Effective with the December 2018 Letting 157 2019 Standard Spec ifications Section 416 Concrete Pavement - Appurtenant Construction
416.1Description
to new concrete and drilling in dowel bars to transfer load bet ween existing and new concrete; concrete surface drains; concrete rumble strips; and concrete p avement repair and replacement.
416.2Materials
416.2.1 General
QMP for class II ancillary c oncrete as specified in 716.
even where the contract does not require it.
grade 1 or grade 2.
of approximately 30 percent. 416.2.2 Concrete Driveways, Truck Aprons, and Surface Drains
416.2.3 Tie bars and Dowel bars 416.2.3.1 General
416.2.3.2 Epoxy for Anchoring Dowel Bars and Tie Bars
AASHTO M235, grade 3 - non-sagging consistency, t ype IV epoxy, except as modified below:
by the manufacturer of the product.
concrete, or at 3 days for grades A, C, and E concrete. Test ac cording to AASHTO M235 and ASTM D695, with the followi ng restrictions:
or analysis from a qualified i ndependent laboratory, to the eng ineer certifying that the epoxy conforms to these specifications. Identify the temperature classes and compressive strength cure times for which the product is certified.
requirements specified for epoxy. 416.2.4 Concrete Pavement Repair and Replacement
concrete as specified in 501. 416.2.5 Special High Early Strength Concrete Pavement Repair and Replacement 416.2.5.1 Composition and Proportioning of Concrete
concrete. Determine materials a nd proportions of the concrete m ixture to obtain a minimum compressive strength in the co ncrete of 3000 psi within 8 hours of placement. The contractor may add one or a combination of admixtures to the ingredients or to the mixture in order to obtain the required minimum strength and required air content. Do not retemper the concrete mixture.
Ensure that job-mixed solutions contain 1.0 pounds per quart of 77 percent calcium chloride or 0.9 pounds per quart of 90 percent cal cium chloride. Do not exceed the manufacturer's recommended maximum dosage. If the engineer requests, provide a written cop y of the manufacturer's dosage recommendations.
Effective with the December 2018 Letting 158 2019 Standard Spec ifications (3) Add calcium chloride, in solution, by an engineer-approved pro cedure to the batch ingredients while placing them in the mixer. Provide sufficient water in job-mixe d solutions to dissolve the calcium chloride completely, and ensure that the solution is of a unifo rm and known conce ntration. Reduce the quantity of mixing water by the quantity of solution used. Intr oduce the correct quantity of calcium chloride into the mixer using a method by which the quantity added cannot vary appreciably from the target value.
aggregates, or within 30 minutes a fter adding an accelerating a dmixture, whichever comes sooner. 416.2.5.2 Evaluating Strength
that the required strength is obt ainable in the field with the materials used and at the various temperatures encountered. Conduc t a continued strength evaluati on, if the engineer requires, during the course of the work to ensure continued compliance with the strength requirements.
the engineer to observe cylinder production. Use a department q ualified laborat ory and an HTCP- certified technician to conduct preliminary and continued stren gth evaluations. Base each reported value on a minimum of 2 cylinders. After submitting data showin g obtainment of the required strength, do not change the mix without first submitting a complete new s et of test data showing compliance with the requirements.
416.3Construction
416.3.1 General
cracking as specified in 415.3.17. Repair cracked concrete as the engineer directs. 416.3.2 Concrete Driveways and Truck Aprons
engineer-approved wood or plastic fo rms. Color concrete for rou ndabout truck aprons red as specified in 405. 416.3.3 Placing Tie Bars in Existing Concrete 416.3.3.1 Force Driven
inches into the prepared hole as the plans show. 416.3.3.2 Epoxied
into the existing concrete with an epoxy conforming to 416.2.3.2 and install conforming to 416.3.4 except no bond breaker is required. 416.3.4 Placing Dowel Bars in Existing Concrete
bars into the existing concrete with an epoxy conforming to 416.2.3.2 .
