Effective with the December 2018 Letting 278 2019 Standard Spec ifications Section 511 Temporary Shoring
511.1Description
511.2Materials
AASHTO Load and Resistance Factor Design Specifications and the WisDOT Bridge Manual. Design to address all limit states using a design life of 36 months or the project specific duration, whichever is greater. Have a professional engi neer, registered in the state of Wisconsin and knowledgeable of the specific site conditions and requirements, verify the adequacy of the design. Submit one copy of each shoring design, signed and sealed by the same professional engi neer verifying the design, to the engineer for incorporation into the permanent project record.
511.3Construction
location as follows: Under the Temporary Shoring bid item: for all temporary shoring locations the contract shows. Under the Temporary Shoring (str ucture) bid items: for temporar y shoring associated with structure ID numbers identified in the bid item supplemental descriptions . Under the Temporary Shoring (loc ation) bid items: for temporary shoring associated with roadway locations identified in the bid item supplemental descriptions.
the left-in-place bid items, leav e the shoring in place as the special provisions specify or as the plans show. Place backfill conforming to 206.3.13 in excavated space not occupied by the new permanent construction.
511.4Measurement
completed at locations the plans show, measured as the area of exposed face in the plane of the shoring from the ground line in front of the shoring to a maximum of one foot above the retained grade. Shoring used for staged construction in multiple configu rations without removal and reinstallation will be measured on ce based on the configuration with the largest area of exposed face.
511.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
511.1100 Temporary Shoring SF
511.1200 Temporary Shoring (structure) SF
511.1300 Temporary Shoring (location) SF
511.2200 Temporary Shoring Left In Place (structure) SF
511.2300 Temporary Shoring Left In Place (location) SF
for providing a signed and sealed copy of the design; for removal or additional work required to leave in place; and for backfilling.
Effective with the December 2018 Letting 279 2019 Standard Spec ifications Section 512 Steel Sheet Piling
512.1Description
512.2Materials
512.2.1 Permanent Steel Sheet Piling
special provisions specify.
items.
piling the certified report of test or analysis as specified fo r mill inspection and tests in 506.3.21. 512.2.2 Temporary Steel Sheet Piling
Extend one foot or higher above the retained grade unless the p lans show a gr eater height. The contractor may employ used steel sheet piling in good condition instead of new material. Remove and dispose of temporary sheet p iling when no longer needed.
512.3Construction
512.3.1 Driving and Cutting Off 512.3.1.1 General
damage to adjacent facilit ies due to vibrations.
show. Ensure that the sheetpiles are within 6 inches of the pla n position after driving. Do not damage sheetpiles attempting to correct for misalignment.
Submit details of planned corrections to the engineer for revie w and approval before initiating any corrective action.
512.3.1.2 Driving System
elevation the plans show.
causes insufficient energy transfer or damages the sheetpiles. Do not return a component to service until the engineer determines that it has been satisfactorily r epaired or adjusted.
512.3.1.3 Cut-Offs
contractor's property. Dispose o f cut-offs not incorporated into the work. 512.3.2 Wales
length between corners and bolt to the piles. 512.3.3 Painting
512.4Measurement
completed. The department will obtain the measured quantity by multiplying the length of the wall the plans show by the length of sheeting required.
completed. The department will m easure the area of the wall fro m the sheet pile tip elevation to the top cutoff. The department will make no allowance for overlap of th e piles.
The department will measure the area from the sheet pile tip el evation to one foot above the retained