Cast Iron Soil Pipe Art. 560.05 Excavation in rock will be measured for payment according to Article 502.12.
552.08 Basis of Payment. This work will be paid for at the contract unit price
per foot (meter) for STORM SEWERS JACKED IN PLACE, of the diameter or equivalent round size specified. Excavation in rock will be paid for according to Article 502.13. UTILITIES SECTION 560. CAST IRON SOIL PIPE
560.01 Description. This work shall consist of constructing a cast iron soil
pipe.
560.02 Materials. Materials shall be according to the following.
Item Article/Section
560.03 General. Construction requirements shall be according to Section 550
with the following exceptions. The pipe shall be laid with its spigot end lacking 1/4 in. (6 mm) of being driven full into the bell. Gaskets of clean, sound hemp yarn braided or twisted and tightly driven shall be used to pack the joints, followed by caulking with pure soft lead of the best quality for the purpose, so as to make a tight and permanent joint. All pipes shall be carefully cleaned before laying, and shall be left clean and in working order. The pipe shall have a solid bearing throughout its entire length. If it becomes necessary to cut the pipe, it shall be cut in such a manner that the ends will be square with the axis of the pipe.
560.04 Method of Measurement. This work will be measured for payment in
place in feet (meters). Excavation in rock will be measured for payment according to Article 502.12. Trench backfill will be measured for payment according to Article 208.03.
560.05 Basis of Payment. This work will be paid for at the contract unit price
per foot (meter) for CAST IRON SOIL PIPE, of the diameter specified. Excavation in rock will be paid for according to Article 502.13. Trench backfill will be paid for according to Article 208.04. Art. 561.01 Water Main SECTION 561. WATER MAIN
561.01 Description. This work shall consist of constructing a water main.
561.02 Materials. Materials shall be as shown in the contract.
CONSTRUCTION REQUIREMENTS
561.03 General. The construction of water mains, including protection from
sewers, pressure testing, and disinfection, shall be according to the “Standard Specifications for Water & Sewer Main Construction in Illinois”, except as follows.
561.04 Method of Measurement. This work will be measured for payment in
place in feet (meters). The length measured will include stops, fittings, and valves. Excavation in rock will be measured for payment according to Article 502.12. Trench backfill will be measured for payment according to Article 208.03.
561.05 Basis of Payment. This work will be paid for at the contract unit price
per foot (meter) for WATER MAIN, of the diameter specified. Excavation in rock will be paid for according to Article 502.13. Trench backfill will be paid for according to Article 208.04. SECTION 562. WATER SERVICE LINE
562.01 Description. This work shall consist of constructing a water service
line.
562.02 Materials. Materials shall be as shown in the contract.
CAST IRON SOIL PIPE in other states