Effective with the December 2018 Letting 104 2019 Standard Spec ifications Section 209 Granular Backfill
209.1Description
as follows:
209.2Materials
209.2.1 General
particles or sand-sized particles mixed with gravel, crushed gr avel, or crushed stone. Do not use crushed concrete or reclaimed asphalt.
than or equal to 6. The contractor may substitute grade 1 for grade 2 material. 209.2.2 Gradation
- For the entire sample, conform to the following gradation lim its: PERCENT PASSING BY WEIGHT SIEVE GRADE 1 GRADE 2 6-inch 100 100 3-inch 85 - 100 85 - 100 No. 4 25 - 100 25 - 100 - For the portion of the sample passing the No. 4 sieve, confor m to the following gradation limits: PERCENT PASSING BY WEIGHT SIEVE GRADE 1 GRADE 2 No. 4 100 100 No. 40 0 - 75 ___ No. 100 0 - 15 0 - 30 No. 200 0 - 8.0 0 - 15.0 209.2.3 Sampling and Testing
Sampling[1] ............................................................................................................................. ........... AASHTO T2 Percent passing t he 200 sieve ................................. ............................................................... ........ AASHTO T11 Gradation[1] ............................................................................................................................. ........ AASHTO T27 Liquid l imit .................................................. ............................................................... ...................... AASHT O T89 Plasticity index and plastic limit ............................ ............................................................... ........... AASHTO T90 [1] As modified in CMM 8-60. 209.2.4 Source
responsible for negotiating with property owners to obtain gran ular material.
material disposal under 104.9 and 208.3 .
passing the No. 200 sieve before excavating the granular material.
after removing overburden and bef ore removing granular material to allow taking accurate measurements. After removing the required quantity of granular material, repeat trimming and shaping of the areas to allow taking accurate measurements.
are neatly constructed.
Effective with the December 2018 Letting 105 2019 Standard Spec ifications 209.3 Construction
embankment construction in 207. If granular backfill is specified for other applications, place and compact as specified for those applications.
209.4Measurement
209.4.1 General
completed. For minor quantities, the engineer may measure by th e cubic yard in the vehicle. The department may convert the measur ement between weight and volum e as specified in 109.1 .
backfilling marsh excavation and in its final position for othe r applications.
tickets submitted daily. Submit a ticket for each load showing the material, net weight, date, and project ID. For material with mor e than 7 percent moisture, the department will reduce the ticket weight by the weight of water exceeding 7 percent. The department will determine moisture content as a percent of dry weight.
contract designates, or the engineer directs. 209.4.2 Measured in Original Position
208.4.2 . Prepare the pit for measurement as specified in 209.2.4 . 209.4.3 Measured in Final Position
truncated prism method. The department will measure material in its final position and compacted condition.
subgrade, the department will comput e volume using the dimensio ns of the plane of the earth subgrade, the depth of the excavation, and the limits of the ar ea that the engineer requires excavated and backfilled.
209.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
209.1100 Backfill Granular Grade 1 CY
209.1500 Backfill Granular Grade 1 TON
209.2100 Backfill Granular Grade 2 CY
209.2500 Backfill Granular Grade 2 TON
stripping, clearing, grubbing , excavating, shaping, trimming, a nd cleaning up the pits; for salvaging, stockpiling, rehandling, and spreading salvaged material over excavated pit areas; and for disposing of surplus materials.
bid item, the department will pays eparately for compaction and dust control water under 624.5 .
pay at the contract unit price for grade 2 material.
separately as specified for borrow sites and material disposal sites under 628.5.1.
Effective with the December 2018 Letting 106 2019 Standard Spec ifications Section 210 Structure Backfill
210.1Description
culverts, retaining walls, and structural plate pipes and pipe arches.
210.2Materials
210.2.1 General Requirements
particles or sand-sized particles mixed with gravel, crushed gr avel, or crushed stone. Do not use crushed concrete or reclaimed asphalt.
than or equal to 6. The contract or may substitute type A for type B material. 210.2.2 Gradation
- For the entire sample, conform to the following gradation lim its: PERCENT PASSING BY WEIGHT SIEVE TYPE A TYPE B 3-inch 100 100 No. 4 25 - 100 25 - 100 - For the portion of the sample passing the No. 4 sieve, confor m to the following gradation limits: PERCENT PASSING BY WEIGHT SIEVE TYPE A TYPE B No. 4 100 100 No. 40 0 - 75 ___ No. 100 0 - 15 ___ No. 200 0 - 8.0 0 - 15.0 210.2.3 Sampling and Testing
Sampling[1] ............................................................................................................................. ........... AASHTO T2 Percent passing t he 200 sieve ................................. ............................................................... ........ AASHTO T11 Gradation[1] ............................................................................................................................. ........ AASHTO T27 Liquid l imit .................................................. ............................................................... ...................... AASHT O T89 Plasticity index and plastic limit ............................ ............................................................... ........... AASHTO T90 [1] As modified in CMM 8-60. 210.2.4 Source
responsible for negotiating with property owners to obtain gran ular material.
material disposal under 104.9 and 208.3 .
passing the No. 200 sieve before excavating the granular material.
are neatly constructed.
210.3Construction
place and compact as specified for those applications. 210.4 Measurement
completed. The department will only include material placed within the limits and in the places the plans show, the contract desig nates, or the engineer directs. F or minor quantities, the engineer may measure by the cubic yard in t he vehicle. The department may co nvert the measurement between weight and volume as specified in 109.1 .