for Highway Construction Page 400 of 71 5 SECTION 522 – CONTROLLED DENSITY FILL (CDF)
522.01 Description.
Furnish all labor, materials, equipment, and incidentals necessary to provide, load, haul, place, and consolidate the controlled density fill (CDF) to the lines and grades specified.
522.02 Materials.
Provide CDF usin g concrete aggregates, fly ash, cement, and water. Guideline mix proportions are presented below: Portland Cement ................................................................................. ASTM C15 0 or AASHTO M 85 Fly Ash .................................................................................................................. Class F or Class C Aggregates ........................................................................................................................ ASTM C33 Water ...................................................................................................................................... Potable Admixtures ..............................................................................AASHTO M 194, ASTM C260 or C494 Ensure CDF mixture meets the acceptable properties in Table 522.02- 1. Table 522.02-1 – CDF Mixture P roperties CDF Mix Property Maximum gallons of mixing water per cubic yard 50 Pounds of cement per cubic yard 50 ± 5 Pounds of fly ash per cubic yard 250 ± 10 Pounds of dry aggregate per cubic yard (an assumed specific gravity of 2.67) 3,200 ± 100 Slump, inches 6 - 8 Submit the CDF mix design with the backup data for approval. Do not install CDF until after the CDF mix design has been approved. Provide a mix design from an approved laboratory.
522.03 Construction Requirements.
Batch, transport, and place CDF as specified in 502.
522.04 Method of Measurement.
The Engineer will measure acceptably completed work by the cubic yard. Measurement will be based upon batch delivery tickets submitted at the time of placement .
522.05 Basis of Payment .
The Department will pay for acceptable quantities at the contract unit price as follows : for Highway Construction Page 401 of 715 Pay Item Pay Unit Controlled Density Fill ............................................................................. CY 523-530 for Highway Construction Page 402 of 715 SECTIONS 523 -550 - RESERVED for Highway Construction Page 403 of 71 5 SECTION 551 – POLYESTER POLYMER CONCRETE (PPC) OVERLAY