701 - TEMPORARY SHORING 700-1

701.1 Description

Design and construct temporary shoring for the locations designated in the Contract Documents and any temporary shoring used for the Contractor’s convenience. B I D I T E M U N I T S T e m p o r a r y S h o r i n g L u m p S u m

701.2 Materials

Provide the materials shown in the Temporary Shoring Plan. The Engineer will accept the temporary shoring materials based on compliance with the dimensional requirements and visual inspection for condition.

701.3 Construction Requirements

For each location designated in the Contract Documents, submit the Temporary Shoring Plan (including the design calculations) sealed by a license d Professional Engineer, according to SECTION 105, to the Engineer for approval a minimum of 6 weeks before the scheduled beginning of temporary shoring operations, unless shown otherwise in the Contract Documents. Shore, sheet, brace or otherwise sup port the excavation or the structure according to the Temporary Shoring Plan. Maintain the temporary shoring until the Engineer authorizes its removal.

701.4 Measurement and Payment

The Engineer will measure each loca tion of temporary shoring designated in the Contract Documents by the lump sum. Temporary Shoring shown to be used in mu ltiple locations in conjunction with a structure will be considered as one location for lump sum payment. Unle ss shown as a bid item in the Contract Documents, the Engineer will not measure for payment any temporary shoring needed to comply with safety standards or due to the Contractor’s methods of operation. Payment for "Temporary Shoring" at the contract un it price is full compensation for the specified work.

Get an email when 701 changes

Kansas revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.

Source: Standard Specifications for State Road and Bridge Construction, 2015 Edition. Pages 332–332 of 978. View official source ↗

Ask about this section

Scoped to Kansas KDOT Standard Specifications for Road & Bridge Construction, Section 701 — Temporary Shoring. Every answer cites the section it came from, with a verification date — don’t trust a percentage, click the citation.