bar.
thick enough to remain in the hole. Insert a sufficient volume of epoxy into the hole to provide a small quantity of excess material at the face of the concrete after f ully inserting the dowel.
retaining ring over the bar, and push the ring flush against th e concrete surface to retain the epoxy.
deposit the epoxy at the back of t he drilled hole. Use a system equipped with a means of checking the mix ratio of the epoxy components . Use the manufacturer’s recom mended mix ratio and check the ratio at least once a day.
equipment capable of thoroughly mixing and depositing the epoxy at the back of the drill hole.
Effective with the December 2018 Letting 159 2019 Standard Spec ifications 416.3.5 Surface Drains
permanent drains are completed.
and cure the concrete conforming to 415.3 .
restore the grade after placement. 416.3.6 Concrete Rumble Strips
strips into new concrete pavement or, if inlaid into existing H MA or concrete pavements, into work built under the Concrete Pavement Replac ement bid item except use con crete conforming to 416.2.2. Do not apply rumble strips across bridges.
size, shape, spacing, and alignment the plans sh ow. Ensure that cutting heads are on a suspension independent from the power unit to allow the heads to self-alig n with slopes and irregularities. Also ensure that the machine has a guidance system that consistently provides the plan alignment of the rumble strips.
the size, shape, spacing, alignm ent, and smoothness the planss how.
desired surface inside each depr ession without damaging the pav ement. Place rumble strips in the pattern and shape the plans show. For shoulders carrying temporary traffic during construction, do not install rumble strips until after routing traffic back to the m ainline.
vacuum the traveled way pavement and shoulder areas. Sweep away or vacuum up milling debris before opening adjacent lanes to traffic. Dispose of waste material as specified in 203.3.4 ; do not place on the finished shoulder surface. 416.3.7 Concrete Pavement Repair and Replacement
the pavement repair plan details. F or individual repair areas at least one lane wide and greater than 15 feet to less than 300 feet long, conform to the pavement replac ement plan details.
- Remove concrete pavement, rem ove asphaltic patch, and prepare the base as specified under 416.3.8.1. - Place concrete in repair areas as specified under 416.3.8.2 . Disregard the same-day requirements for completion of curing and opening to traffic and instead conform to 415.3.12 through 415.3.15 . - Place concrete in replacement areas conforming to 416.3.8.3 except disregard the same-day requirements for completion of curing and opening to traffic. 416.3.8 Special High Early Strength Concrete Pavement Repair and Replacement 416.3.8.1 General
pavement repair plan details. For individual repair areas at le ast one lane wide and greater than 15 feet to less than 300 feet long, conform to pavement replacemen t plan details. 416.3.8.1.1 Removing Concrete Pavement
existing slab, make a straigh t full lane-width full depth saw c ut to facilitate removal without damaging the remaining pavement. Ensure that repair areas in adjacent la nes match longitudinally.
concrete pavement repair and replacement details show. Ensure t hat the length of the damage repair and the adjacent planned repair ar e the same and both are a ful l lane wide. If damage is done to pavement not adjacent to a planned repair, conform to the minim um removal length the repair and replacement details show and remove and repair the full lane width.
ensure that all slabs have been removed from the project limits and stored away from the roadway. Incorporate or dispose of removed pavement as specified in 203.3.4.
