702 – CONTROLLED DEMOLITION 700-2
702.1 Description
Controlled demolition is the process of transporting, handling and disassembling the components of an open span structure to result in the complete or partial re moval of the entire structure or elements of a structure according to the approved demolition plan. The Contract Documents will identify the category for each structure. Information on existing structures is made accessible by the Owner, if the information is available. Evaluate project characteristics and prepare demolition plans according to the specified category listed in the General Notes. Plan and execute all procedures nece ssary for full or partial removal of the structure in a safe and controlled manner that meets all applicable KDOT specifications and all applicable OSHA requirements. After concrete removal, or before any steel repairs, te st the paint for lead content. Properly handle any lead based paint. See SECTION 714.
702.2 Demolition Supervisor
The Demolition Supervisor is the person responsible for all rigging and handling of bridge primary and secondary members. The Demolition Supervisor shall be pr esent at the construction site during the removal of Category B & C Structures. All Demolition Supervisors must be pre-qualified for the scope, type and complexity of the existing structure. To become pre-qualified, provide proof of e xperience that the Demolition Supervisor has a minimum of 3 years of experience and at least 5 projects similar in scope, type and complexity. KDOT will maintain a list of approved Demolition Supervisors on a Pre-Qualified List. Complete the pre-qualification of the Demolition Superv isor prior to the pre-construction meeting, and/or submit to the KDOT Field Engineer proof of pre-qualification at the pre-construction meeting.
702.3 Demolition Plans
a. General. The Contract Documents will indicate the demolition category for each structure. Submit shop drawings according to SECTION 105. Develop a unique Demolition Plan for each qualifying existing open span structure in the Contract Documents. Submit a detailed Demolition Plan to the Owner’s Engi neer for each open span structure. Address all requirements for removal of the structure to the limits shown in the Contract Documents. Demolition may not proceed until a Demolition Plan has been approved. During phased/staged demolition, the Contractor’s responsibilities extend to the removal limits stated in the Contract Documents for each phase. Do not directly affect the remaining structure outside the removal limits for each phase, or affect the adjacent structure. Include a Contingency Plan within the Demolition Plan indicating procedures to be carried out if the demolition stage completed does not comply with the Demolition Plan (i.e. the Plan states completion of rail removal, but due to unforeseen obstacles the majority of one rail has been partially disconnected from the existing structure, but it has not been removed). b. Definitions. The level of review and the requirements for submittals by the Contractor to the Engineer are categorized by risk and complexity. The Design Engineer will determine and assign the Category of the demolition and will indicate the demolition Category for each open span structure requiring removal on the design plans. Signing and Lighting structures, due to the typical removal procedures, will sp ecify a demolition Category based upon the Signing and Lighting Engineer’s engineering judgment. If this information is erroneously omitted, contact the State Bridge Office (SBO). Special considerations will control the selection of the demolition Category. Controlled demolition of open span structures falls under three separate categories:
702.4 Demolition Information Responsibility Summary
The Contractor’s Engineer shall provide the following information (Category C): Plan of the work area showing the as-built perman ent support structures of the structure to be disconnected or removed, roads, railroad tracks, waterways (including navigational channel), overhead and underground utilities and other information pertinent to the demolition procedure. Removal sequence for all elements of the structur e noting any temporary support conditions, such as holding crane positions, temporary supports or bracing, shoring, protective shields or covers, dead man cables, anchor blocks, etc. Details describing the number and location of the permanent, or temporary, cross-frames or diaphragms for each stage of removal. Details addressing the expected condition of each be aring device for each stage of construction. State the minimum number of positive bearing connections or supplemental connections to each bent cap which will resist potential destabilizing forces. Details addressing modified traffic control, utility and railroad issues. Demolition Plans to meet general falsework requirements in DIVISION 700 if falsework bents, temporary shoring, or strong-backs are used to maintain the stability of the remaining structure. 702 – CONTROLLED DEMOLITION 700-5 Contingency Plan specifying the various unintended partial stages of demolition and removal, including end-of-day bracing and stability requirements. The Contractor’s Engineer will also need to address real-time concerns arising from the on-going demolition process. The Contractor’s Demolition Superv isor shall provide the following information (Category B or C): Verification to the Contractor and the Field Engineer that member reference marks, as described in the Demolition Plan, have been transferred to the existin g structure to allow the Contractor and the Field Engineer to conduct a field review; Limits for windspeed/gust, or other environmental concerns for crane operations; Proposed crane locations for primary picks showing all necessary information; Capacity chart for each crane configuration; Center of gravity, lift weight (including rigging) for all picks; Primary/secondary element removal location and storage; Details of any temporary lifting devices to be bolted/welded to permanent members, including stage and method of attachment, capacity, and stage of removal and Temporary support details for bridge bearings. The Owner’s Inspector shall require the following (Category A, B and C): A dimensionally accurate Demolition Pl an, clearly stating the limits of removal, girder line locations, etc., to permanently transfer to the existing structure; Requirements for bracing. At the en d of each workday, remove, or te mporarily brace, the structural elements not properly stabilized to bring these elements into compliance with the Demolition Contingency Plan; and All rigging must have capacity stamps, tags or be otherwise permanently marked on the device (per OSHA Standards).
702.5 Preconstruction Conference
Discuss the Demolition Plan at the pre-construction or pre-demolition meeting. Resolve any questions during the meeting concerning the Demolition Plan or specific demolition procedures to the satisfaction of the Contractor, Contractor’s personnel, and the Engineer before demolition begins. Additional circumstances may be addressed to include within the Contingency Plan. Modify the Contingency Plan to include all situations agreed upon during the meeting.
702.6 Construction Requirements
Do not perform any demolition work without an approved Demolition Plan. Keep the approved Demolition Plans available on site at all times. Maintain a consistent, core group of staff (supervisors and laborers) through the completion of demolition. Demolish the existing structure and perform all work required to remove the structure to the limits stated and as detailed in the Contract Documents. Upon completion of the demolition, remove all obstructions or debris resulting from these operations. Without prior written approval by the KDOT Area Engi neer, do not stock pile construction materials, debris, or rubble exceeding the lesser of the posted load limit, or 20 tons. Equipment on the structure must not exceed the lesser of the poste d load limit, or the Operating Load Rati ng for the structure. To request written approval, provide the KDOT Area Engi neer plans showing the location, quantity and weight of the proposed materials, debris and/or equipment exceeding the stated limits. Perform demolition in a reasonable, controlled, met hodical fashion. Demolition Plan approval by the Engineer will not and does not relieve the Contractor of the responsibility for the safety of the methods used, safety of the equipment, or from carrying out the work in full accordance with SECTION 107. Demolition is complete when all elements are removed to the limits shown in the Contract Documents and any shoring and debris are removed.
702.7 Measurement and Payment
The Engineer will not measure Controlled Demolition, Demolition Plans and Contingency Plans for separate payment. All required work is subsidiary to the other bridge items in the contract.