Effective with the December 2018 Letting 138 2019 Standard Spec ifications Section 350 Subbase
350.1Description
350.2Materials
not exceed 3/4 of the compacted thickness of any individual layer being placed.
- Within the right-of-way as the plans show or as allowed in 104.8 . - Beyond the right-of-way as specified for borrow in 208.3 .
350.3Construction
350.3.1 General
subbase. With the engineer's approval, the contra ctor may use c ement, fly ash, lime, or similar engineer-approved materials to stabilize the subbase.
layers, construct successive layers in the sequence and at the times the engineer directs. The engineer will phase that construction to provide a usable surface for traffic. 350.3.2 Preparing Subgrade
211. Excavate and backf ill areas of soft, yielding, or spongy subg rade or otherwise treat unstable areas as the engineer directs. 350.3.3 Constructing Subbase
subgrade material. Do not places ubbase material on a frozen su bgrade, subgrade covered by ice or snow, or on a wet or soft subgrade unless the engineer specific ally directs.
Follow the standard compacti on methods specified in 207.3.6.2 unless the contract requires the special compaction methods specified in 207.3.6.3 .
Maintain the finished subbase unt il it is covered, or until the engineer accepts the work if the contract does not require covering the subbase.
350.4Measurement
350.4.1 General
acceptably completed. 350.4.2 By Volume
original source position using one of the following methods: - Average end areas, with no correction for curvature. - Truncated prisms.
deposit. Notify the engineer before removing subbase material. The department will not measure material removed before the engineer measures the original volu me.
will determine the capacity of each vehicle used to the nearest 1/10 cubic yard. 350.4.3 By Weight
tickets submitted daily. Submit a ticket for each load showing the material, net weight, date, and project ID. For material with mor e than 7 percent moisture, the department will reduce the ticket weight by the weight of water exceeding 7 percent. The department will determine moisture content as a percent of dry weight.
Effective with the December 2018 Letting 139 2019 Standard Spec ifications 350.4.4 By Area
thickness the contract specifies or the engineer directs. For s ubbase with sloping sides, the department will compute area based on the mean width of the top and bottom of the layer. The department will measure additions ordered to correct for settlement of the earth subgrade based on the in place volume converted to an equivalent area.
350.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
350.0102 Subbase CY
04 Subbase TON
10 - 0199 Subbase (inch) SY
loading, and hauling material from within the right-of-way or furnishing material as required from beyond the right-of-way; and for providing and maintaining the subbase.
associated with the procurement of material from beyond the right-of-way are incidental to the Subbase bid items.
Effective with the December 2018 Letting 140 2019 Standard Spec ifications Section 390 Base Patching
390.1Description
mixtures for overlaying with new pavement.
390.2Materials
concrete, grade B, B-FA, B-S , B-IS, B-IP, or B-IT, under 501, except that under the Base Patching Concrete SHES bid item, furnish concrete as specified for SHES concrete repair and replacement in 416.2 . Provide QMP for class II ancillary concrete as specified in 716.
390.3Construction 390.3.1 General
restrict operations to one lane at a time. Perform work to caus e the least possible inconvenience to traffic.
locations the plans show or the engineer directs in the field. Saw the connecting edges as true and perpendicular as possible as specified for sawing pavement in 690. Remove the pavement without injury to the remaining pavement. D ispose of removed material a s specified in 204.3.1.3 .
the thickness of the contiguous pavement, including the existin g asphaltic pavement or surfacing. 390.3.2 Concrete Patching
off and finish flush with adjoining surfaces. The engineer will not require forms un less necessary to provide the required edge, grade, or alignment.
compound conforming to 501.2.9 . Protect as specified for concrete pavement in 415.3.14 . Open to traffic as specified for concrete base in 320.3 . 390.3.3 Asphaltic Patching
the required grade and contour wit h rakes and lutes. Do not rak e dumped material into the patch. The engineer will not require forms unless necessary to provide the required edge, grade, or alignment.
otherwise, compact each layer to a thickness of 6 inches or less. Roll the top layer until flush with the adjacent surface.
390.3.4 Special High Early Strength Concrete Patching
- The contractor may delay removal for up to 14 calendar days after cutting the existing pavement. - Open to traffic as specified for concrete base in 320.3 .
compound conforming to 501.2.9 . Do not apply excess curing com pound that could cause slippery pavement under traffic.
390.4Measurement
completed.
SHES by the square yard acceptably completed.