Structures (500-599)

520SECTION 609 – REINFORCED CO NCRETE BRIDGE APPROACHES

IN · 2024 Standard SpecificationsBook pages 710View official source ↗

520 SECTION 609 – REINFORCED CO NCRETE BRIDGE APPROACHES

609.01 Description

This work shall consist of constructing reinforced concrete bridge approaches, RCBA, and extensions require d for bridge railing transitions in accordance with 105.03. MATERIALS

609.02 Materials 10

Materials shall be in acco rdance with the following: Coarse Aggregate, Class B or Higher, Size No. 8 ....... 904.03 Coarse Aggregate, Class D or Higher, Size No. 53 ..... 904.03 Concrete, Class A ........................................................ 702 Curing Materials .......................................................... 912.01 Geotextile for Pave ment and S ubgrade ....................... 918.02 Joint Materials ............................................................. 906.02(a)1 Reinforcing Bars, Epoxy Coated ................................. 910.01 Support Devices .......................................................... 910.01(b)11 20 Threaded Tie Bar Assembly ........................................ 910.01(b)2 CONSTRUCTION REQUIREMENTS

609.03 General Requirements

Subgrade shall be prepared in accordance with 207. Subba se shall be prepared in accordance with 302. Geotexti le shall be installed in accordance with 214. The RCBA extension shall be placed only where a concrete bridge-railing transition shall be located on the RCBA. If the transition shall be placed on the bridge, 30 the RCBA shall be placed as shown on the plans.

609.04 Forms Forms shall be either steel or wood and shall be in accordance with 508.04(c)1 or 508.04(c)2. 609.05 Joints

Longitudinal construction joints will only be allowed as shown on the plans. The Type I-A joint shall be constructed as shown on the plans. Type I-A joints shall be created by sawing slots using sawing equipment in accordance with 508.07. The joint shall be cut in two operations. The initial saw cut shall commence as soon as the concrete has hardened sufficiently to enable sawing without raveling, usually 2 to 12 h after placement. The second saw cut shall be made after the concrete has sufficiently cured, but 609.01 521 before opening the RCBA to all traffic. Slurry or saw residue remaining in the slot shall be immediately flushed. Construction traffic shall not be on the RCBA after the second saw cut until the joint is sealed. The sawed slot shall be cleaned to remove all foreign matter from the entire depth of cut. Joint sealing shall be in accordance with 503.05.

609.06 Reinforcing Bars

Furnishing and placement of reinforcing bars shall be in accordance with 703.

609.07 Thickness The depth of the RCBA will be checked by the Engineer prior to pouring, by making stringline measurements every 3 ft across the width of the approach. Any location deficient in depth by 1/2 in. or more shall be corrected prior to placing the 60

concrete.

609.08 Concrete Placement The subbase shall be uniformly moist at the time of concrete placement. Delivery and placement of concrete shall be in accordance with 702.

609.09 Finishing

The RCBA shall be finished with equipment in accordance with 508.04(c)3 and 508.04(c)4. The operations shall be controlled so that an excess of mortar and water is not worked to the top. Long-handled floats may be used to smooth and fill in open 70 textured areas. The edges of formed RC BA shall be tooled or chamfered. The finished RCBA surface shall be textured with a double thickness burlap drag or a minimum 4 ft wide turf drag. Longitudinal grooving shall be in accordance with 722.11 and shall not commence until the smoot hness has been measured in accordance with 609.11.

609.10 Curing

RCBA shall be wet cured in accordance with 702 or shall have liquid membrane forming curing compound applied and maintained in accordance with 504.04(a) to 80 exposed surfaces within 30 minutes after the finishing operations have been completed. The edges of the RCBA shall be cured immediately upon removal of the forms. The edge shall be covered with curing materials equal to the material used on the surface or banked with soil 12 in. wide or greater. When conditions arise whic h prevent timely application of curing materials the surfaces shall be kept wet with a fine spray of water. The fine spray of water shall continue until application of curing materials is resumed.

609.11 Smoothness 90

The smoothness of the surface of the RCBA will be measured by means of a 10 ft straightedge as soon as practical following curing or completion of adjoining 609.11 522 roadway or structure sections. All surface vari ations shall be corrected to 1/8 in. or less. Smoothness variations outside specified tolerances shall be corrected in accordance with 502.20. 609.12 Opening to Traffic The RCBA may be opened to equipment and traffic when the flexural strength of 100 the test beams indicates the concrete has attained a modulus of rupture of 550 psi or greater. The Contractor and Engineer will conduct an inspection of the new RCBA for any damage. The inspection and all necessary re pairs shall be completed prior to opening to traffic.

609.13 Method of Measurement

Reinforced concrete bridge approaches, including extensions required for bridge railing transitions, will be m easured by the square yard. Subbase for PCCP will be 110 measured in accordance with 302.08. Subg rade treatment will be measured in accordance with 207.05. Geotextile will be measured in accordance with 214.05. Reinforcing bars will be measured in accordance with 703.07. Threaded tie bar assemblies will be measured in accordance with 703.07. Longitudinal grooving will be meas ured in accordance with 722.15. Finishing and curing of the RCBA will not be measured for payment. Construction joints or Type I-A joints will not be measured. 120

609.14 Basis of Payment

Reinforced concrete bridge approaches, including extensions required for bridge railing transitions, will be paid for at the contract unit price per square yard. Subbase for PCCP will be paid for in accordance with 302.09. Subgrade treatment will be measured in accordance with 207.06. Geotex tile will be paid for in accordance with

214.06 Reinforcing bars will be paid for in accordance with 703.08. Threaded tie bar

assemblies will be paid for in accordance with 703.08. Longitudinal grooving will be paid for in accordance with 722.16. Payment will be made under: Pay Item Pay Unit Symbol Reinforced Concrete Bridge Approach, ________ in. .............. SYS thickness The cost of finishing, furnishing and placing curing materials shall be included in the cost of the RCBA. 609.12 523 140 The cost of corrections for smoothness or re-texturing shall be included in the cost of the RCBA. The cost of all labor and materials for the placement of construction joints and Type I-A joints shall be included in the cost of the RCBA.

Source: Indiana Standard Specifications, 2024 Edition. Pages 710 of 1,248.