303.1 Description
Mix subgrade soil, cement or fly ash and water to construct a uniform treated subgrade as shown in the Contract Documents. B I D I T E M S U N I T S C e m e n t T o n F l y A s h T o n Manipulation for Treated Subgrade (*) Square Yard Water (Treated Subgrade) (Set Price) M Gallon * Cement or Fly Ash
303.2 Materials
Provide materials that comply with the applicable requirements. Emulsified Asphalt (SS-1 or CSS-1) ..................................................................... DIVISION 1200 Medium Cure Cutback Asphalt (MC-250) ............................................................ DIVISION 1200 Concrete Admixtures & Curing Materials ............................................................. DIVISION 1400 Portland Cement & Blended Hydraulic Cement ................................................... DIVISION 2000 Fly Ash .................................................................................................................. DIVISION 2000 Water for Treated Subgrade .................................................................................. DIVISION 2400
303.3 Construction Requirements
a. Subgrade Preparation. Prepare the subgrade to the lines and grades shown in the Contract Documents. Scarify the prepared subgrade to the depth of treatment designated in the Contract Document prior to applying the cement or fly-ash. Perform the scarification with positive depth control equipment. Do not use a plow or disc for the scarification. Based on performance, the Engineer may approve the use of an automatic grade control motor grader scarifier. Bring the sc arified subgrade to within the specified moisture content of the previous moisture range before adding cement or fly ash. b. Application. On projects having more than 20,000 square yards of manipulation, apply cement or fly ash using a controlled application system. This system may be pressurized or mechanical in nature, utilizing vane or augers feeding cement or fly ash through a funnel or hood at a controlled rate. On projects having less than 20,000 square yards of manipulation, and in irregular areas, submit a plan to the Engineer for approval that includes equipment and procedures that address subgrade preparation and application process to spread the cement or fly ash at the specified rate. On projects having more than 20,000 square yards of manipulation, and consisting of multi-phased construction, contact the District Office for approval to waive the use of the controlled application system. Consideration will be based on the Cont ractors proposed alternate method of applying the cement or fly ash, the square yards of manipulation in each phase, and the size of individual areas within each phase. Do not apply the cement or fly ash when conditions are such that the material is lost due to the wind. Do not use cement or fly ash that was not properly handled and not stored in weatherproof containers. The Engineer will check the application rate of cement or fly ash by having the Contractor blade a flat area in the path of the cement or fly ash application, place a planar surface with a minimum surface area of 1 square foot (e.g. a straight-sided pan) and of sufficient height to co ntain the admixture on the prep ared area and allow the train to pass over the surface. Weigh the test surface before and after the cement or fly ash a pplication and calculate the application rate. Other methods to check the application rate may be used. 303 – CEMENT OR FLY ASH TREATED SUBGRADE 300-10 c. Mixing. Mix the scarified subgrade and cement or fly ash. Continue mixing and adding water until a homogeneous, friable mixture that complies with TABLE 303-1 is obtained. Use equipment with a recycling or mixing drum, and with an automatic water proportioning system to pulverize the subgrade to the specified depth. Do not perform treated subgrade operations when the ambient air temperature is below 40°F, or the soil is frozen. TABLE 303-1: PERCENT RETAINED - SQUARE MESH SIEVES* 1½-inch ½-inch 0 50 maximum *The Engineer will determine the percent retained on the specified sieves according to KT-42. Complete the mixing within 30 minutes of adding the cement or fly ash to the pulverized subgrade. The uniform moisture content of the mixture immediately before being compacted shall be ±3 percentage points of the optimum moisture content. If the moisture content of the mixture exceeds the specified moisture content, add additional cement or fly ash to lower the moistu re content. Spray the mixture with water, as necessary, to maintain the specified moisture content during the compaction operations. d. Compaction. For the initial compaction of the mixture, use a vibratory roller having a minimum operating weight of 12 tons, with a minimum centrifugal force of 24 tons. Use a rubber-tired or smooth-wheeled roller to complete the compaction of the surface. When the thickness is greater than 6 inches, compact multiple lifts of equal thickness with a maximum lift thickness of 6 inches . Compact the treated su bgrade to a minimum of 95% of the combined materials dry density. Complete the compaction operations within 2 hours of incorporating the cement or fly ash into the subgrade. If any of these requirements are not satisfied, reprocess, recompact and refinish the deficient areas. e. Trimming. After compaction of the treated subgrade, trim and recompact the treated subgrade to the specified lines and grades. On projects having more than 20,000 square yards of manipulation, use automatic grade controlled equipment to trim the subgrade. In irregular areas, trim the subgrade by wetting, blading and rolling.
303.4 Measurement and Payment
The Engineer will measure cement or fly ash used in the mixture by the ton. The Engineer will not measure additional cement or fly ash added to the mixture to reduce the moisture content. The Engineer will measure the manipulation for treated subgrade by the square yard. The Engineer will measure water used for cement tr eated subgrade by the M Gallon using calibrated tanks or water meters. The Engineer will measure water used for preparation of the subgrade, mixing subgrade and cement or fly ash, and the 7-day protection from drying period. The Engineer will not measure water used for dust control, water wasted through the Contractor’s negligence or water in excess of the quantity required for mixing and compacting the cement subgrade. If the Contractor opts to use asphalt material to cure the treated subgrade, the Engineer will not measure the asphalt material for payment. Payment for "Cement", "Fly Ash" and "Manipulation fo r Treated Subgrade" at the contract unit prices and "Water (Treated Subgrade) (Set Price)" at the contract set unit price is full compensation for the specified work.
Get an email when 303 changes
Kansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.