Effective with the December 2018 Letting 93 2019 Standard Speci fications Section 206 Excavation for Structures
206.1Description
bridges, and retaining walls. It a lso describes removing old su bstructure units within the space occupied by the ne w structure.
206.2Materials
other extraneous or perishable ma terial. The contractor may use engineer-approved material obtained from excavation.
material conforming to the requi rements for structure backfill obtained from excavation as specified under 104.8 .
206.3Construction
206.3.1 General
department will not classify this e xcavation as common, rock, o r marsh excavation under 205 or as dry or wet excavation.
structure. Dispose of material obtained from excavation. Backfi ll, compact, shape, slope, and clean the site.
necessary sheeting, shoring, bracing, draining, and pumping to allow constructing the substructure, above the seal, in the dry. Do no t use stream diversions and ea rth dikes instead of specified cofferdams or well-point systems, unless the engineer authorizes in writing. 206.3.2 Excavation Depth
order, in writing, changes in dimensions or elevation of footin gs necessary to secure a satisfactory foundation. 206.3.3 Cofferdams and Cribs
constructed, carried to adequate depths and heights, and are ma de watertight as necessary for the proper performance of the work. C onstruct cofferdams and cribs so that interior dimensions give sufficient clearance for the cons truction of forms and the insp ection of their exteriors, and to allow pumping from sumps outside the forms. If cofferdams or cribs ti lt or move laterally during the process of sinking, right, reset, or enla rge them to provide the necessary clearance. The contractor is responsible for any claims for damages resulting from the use o f a well-point system. 206.3.4 Protecting Concrete
stream and to prevent damage to the foundation by erosion. Plac e wales and cross braces at locations that allow construction of the su bstructure unit without constr uction joints other than those the plans show. If required to leave wales or braces in place, use only p ipe, precast concrete or rolled steel sections. Do not box out with timber braces. 206.3.5 Plans Required
cribs under 105.2 , showing the proposed method of cofferdam or crib construction for the file. At the engineer’s request, submit 2 additional copies of these plans f or review. If the engineer does not find the plans submitted for reviews atisfactory, make the required changes. Whether or not the engineer requests submittal of the plans or concurs in the use of the pl ans as submitted or corrected, the department will not relieve the contractor of the responsibility to secure a safe and satisfactory cofferdam or crib. 206.3.6 Removal
completion and curing of the subs tructure unit. Exercise care n ot to disturb or otherwise injure the finished masonry.
Effective with the December 2018 Letting 94 2019 Standard Speci fications 206.3.7 Excavation
elevations and measurements o f the existing ground and substruc ture units before disturbance and removal.
excavation as required by soil conditions to stabilize the sides for safe working conditions. Limit excavation to the quantity consid ered necessary for safety. If the plans require, shore the excavation instead of sloping the sides. If the plans do not require shori ng, the contractor may elect to use, at no expense to the department, shoring rather than excavating to a slope. http://www.dol.gov/dol/cfr/title_29/ 206.3.8 Preparing Foundation for Footings
surface, either level, or ste pped, or serrated. Clean out and f ill seams with cement mortar or grout.
bottom of the excavation. Do no t make the final removal of the foundation material to grade until just before placing the masonry. Pro tect surfaces from freezing afte r excavation and before placing concrete for the footing. Do no t place concrete on frozen subgr ade.
driving operations in the pit . After completing pile-driving op erations in a given pit, remove loose and displaced material in the pit to the elevation of the bottom of the footings.
approval. In this case, fill the ent ire excavation with concret e to the elevation of the top of the footing.
the keyway to plan dimensions. F or footing excavations in sound rock, fill the footing with concrete to the elevation of the top of the rock or the top of the footing, whichever is lower. 206.3.9 Dewatering
foundation material or concrete ingredients.
at least 24 hours afterwards, unless done from a suitable sump outside the forms. Do not pump from within any foundation enclosure while depositing concrete under water in the enclosure. Do not begin pumping to dewater a sealed coffe rdam until the seal has set su fficiently to withstand the hydrostatic pressure, or until at least 3 days have elapsed since placing the seal. 206.3.10 Subfoundation Course 206.3.10.1 Bridges and Retaining Walls
excavation is kept dewatered for a reasonable length of time, furnish and place a subfoundation course if the engineer directs. Construct a subfoundation cours e of structure bac kfill conforming to 210, or other engineer-approved materials. Place the subfoundation course directly below the elevation of the bottom of the footings to the depth the engineer designates. 206.3.10.2 Culverts
approved materials, directly below the elevation of the bottom of the slab between the cutoff walls of culverts. 206.3.10.3 Structural Plate Pipe and Pipe Arches
specified for erection in 527.3.2. 206.3.11 Foundation Seal
before placing the masonry, the engineer may require constructi on of a concrete foundation seal of necessary dimensions. After the seal sets, dewater the foundati on excavation and place the balance of the masonry in the dry. Place foundation seals the plans do not show below the bottom of the footing unless authorized other wise. Place concrete in foundation seals as specified for depositing concrete underwater in 502.3.5.3 .
