for Highway Construction Page 98 of 715 SECTION 109 – MEASUREMENT AND PAYMENT
109.01 Measurement of Quantities.
The Engineer will measure the contract pay item quantities, except for items that require the Contractor to provide survey measurement as specified in 675, using the units of measure specified in the contract and the methods of measurement and calculation as specified in this section . The U.S. customary system of weights and measures units is defined in 15 CFR. Unless otherwise agreed upon by the Engineer, progress payments will not be issued for items requiring survey measurement until the Engineer has received a statement of quantities, along with supporting documentation and calculations, signed and sealed by a licensed Idaho professional engineer or professional land surveyor. Measurements will be rounded as specified in Table 109.01-1 , unless otherwise specified . Table 109.01- 1 – Standard Rounding Pay Unit Rounding Acre / Acre Unit (AU) 0.001 Contingency Amount (CA) 0.01 Cubic Foot (CF) 0.1 Cubic Yard (CY) 0.1 Day 1 Each 1 Foot ( FT) 0.5 Gallon (gal) 1 Hour (hr) 0.5 Lump Sum (LS) 0.001 Mile 0.01 Month 1 Pound (lb) 1 Square Foot (SF) 0.1 Square Yard (SY) 0.1 Station (Sta) 0.01 Thousand Feet Board Measure (MFBM) 0.001 Thousand Gallons (MG) 1 Ton 0.01 For standard manufactured materials identified by gauge, thickness, unit weight, or section dimensions, the Department will consider these as nominal weights and dimensions, and accept industry established manufacturing tolerances. The Engineer will measure contract pay item quantities by the actual quantity or by the plan quantity, as required by the contract. for Highway Construction Page 99 of 715 A. Actual Quantities . Where the contract specifies actual quantity as the basis of payment for a contract pay item, the Engineer will measure and calculate the actual work quantity performed, using quantities from measurements taken from the completed work in place or from measurements taken from delivery vehicles. This excludes work outside the project site as specified in the method of measurement section for the relevant contract pay item. The Engineer will measure the actual contract pay item quantities using the following methods:
109.03 Payment for Quantity Variations , Contract Revisions , and Delays.
109.03 C.5.e, 109.03.C.5.f, and 109.03.C.5.g.
If an approved subcontractor performs work on a force account basis, the Department will pay the Contractor for field office overhead, home office overhead, and profit as follow s: Dollars The Contractor’s Pay Up to $10,000 15% Over $10,000 $1,500 + 10% of excess over $10,000 The Engineer will calculate the Contractor’s overhead and profit based on the total amount of force account work performed, including allowable markups. Submit receipts and invoices. The Department will approve and pay the additional amount after receipt of the invoices.
109.04 Increases or Decreases Du e to Changes in Tax Rules.
The total contract amount includes applicable federal, state, and local taxes and duties. The Department will not adjust the contract amount for increases or decreases due to taxes , unless the amount of an increase or decrease is greater than $100 from the contract amount. for Highway Construction Page 112 of 715 Notify the Engineer promptly of a statute, court decision, written ruling, or regulation that will result in an increase or decrease in the contract amount.
109.05 Partial Payments.
Partial payments are only approximate and are subject to correction in any payment following the discovery of an error. Partial payments will be made at least once each month as the work progresses and only if the Contractor performs work in accor dance with the contract or as directed. Semi -monthly payments will be made upon the Contractor’s written request. The Engineer will pr epare estimates and partial payments will be made based on the value of the work performed and for material delivered and on hand as specified in 109.06. The Engineer may withhold part of a pay estimate until the Contractor complies with the contract , including:
109.06 Payment for Material on Hand.
The Engineer may make partial payments for material that will be incorporated into the work, if the material is delivered to or stockpiled in approved storage sites. Ensure the stockpiled material quantity eligible for for Highway Construction Page 114 of 71 5 partial payment does not exceed the total estimated quantity required to complete the work. The stockpiled material partial payment will not exceed the value of t he portion of the contract pay item in which the material will b e incorporated. The Engineer will not make partial payments on living or perishable plant materials until planted.
109.07 Allowance fo r Material Left on Hand.
If materials are not incorporated into the work because of contract pay item elimination, contract revisions as specified in 104.02, termination of the contract for the Department’s convenience as specified in 108.09, and it is not commercially feasible for the Contractor to return the material for credit or otherwise dispose of the material, the Department will purchase the materials provided the Contractor:
109.08 Acceptance and Final Payment .
The Contractor will have 20 business days after the last charged contract day and notification by the Engineer to submit outstanding documentation on completed work or the Contractor will receive a pay reduction for failure to submit documentation for the applicable pay item(s) as documented on a change order . After accepting the work as specified in 105.16, the Engineer will prepare a final estimate including the following:
110.01 General Requirements.
Contractor will comply with 110 in accordance with the Special Equal Employment Opportunity Responsibilities under 23 CFR 140 and 23 CFR 230, Subpart A and D (also refer to United States Department of Transportation (USDOT) form FHWA -1273 attached to each contract ). To find the nearest employment office, visit https://www.labor.idaho.gov/dnn/Local -Office-Directory The Contractor will take affirmative action to assure equal employment opportunity as required by Executive Order 11246 and Executive Order 11375. The Contractor must ensure compliance with the Uniformed Services Employment and Reemployment Rights Act (USERRA) and the Vietnam Era Veterans’ Readjustment Assistance Act (VEVRAA) where appropriate. Contractors, consultants, suppliers, and service providers bidding and performing the Department’s federal - aid funded projects must register as vendors at https://itd.dbesystem.com . For more information, contact the Office of Civil Right s 208- 334-8567 or email civilrights@itd.idaho.gov .
110.02 Equal Employment Opportunity.
MEASUREMENT AND PAYMENT in other states
Get an email when 109 changes
Idaho revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.