. If the Contractor does not do the following, the Engineer may suspend the work by wr itten notice until the Contractor complies with the contract :
108.07 Extension of Contract Time .
108.07 B, 108.07.D, or 108.07.F, extends the scheduled substantial completion date. The Engineer will only consider a request to revise contract time if the fol lowing conditions are met:
108.08 Failure to Complete on Time .
If the contract time expires, liquidated damages will be assessed as noted in the special provisions of the contract documents for each day the work remains substantially incomplete after the contract time or its most recent extension has expired. The daily rate will be assessed per working day for working day contracts and per calendar day for calendar day and completion date contracts. Liquidated damages are not a penalty. The Engineer will determine working days for the assessment of liquidated damages as specified in 108.02.B. For calendar day and completion date contracts, the Engineer will not exclude days during December, January, and February. Liquidated damages will be deducted from monies due to the Contractor or will be billed to the Contractor. Liquidated damages will not be assessed after substantial completion of the work as evidenced in writing, as long as the Contractor performs the remaining work. Allowing the Contractor to continue and finish the work after the contract time expires in no way operates as a waiver on the part of the Department of its rights under the contract.
108.09 Default and Termination of Contract .
If the Contractor is responsible for any of the following, the Engineer may provide written notice to the Contractor and surety of the delay, neglect, or default:
108.10 Termination for Convenience of the Department .
109.01 Measurement of Quantities.
The Engineer will measure the contract pay item quantities, except for items that require the Contractor to provide survey measurement as specified in 675, using the units of measure specified in the contract and the methods of measurement and calculation as specified in this section . The U.S. customary system of weights and measures units is defined in 15 CFR. Unless otherwise agreed upon by the Engineer, progress payments will not be issued for items requiring survey measurement until the Engineer has received a statement of quantities, along with supporting documentation and calculations, signed and sealed by a licensed Idaho professional engineer or professional land surveyor. Measurements will be rounded as specified in Table 109.01-1 , unless otherwise specified . Table 109.01- 1 – Standard Rounding Pay Unit Rounding Acre / Acre Unit (AU) 0.001 Contingency Amount (CA) 0.01 Cubic Foot (CF) 0.1 Cubic Yard (CY) 0.1 Day 1 Each 1 Foot ( FT) 0.5 Gallon (gal) 1 Hour (hr) 0.5 Lump Sum (LS) 0.001 Mile 0.01 Month 1 Pound (lb) 1 Square Foot (SF) 0.1 Square Yard (SY) 0.1 Station (Sta) 0.01 Thousand Feet Board Measure (MFBM) 0.001 Thousand Gallons (MG) 1 Ton 0.01 For standard manufactured materials identified by gauge, thickness, unit weight, or section dimensions, the Department will consider these as nominal weights and dimensions, and accept industry established manufacturing tolerances. The Engineer will measure contract pay item quantities by the actual quantity or by the plan quantity, as required by the contract.