Effective with the December 2018 Letting 95 2019 Standard Speci fications 206.3.12 Inspection
the engineer approves t he depth of the excavation and the chara cter of the foundation material. 206.3.13 Backfilling 206.3.13.1 General
before excavation. Do not place backfill above the required section for the finished work. If placing backfill, provide allowance for settlement.
involved of falsework , sheet piling, cribbing, shoring, bracing, forms, and rubbish. Backfill the cofferdams before removing the sheeting, unless the engineeral lows otherwise.
sheet piling, cribbing, shoring, and bracing as backfilling pro gresses.
slopes as necessary to prevent slipping and wedging of the back fill.
If practicable, uniformly raise l ayers on all sides of each sub structure unit or cu lvert. Surround the stone used in backfilling by finer material. Compact each layer , before placing the next layer, by using engineer-approved rollers or portable mechanical or pneumatic t ampers or vibrators.
not use water to expedite backfill settlement except with the e ngineer’s written approval. However, the engineer will not require the contractor to dewater the excavation before placing backfill. If allowed to use water, keep the entire exca vation inundated while placing b ackfill, except if jetting.
alignment. Gradually deposit the backfilling material transported in trucks or other vehicles instead of dumping the entire contents as o ne mass. Lower clams, dippers, and similar backfill containers to within 5 feet of previously depo sited backfill, or of the water surface, before dumping.
spread and place the end-dumped material in the above-described 8-inch horizontal layers. Do not place backfill in or from narrow ramps or driveways up to or fr om the structure.
and pipe arches under 527.3.3.
of the weep holes, unless designated otherwise.
gravel or crushed sto ne behind the culvert, abutment, or retaining wall at the level of the weep holes according to dimensions the plans show.
surface preparation, dampproofi ng, and waterproofing of the wor k to be backfilled. 206.3.13.2 Self-Supported Abutments and Retaining Walls 206.3.13.2.1 General
206.3.13.2.2 Backfill on One Side of the Structure
expiration of the minimum time periods tabulated below: GENERAL PURPOSE HIGH EARLY STRENGTH COMPRESSIVE STRUCTURE TYPE[1] CONCRETE CONCRETE STRENGTH i n days[2] in days[2] in psi Abutment type A1, A2, A5[4] 2 1 2000 Abutment type A3[3] 2 1 2000 Abutment type A4 14 7 3000 Full retaining abutments 14 7 3000 Box culverts[5] 14 7 3000 Retaining walls and end walls 14 7 3000
Effective with the December 2018 Letting 96 2019 Standard Speci fications [1] Abutment types: A1: Body about 5 feet tall wi th one row of piles. A2: Body about 5 feet tall wi th 2 rows of piles. A3: Body about 5 feet tall with backwall and 2 rows of piles A4: Body about 13 feet tall with bac kwall and 2 or more rows of piles. A5: Body about 10 feet tall with one row of piles extending to within 2 feet of abutment top. Full retaining: Body extending from lower roadw ay/river elevati on to beam seats. [2] Only count days wher e the concrete temper ature did not fall be low 40 F. [3] Upon obtaining the required compressive strength, the contract or may backfill the bo dy of A3 abutments before placing the backwall. [4] Place and cure the superstructure before backfilling A5 abutme nts as specified in 206.3.13.3 . [5] Place and cure the top before ba ckfilling except as allowed un der 206.3.13.3 . 206.3.13.2.3 Backfill on Both Sides of the Structure
retaining walls and piers unif ormly and simultaneously on both sides to the elevation of the front ground surface immediately upon removing the forms. 206.3.13.3 Rigid Frame Structures
placing and curing that superstructure.
compressive strength of 2000 psi. Do not c omplete the backfill until the top is placed and conforms to 206.3.13.2.2 . 206.3.14 Incorporating or Dis posing of Excavated Material
engineering properties for ripr ap or backfill. If the contract contains the Excavation Common or Borrow bid items and embankment material is needed at the time of disp osal, use the balance of the excavated material, with suitable engineering properties, in th e embankment.
