Art. 702.01 Nighttime Work Zone Lighting SECTION 702. NIGHTTIME WORK ZONE LIGHTING
702.01 Description. This work shall consist of furnishing, installing,
maintaining, moving, and removing lighting for nighttime work zones. Nighttime shall be defined as occurring shortly before sunset until after sunrise.
702.02 Materials. The lighting shall consist of mobile and/or stationary
lighting systems as required herein for the specific type of construction. Mobile lighting systems shall consist of luminaires attached to construction equipment or moveable carts. Stationary lighting systems shall consist of roadway luminaires mounted on temporary poles or trailer mounted light towers at fixed locations. Some lighting systems, such as balloon lights, may be adapted to both mobile and stationary applications.
702.03 Equipment. The Contractor shall furnish an illuminance meter for use
by the Engineer. The meter shall have a digital display calibrated to NIST standards, shall be cosine and color corrected, and shall have an accuracy of ± five percent. The sensor shall have a level indicator to ensure measurements are taken in a horizontal plane. CONSTRUCTION REQUIREMENTS
702.04 General. At the preconstruction conference, the Contractor shall
submit the type(s) of lighting system to be used and the locations of all devices. Before nighttime construction may begin, the lighting system shall be demonstrated as being operational.
702.05 Nighttime Flagging. The requirements for nighttime flagging shall be
according to Article 701.13 and the glare control requirements contained herein.
702.06 Lighting System Design. The lighting system shall be designed to
meet the following.
702.07 Construction Operations. The lighting design required above shall
be provided at any location where construction equipment is operating or workers are present on foot. When multiple operations are being carried out simultaneously, lighting shall be provided at each separate work area. The lighting requirements for specific construction operations shall be as follows.
702.08 Basis of Payment. This work will be paid for at the contract lump sum
price for NIGHTTIME WORK ZONE LIGHTING. Art. 703.01 Short Term and Temporary Pavement Markings SECTION 703. SHORT TERM AND TEMPORARY PAVEMENT MARKINGS
703.01 Description. This work shall consist of furnishing, installing,
maintaining, and removing short term and temporary pavement markings.
703.02 Materials. Materials shall be according to the following.
Item Article/Section
703.03 General. Short term pavement markings shall consist of abbreviated
patterns for edge, lane, and center line markings. Within a specified time limit, short term pavement markings shall either be resurfaced or removed and replaced with the full pavement marking patterns indicated on the plans with either a temporary material paid for as temporary pavement marking or with permanent material. Within the conditions as specified, the Contractor may be required to place all or a part of the quantities shown on the plans for short term pavement markings and temporary pavement markings. Before applying the pavement marking material, the pavement shall be cleaned according to the manufacturer. Paint pavement markings shall be installed according to Section 780, except hand-operated stripers may be used for all applications of short term and temporary pavement markings. Epoxy, polyurea, and modified urethane pavement markings shall be installed according to Section 780. Pavement marking tapes shall be applied to the prepared surface according to the manufacturer's recommendations or by a method approved by the Engineer.
703.04 Short Term Pavement Markings. Before the lane is opened to traffic,
appropriate short term pavement markings shall be installed between all lanes open to traffic. Center line or lane line markings shall consist of an abbreviated pattern of single stripes 4 ft (1.2 m) in length and a minimum of 4 in. (100 mm) wide at a maximum spacing of 40 ft (12 m) between stripes. Center lines on two-lane highways shall be yellow and lane lines separating two or more lanes of traffic moving in the same direction shall be white. Edge line markings shall be applied on multilane divided highways and other highways with a paved shoulder greater than 4 ft (1.2 m) wide. Edge line markings shall consist of stripes 4 ft (1.2 m) in length and a minimum of 4 in. (100 mm) wide at intervals of 50 ft (15 m) on ramps and 200 ft (60 m) on mainline installed at approximately a 45 degree diagonal pointing in the direction of traffic. Short term pavement markings on the final wearing surface shall be transversely offset from the permanent pavement marking location as directed by the Engineer. Short term pavement markings shall be removed within five calendar days after permanent pavement markings are installed.