Effective with the December 2018 Letting 160 2019 Standard Spec ifications (4) Replace areas of the asphaltic sh oulder removed during these pavement removal operations to the elevation of the adjacent shoulde r using a commercially produced asphaltic patching material. Before patching, clean, dry, and provide a uniform edge for the repair area. 416.3.8.1.2 Removing Asphaltic Patches
concrete as the plans show. 416.3.8.1.3 Base Course
rubble and foreign material wit h minimal disturbance of the bas e.
aggregate base or additional concrete. 416.3.8.2 Placing Concrete in Repair Areas
pavement. Place each repair i n one continuous, full depth operation. Consolidate the concrete in place using an immersion type vibrator . Finish the surface by screedi ng twice, floating, and texturing. Orient the length of the screed parallel to the pavement centerline, u nless the repair is over 12 feet in length.
pavement. Make the longitudinals urface form a straight line fr om edge to edge with a tolerance of +/- 1/8 inch.
pavement and, if the abutting pavement is concrete, match the e xisting pavement texture. Cure, protect, open to service, and adhere to cold weather concreting as specified in 415.3.12 through 415.3.15 . 416.3.8.3 Placing Concrete in Replacement Areas
removing the old pavement. Place each repair in o ne continuous, full-depth operation conforming to 415.3.6 through 415.3.15 except date each replacement slab with the month and year of c onstruction.
416.4Measurement
completed, measured as specified in 415.4 for Concrete Pavement including the intersection with the sidewalk and the associated driveway apron. The department will only measure area outside the specified limits for the pavement, curbs, gutters, combination curb & gutter or other structures.
completed.
bar acceptably completed.
completed, based on the dimensions the plans show or the engineer directs.
completed, measured as the length along each side of the traveled way from the center of the first groove in a segment to the center of the last groove in thatse gment. A segment is a series of grooves including 50-foot and shorter gaps as well as skips at transverse joints the plans show. Gaps greater than 50 feet define a new s egment. The department will deduct for skips at transvers e joints greater than the plans show.
completed, measured to include the area between the milled or c ast-in-place grooves, or if inlaid into existing HMA or concrete pavement, the area of the inlay. The d epartment will not deduct the area of embedded fixtures with an area of one square yard as measured i n the plane of the pavement surface.
bid items by the square ya rd acceptably completed.
416.5Payment
416.5.1 General
items:
Effective with the December 2018 Letting 161 2019 Standard Spec ifications ITEM NUMBER DESCRIPTION UNIT
416.0160 - 0199 Concrete Driveway (inch) SY
416.0260 - 0299 Concrete Driveway HES (inch) SY
416.0508 - 0520 Concrete Truck Apron (inch) SY
416.0610 Drilled Tie Bars EACH
20 Drilled Dowel Bars EACH
416.1010 Concrete Surface Drains CY
15 Concrete Surface Drains HES CY
416.1110 Concrete Shoulder Rumble Strips LF
80 Concrete Intersection Rumble Strips SY
416.1710 Concrete Pavement Repair SY
15 Concrete Pavement Repair SHES SY
20 Concrete Pavement Replacement SY
25 Concrete Pavement Replacement SHES SY
415.5.1 and 415.5.2 for Concrete Pavement. The depar tment will pay separately for coloring concrete as required for roundabout truck aprons under the Coloring Concrete Red bid item.
holes in concrete not placed under the contract; and for epoxyi ng or driving.
drilling holes in concr ete not placed under the contract; and f or epoxying.
for steel reinforcement and dow el and tie bars; and for excavating, preparing the subgrade and aggregate base, and backfilling.
vacuuming; and for disposing of waste materials.
for sweeping or vacuuming; and for disposing of waste materials . The department will pay separately for new concrete pavement under the Concrete Pavement bid items; and for concrete inlaid in existing HMA or concrete pavement under t he Concrete Pavement Replacemen t bid item.