206.3.15 Preserving Channels and Waterways
not disturb the natural stream bed next to the structure. If per forming any excavation or dredging at the site of the structure before cais sons, cribs, or cofferdams are sunk in place, backfill these excavations to the original ground surface or stream bed with material sati sfactory to the engineer after placing the foundation.
cofferdams to the stream bed elev ation, unless specified otherw ise.
channels, ditch lines, or waterw ays to the level of the finishe d streambed or ground line at no expense to the department. 206.4 Measurement
each structure acc eptably completed.
acceptably completed. 206.5 Payment 206.5.1 General
items: ITEM NUMBER DESCRIPTION UNIT
206.1000 Excavation for Structures Bridges (structure) LS
206.2000 Excavation for Structures Culverts (structure) LS
206.3000 Excavation for Structures Retaining Walls (structure) LS
206.4000 Excavation for Structures Structural Plate Pipe or Pip e Arches (station) LS
206.5000 Cofferdams (structure) LS
Effective with the December 2018 Letting 97 2019 Standard Speci fications (2) The department will pay for material excavated under this section and used in embankments at the contract unit price for Borrow , or absent the Borrow bid item, at the contract unit price for Excavation Common. The department will measur e material as specified for e xcavation in 205.4.1 .
the Concrete Masonry Seal b id item as specified in 502.5 .
Excavation for Structures bid items. Unforeseen structures are man-made structures not visible when visiting the construction site and that the plans do not list o r show. The department will pay for removing all or part of a culver t or bridge as specified in 203.5 . The department will pay for excavating other unforeseen structures as ex tra work. Other removals visible when visiting the construction site or that the plans list or show a re incidental to the work. 206.5.2 Excavation for Structures
excavation, including excavating for seals, girders, projections, and subfoundation courses; for preparing foundation; and for backfilling and compacting space excavated and not occupied by the new structure, including subfoundation course.
dewatering except, if the contract contains the applicable bid items, the department will pay separately for this work.
and below the plan elevation of the bottom of the footings or f loor of culverts, or the invert of structural plate pipe or pipe arches as the plans show for the specific un its.
between planes lying one foot above and below the plan elevatio n of the bottom of the footing, for each stepped section; or excavation between planes lying one fo ot above, below, and parallel to the slope established by t he plan elevations for the bottom of the footing.
the elevation of the bottom of t he footings or floor or invert as indicated on the plans, the department will pay for this excavation as extra work.
Grubbing bid items as specified in 201.5 .
item as specified in 210.5 . 206.5.3 Cofferdams
including well-point systems, sheeting, shoring, and bracing; f or constructing, mai ntaining, backfilling, and removing cofferdams and cribs; and for pumping and dewateri ng.
Effective with the December 2018 Letting 98 2019 Standard Speci fications Section 207 Embankment
207.1Description
under the bid items in the road way and drainage excavation, bor row, or excavation for structures sections.
207.2Materials
perishable material. The contractor may place excess unstable topsoil and other unstable soil in embankments outside the roadwa y foundation as defined in 101.3 . Do not place frozen soil in embankments within the roadway foundation.
concrete or other materials that significantly affect scarifyin g, compacting, and finishing the subgrade.
piling through, use materials that do not contain stone or broken concrete retained on a 3-inch sieve and free from quantities of gravel, stone, or broken concrete p assing a 3-inch sieve or other material that significantly affects bori ng the holes or driving the pili ng.
207.3Construction
207.3.1 General
prepare the roadway foundation as specified in 205.3.2, unless the contract specifies otherwise.
place embankment on frozen subgrade.
winter if weather conditions prevail that cause substantial fre ezing of the materials during placement, except if using materials from rock excavation, or of a granula r nature and that contain only minor quantities of silt, clay, loam, or similar materials. 207.3.2 Placing Layers
ravines. Construct the embankmen t in layers by spreading and le veling the material during placement. Spread individual layers evenly to uniform thickness throughout and approximately parallel with the finished grade for the full width of the embankment, unless dir ected otherwise. Place the material in layers generally no thicker than 8 inches, to secure the required compaction. On side hills too steep to operate hauling equipment, over low wet ground, in marshes, or if filling in water, provide a single layer, just thick enough to support the hauling equipment while placing subsequent layers. 207.3.3 Placing in Marsh
material. Begin filling at one end of the marsh and proceed acr oss the marsh, close enough to the excavating operations to allow the equipment to remove any disp laced peat or muck as it accumulates ahead of the advancing embankment toe. Place fill material in a way that, and to a height that, effectively displaces unstable material from within the area of the proposed embankment. Build temporary surcharges, as required, to the height and horizontal dimensions the plans show. Progressively move temporary su rcharges ahead as the embankment advances.
layers and compact it to t he extent practicable. 207.3.4 Placing Rock
makes placing in 8-inch layers impracticable, then place the em bankment material in layers no thicker than the approximate average size of the larger rocks. Avoid ne sting and fill the voids with smaller stones and satisfactory soil or rock fines. 207.3.5 Hydraulic Fills
specified in 208.3 and construct as the engineer directs.