Effective with the December 2018 Letting 322 2019 Standard Spec ifications Section 601 Concrete Curb and Gutter
601.1Description
reinforcement.
601.2Materials
Joint filler .................................................. ................................................................................................ 415.2.3
in 716. Provide QMP for class II ancillary concrete as specified in 716.
601.3Construction
601.3.1 General
ancillary concrete. Repair cracke d concrete as the engineer dir ects. 601.3.2 Preparing the Foundation
required for placing concrete. Remove and replace soft or unsui table material with suitable material. Compact thoroughly and finish the foundation or material underlying the proposed curb, gutter, or curb & gutter to a firm, true surface . Thoroughly moisten the foundation immediately before placing the concrete.
thickness, and section the plans show.
& gutter at the locations, thickn ess, and section called for.
constructed as specified for underdrains in 612, where the plans show or the engineer directs. 601.3.3 Forms
displacement during depositing and consolidating the concrete. Use surfaced planks for wood forms at least 2-inch nominal thickness stock, except for sharply curved sections. Use metal forms of engineer- approved section. Use forms tha t are the full depth of the required curb, gutter, or curb & gutter sections and designed to allow secure fastening. If used, const ruct and shape face boards, so that their lower edge conforms to the lines and radius shown by the cross-section for the pertinent structure the plans show. For curves of 100-foot radius or less, use flexible or curved forms of proper radius. Clean and oil forms before placing concrete against them. 601.3.4 Placing Concrete
resulting curb, gutter or curb & gutter shall equal or exceed that produced by forming.
process, deposit the concrete in the forms to the proper depths , spade against the forms, and consolidate thoroughly. Use mechanical vibration for concrete with slump less than 2 inches. After consolidation strike off, and finish to the required section.
gutter, to adjoining concrete pavement by placing specified tie bars if and as the plans show.
Use only cast-in-place tie bars in construction joints between pavement and curb, gutter, or curb & gutter placed under the contract.
the curb, gutter, or curb & gu tter directly opposite constructi on or contraction joints in adjoining concrete pavement and at the requi red spacing in curb, gutter, or curb & gutter adjoining asphaltic pavement. Space joints between 6 feet and approximately 20 feet apart, as the engineer directs.
after the concrete sets suffici ently to prevent raveling during sawing, and before shrinkage cracking takes place. If this method resu lts in random c racking, then form an induced plane of weakness.
Effective with the December 2018 Letting 323 2019 Standard Spec ifications (7) If using separators, remove them as soon as possible after str iking off, consolidating, and setting sufficiently to protect the joint width and shape. If using fac e forms, remove them for finishing curb face and fillets as soon as the concrete retains its shape.
and driveways at locations and as the plans show. 601.3.5 Finishing
back edge of curbs, the edge o f the gutter next to the pavement , and edges next to expansion joints or induced contraction joints, w ith a 1/4 inch radius edger. 601.3.6 Expansion Joints
surfacing. Locate joints every where that tangent and radial cur b, or curb & gutter meet; on each side of every inlet 3 feet from the inlet, but no closer than 6 feet from another joint; and on tangent sections place between 6 feet and 300 feet.
expansion joints, then place expansion joints to match the expa nsion joint locations in the pavements.
of gutters. Use 3/4-inch wide joint filler conforming to 415.2.3 . 601.3.7 Protecting and Curing
601.3.8 Protecting in Cold Weather
601.3.9 Integral Construction
by slip forming integrally with the pavement. Construct to the section the plans show. Extend the transverse joints in the pavemen t through the integral curb, gu tter, or curb & gutter.
longitudinal joint may be required to limit panel width to the maximum the plan details specify.
601.4Measurement
linear foot acceptably completed.
gutter. The department will measure continuously along a line e xtended across driveway and alley entrance returns or ramps.
as drop inlets, etc.
bid item in the contract, as specified in the specifications. H owever, if the contract does not provide a bid item for excavation, it is incidental to the work.
601.5Payment
items: ITEM NUMBER DESCRIPTION UNIT
601.0100 - 0149 Concrete Curb (type) LF
50 - 0199 Concrete Curb Integral (type) LF
601.0200 - 0249 Concrete Gutter (inch) LF
601.0300 - 0339 Concrete Curb & Gutter (inch) LF
40 - 0349 Concrete Curb & Gutter Integral (inch) LF
601.0400 - 0449 Concrete Curb & Gutter (inch) (type) LF
50 - 0499 Concrete Curb & Gutter Integral (inch) (type) LF
601.0500 - 0549 Concrete Curb & Gutter Integral (inch) Sloped ( inch) LF
50 - 0599 Concrete Curb & Gutter (inch) Sloped (inch) (ty pe) LF
Effective with the December 2018 Letting 324 2019 Standard Spec ifications 601.0600 Concrete Curb Pedestrian LF
ancillary concrete.
foundation excavation and preparation; special construction required at driveway and alley entrances, or curb ramps; for providing ma terials, including concrete, exp ansion joints; for placing, finishing, protecting, and curing; for sawing joints; and for disposing of surplus excavation material, and restoring the work site. However, if the contract provides a bi d item for excavation, then the department will pay for excavation required for this work as sp ecified in the contract. Payment also includes providing tie bars in unhardened concrete. For tie bar s provided in concret e not placed under the contract, the department will pay separately under the Dril led Tie Bars bid item as specified in 416.5 .
Effective with the December 2018 Letting 325 2019 Standard Spec ifications Section 602 Concrete Sidewalks, Loading Zones, Safety Islands, and Steps
602.1Description
landings, of concrete, with or without reinforcement.
bridges or culverts are not included.
602.2Materials
Expansion jo int filler ........................................ .......................................................................................... 415.2.3
in 716. Provide QMP for class II ancillary concrete as specified in 716.
defined in the Curb Ramp Detectabl e Warning Field bid items.
602.3Construction
602.3.1 General
ancillary concrete. Repair cracke d concrete as the engineer dir ects. 602.3.2 Sidewalks 602.3.2.1 Preparing the Foundation
subbase bottom if specified. Tamp or compact the foundation to ensure stability. In cuts, make the foundation wide enough to allow placing forms and performing co ncrete placement and finishing. On embankments, construct the found ation at least 2 feet wider tha n the proposed sidewalk and extend it at least one foot beyond ea ch end of the sidewalk.
similar to those in the existing foundation. The contractor may use granular subbase or aggregate base.
show. 602.3.2.2 Forms
other displacement during depositing and consolidating the conc rete. If using wood forms, provide surfaced planks, at least 2-inch nominal thickness stock except for sharply curved sections. If using metal forms, ensure they are t he engineer-approved section with a flat surface on top. Use forms as deep as the depth of the sidewalk. Securely stake, brace, and h old the forms firmly to the required line. Make the forms tight to pre vent mortar leakage. Clean and oil before placing concrete against them. 602.3.2.3 Placing and Finishing Concrete
placing the concrete. Place the concrete on a moist foundation, deposit it to the required depth, and consolidate sufficiently to bri ng the mortar to the surface, th en strike-off and finish to a true and even surface. Before the mortar sets , brush or lightly broom the surface. Before performi ng the final surface finish, check the sidewalk surface with a 10-foot straightedge, and correct areas that vary 1/4 inch from the testing edge by adding or removing concrete while the concrete is still plastic.
approved, slip-form equipment. The contractor may omit wood flo ating if the slip-form equipment produces a suitable finish.
Embed detectable warning field arrays in plastic concrete confo rming to manufacturer-recommended procedures. Do not install on hardened concrete. Do not field cut plates except where the ends of radial arrays abut ramp edges. S mooth the edges of field cuts.