compensation for furnishing, hauling, preparing, placing, curin g, and protecting materials; for replacing damaged pavement designated to remain in place; for removing an d disposing of existing pavements and excavated materials; for re pairing asphaltic shoulders; for sawing joints; fo r preparing the foundation; for backfilling; and for testing concrete cylinders . The department will pay for individual repairs at least one lane wide and greater than 15 feet to less than 300 feet long as Concrete Pavement Replacement. Payment inc ludes jointing a nd providing t ie bars and dowel bars in unhardened concrete. The departm ent will pay separately for ass ociated work as follows: - For tie bars and dowel bars pro vided in concrete not placed u nder the contract, exclusive of those necessary to repair contractor-caused damage, under the Drilled Tie Bars and Drilled Dowel Bars bid items. - For sawing existing concrete for removal, under the Sawing Co ncrete bid item as specified in 690.5 . - For repairs 300 feet long or longer, under the Removing Pavement bid item as specified in 204.5 and the Concrete Pavement bid items as specified in 415.5 . 416.5.2 Adjusting Pay for Anc illary Concrete Crack Repairs
& gutter whether separately or integrally placed, curb, gutter, medians, sidewalks, loading zones, safety islands, steps, concrete surface drains, truck aprons, and driveways. The engineer will allocate responsibility and costs for crack repairs, mobilization for tr affic control, and traffic control devices, according to CMM 4-24 . The department will adjust pay under the Crack Repair Ancilla ry Concrete administrative item.
furnishing and placing materials including dowel bars and steel reinforcement; drilled tie and dowel bars; and all incidentals. The engineer will compute the pay ad justment for repair costs as the contract unit price for the item, times the quantity replaced, multiplie d by the appropriate multiplier as follows:
Effective with the December 2018 Letting 162 2019 Standard Spec ifications COMPUTED AMOUNT MULTIPLIER PER Q UANTITY FOR ANCILLARY CONCRETE ITEM SHARED REIMBURSEMENT TOTAL REIMBURSEMENT REPLACED MULTIPLIER MULTIPLIER Quantity replaced 6 12
Effective with the December 2018 Letting 163 2019 Standard Spec ifications Section 420 Diamond Grinding
420.1Description
restoration of existing or re paired pavement and profile correction for new pavement. 420.2 (Vacant)
420.3Construction 420.3.1 General
free of excessively large scarif ication marks, and has the grad e and cross slope the plans show or the engineer specifies. Do not damag e the remaining pavement. Do no t grind deeper than 3/4 inch from the top of the original surface.
pavement repair operations befor e grinding. Begin and end grinding at lines perpendicular to the roadway centerline at the projec t limits. Do not overlap adjace nt grinding passes by more than 1-inch. Do not leave un-ground surface area between passes.
of the joints and cracks. Grind warped and curled slabs as requ ired to provide an acceptable ride. Provide smooth transitions from the edge of the mainline to sho ulders, adjacent lanes, and ramps leaving no more than a 3/16-inch ridge at transitions. Grind adjacent pavement and paved shoulders as necessary to feather in a smoot h transition and maintain drainage. Do not grind approach slabs unless necessary to provi de a smooth transition.
lane including feathered areas of t he shoulder. Ensure that the finished cross slope conforms to the plans and has no depressions or slope misalignment greater than 1/4-inch in 12 feet when measured perpendicular to the centerline with a 12-foot straightedge.
diamond ground surface to the top of the fixture. 420.3.2 Equipment 420.3.2.1 General
texturing concrete. Equip grinding machines with diamond blades and a vacuuming system capable of removing liquid and solid residue from the ground surface. Shro ud the machine to prevent discharging loosened material into adjacent work areas or live traffic lanes.
material remaining in place.
round. Stop grinding and immedi ately replace out-of-round wheels. 420.3.2.2 Continuous Grinding
machine, including the grinding head, weighs 35,000 pounds or m ore, will grind a strip at least 4 feet wide, and has an effective wheel base of 25 feet or more. 420.3.2.3 Intermittent Grinding
grind a strip at least 3 feet wi de and has an effective wheel b ase of 12 feet or more. The engineer may require continuous grinding equipment if intermittent grinding equipment does not produce acceptable results. 420.3.3 Final Surface Finish
texture with corrugations parallel to the outside pavement edge .
aggregate type. Determine the seq uence of operations and number of passes required to meet the specifications.
as follows: For limestone: 0.09 to 0.11 inches between grooves.