581.01 Description.
A.Preparation. Prepare concrete surface cracks to inject with an epoxy resin adhesive. Repair cracks wider than 0.016 inch measured at the concrete surface including the finishing and cleaning of girders, pier caps, columns, and abutments as specified and as directed.
B.Injection. Inject epoxy resin adhesive into prepared concrete cracks.
581.02 Materials.
A.Preparation. Use the following material to prepare the cracks for injection: Epoxy Resin for Surface Sealing. Provide a troweling -grade epoxy paste adhesive conforming to ASTM C881, Type I, Grade 3, Class B and C for the surface seal material capable of being applied to vertical and overhead surfaces and capable to confine the injection adhesive in the cracks during injection and curing . Ensure the surface seal material has adequate strength to hold injection fittings firmly in place and to resist injection pressures adequately to prevent leakage during injection. The Department will not allow material that contains asbestos. Ensure properties meet Table 581.02- 1. Table 581.02 -1 – Epoxy Resin Properties for Surface Sealing Property Requirement Test Method Tensile Strength ≥ 3,000 psi at 14 days ASTM D638 Flexural Strength (Modulus of Rupture) ≥ 3,700 psi at 14 days ASTM D790 Total Water Absorption 1.0% max at 7 days ASTM D570 (2 -hour boil) Bond Strength – dry cure ≥ 1,500 psi at 2 days ASTM C882 hardened con crete to hardened concrete Bond Strength – moist cure ≥ 1,500 psi at 14 days ASTM C882 hardened concrete to hardened concrete
B.Injection. Use the following material for injection: Epoxy Resi n for Injection. Provide epoxy adhesive for crack injection as an epoxy resin, 2- component, low viscosity adhesive containing no solvents or nonreactive dilutives conforming to ASTM C881, Type I and IV, Grade 1, Class B and C. Ensure properties meet Table 581.02 -2. for Highway Construction Page 451 of 71 5 Table 581.02-2 – Epoxy Resin Properties for Injection Property Requirement Test Method Tensile Strength ≥ 7,000 psi at 14 days ASTM D638 Initial Viscosity > 150 to <450 centipoise ASTM D2393, Brookfield RVT Spindle No. 2 at 100 rpm Flexural Strength (Modulus of Rupture) ≥ 1200 psi at 14 days ASTM D790 Total Water Absorption 1.5% max at 7 days ASTM D570 ( 2 hour boil) Bond Strength – dry cure ≥ 1500 psi at 2 days ASTM C882 hardened concrete to hardened concrete Bond Strength – moist cure ≥ 1500 psi at 14 days ASTM C882 hardened concrete to hardened concrete
581.04 Method of Measurement.
The Engineer will measure acceptably completed work for crack repair preparation by the foot along the exposed surface of cracks. The Engineer will measure acceptably completed work for crack repair inj ection by the gallons of epoxy used. Cracks that penetrate a concrete member at full depth, sealed on both sides of the member with injection/ inspection ports installed on both sides of the member verifying full penetration of epoxy adhesive, will be measured and paid for on both sides of the member. for Highway Construction Page 453 of 71 5 581.05 Basis of Payment . The Department will pay for accepted quantities at the contract unit price as follows: Pay Item Pay Unit Concrete Crack Repair Preparation ........................................................ FT Concrete Crack Epoxy Injection ............................................................. gal Coring injected areas to confirm full crack penetration and repairing the core locations is incidental . for Highway Construction Page 454 of 71 5 SECTION 582 – PATCH AND REPAIR OF CONCRETE
582.01 Description.
A.Concrete Surface. Repair and patch spalls, scaling, delaminations, honeycombing, and other deteriorated concrete on the surface of the girders, deck underside, pier caps, columns and abutments, including removal of debris from pier cap seats and abutment seats as specified and directed.
B.Concrete Deck . Repair spalls and delaminations in the bridge deck including determining the working areas by chain dragging or other approved method, preparing the concrete surface, repairing metal reinforcement , and applying the patching material.
Source: Idaho Standard Specifications for Highway Construction, 2023 Edition. Pages 486–489 of 768.