Effective with the December 2018 Letting 75 2019 Standard Speci fications Section 203 Removing Old Culverts and Bridges
203.1Description
of the resulting materials, or if required, salvaging and storing designated materials. 203.2 (Vacant)
203.3Construction 203.3.1 General
by or interfere with new constru ction. The contractor who const ructs the new structure that replaces the existing facility, unless the contract specifies otherwise, shall perform this removal or closing.
roadway limits, but within the highway limits.
contract specifies otherwise.
designated in the contract as sa lvageable. If the contractor re moves, but does not replace entrance pipes from private property, t he contractor must offer these pipes to the property owners before claiming them. 203.3.2 Breaking Down and Removing 203.3.2.1 General
equipment, facilities, or methods that might damage members, po rtions of the structure to be preserved, or adjacent construction. Before starting new work, complete blasting or other operations that might endanger new work. If i ncorporating portions of exis ting culverts or bridges in the new work, remove the portions not being saved in a way that leaves the re mainder of the structure undamaged.
construction operations that would obscure that damage or cause additional damage until the department has had an opportunity to assess the structural significance of the damage. Provide the engineer with means to access the site to make this determinati on.
203.3.2.2 Removal Operations Revise 203.3.2.2 to require department assessment of and written approval for restoration of contractor-caused damage done during deck removal. This cha nge was implemented in ASP 6 effective with the December 2017 letting. 203.3.2.2.1 General
superstructure of other culverts and bridges designated for rem oval. Completely remove existing piles, cribs, or other timber construction within the limits of new embankments, or remove these structures to an elevation at least 2 feet below finished ground line. Remove sidewalls or substruc ture units in water to an elevation no higher than the elevation of the natural str eam or lake bed, or, if grading the channel is required under the contract or the plans, to the pro posed finished grad e of the stream or lake bed. Remove sidewalls or sub structure units not in water d own to at least 2 feet below natural or finished ground line.
the existing structure as necessary to provide a proper connection to the new work. Saw, chip, or trim the connecting edges to the required lines and grades without weakening or damaging the remaining part of the structure. During co ncrete removal, do not damage r einforcing bars left in place as dowels or ties incorporated into the new work.
damage to the members. If the contra ct specifies removing the s tructure in a way that leaves it in a condition suitable for re-erection, matchmark members with dura ble white paint before dismantling. Mark pins, bolts, nuts, loose plates, etc., similarly to indica te their proper location. Paint pins, bolts, pinholes, and machined surfaces with a department-approved rust preventative. Securely wire loose parts to adjacent members, or label and pack them in boxes.
Effective with the December 2018 Letting 76 2019 Standard Speci fications (5) Remove timber structures or p arts of timber structures designa ted for salvage in a way that prevents damage to the members.
falsework used to construct new w ork. Do not damage or reduce the value of those materials through temporary use. 203.3.2.2.2 Deck Removal
surfaces and wetlands as the contract specifies in 107.18 or in the special provisions. Also, minimize debris falling on the ground and roadway.
in new work. Remove decks on prestressed concrete girders using a hydraulic shear or other engineer-approved equipment. Thorou ghly clean, realign, and ret ie reinforcement as necessary.
the engineer. Allow 1 business day for the engineer to complete the damage survey. If damage is identified, the department will det ermine if repairs or girder restoration w ill be allowed.
Wisconsin analyze the effect of the damage to the bridge, make recommendations, and prepare signed and sealed computati ons and structural details required to restore girders to their previous structural capacity . Submit the restoration proposal, including analysis and struc tural details, to the department and design engineer of record. The department will accept or reject the restoration proposal within 3 business days. Do not begin restoration work until the department allows in writing.
203.3.3 Closing Culverts
ground line. Completely fill each end of the culvert with satis factory soil for a distance from each end of at least 2 feet plus the height o f the opening of t he structure . 203.3.4 Incorporating or Disposing of Materials
incorporation in the work, from t he right-of-way. Ensure that d isposal sites are neatly constructed.
locations the engineer designates. Clean salvaged pipe culverts . Locate the piles far enough from the traveled way so they do not c reate a hazard to traffic.
the extent practicable. The cont ractor may use these materials, if suitable, to construct riprap, tree wells, and similar structures. U nless the contract or the engin eer specifies otherwise, incorporate the balance of these materials, if they have suitable engineering p roperties, in embankments as specified for placing rocks under 207.3.4 . Do not place these materials within 8 inches of the surface o f the earth grade.
engineering properties to backfill areas resulting from removals and to construct embankments. Dispose of surplus or unsuitable material as specified under 205.3.12.
to regulations governing solid was te disposal. Obtain written p ermits for this dispo sal from the owner of the property where placing t he material, unless disposing of the material at a licensed waste disposal operation. Furnish per mits, or copies of permits, to t he engineer before disposal begins. Do not deposit waste in wetlands.
designated for salvage on blocking in a location suitable for l oading. Store structures or portions of structures, specified in the prop osal for re-erection, in separate piles.
Effective with the December 2018 Letting 77 2019 Standard Speci fications (8) Remove nails and bolts from timber or piling from old structures, designated for salvage. Store this timber or piling in neat piles in locations suitable for loadin g. Dispose of waste ti mber and lumber by open burning, if allowed; by burning in an air curtain destruct or, if allowed; by chipping, or dispose of as specified for surplus material in 205.3.12. Dispose of chipped material as specified for machine cutting or chipping in 201.3(13) . Dispose of creosote treated p iling as required by the WDNR. 203.3.5 Backfilling
by new structures or required for waterways. Use either satisfactory soil or broken masonry and satisfactory soil. If the contrac t plans or special provisions specify granular backfill, use backfill material conforming to 209. Place backfill material in la yers no thicker than 8 inches. I f using granular backfill, the contractor may place granular backfill in layers up to 12 inches thick. Thoroughly compact each layer using engineer-approved tampers, rollers, or vibrato rs. If encountering water in an excavation, place backfill in a w ay that displaces the water an d does not trap it.
provision does not require the co ntractor to de-water the excav ation before placing backfill.
203.4Measurement
acceptably completed.
structure accept ably completed.
roadway, drainage, or structure excavation item.
203.5Payment
203.5.1 General
items: ITEM NUMBER DESCRIPTION UNIT
203.0100 Removing Small Pipe Culverts EACH
203.0200 Removing Old Structure (station) LS
Revise 203.5.1(2) to clarify that all costs associated with contractor-caused damage are incidental. This change was implemented in ASP 6 effective with the December 2017 letting.
caused damage ; required salvaging, storing, and disposing of materials; and, unless the contract specifies granular backfill, for backfilling.
diameter round pipe is incidental to associated items of work.
backfilling under the Backfill Granul ar bid items as specified in 209.5 . 203.5.2 Removing Small Pipe Culverts
sectional area equivalent to or larger than the area of a 12-in ch diameter round pipe but smaller than a 60-inch diameter round pipe.
Associated precast components are incidental to this bid item. The department will pay for associated cast-in-place components sepa rately under the appropriate 204 removal item.
the Removing Small Pipe Culverts bid item, but the contract does not show that removal, the department will pay for that removal at the contract price each or, absent the bid item, as extra work. If a removal that the plans show as a small pipe culvert conforms to the classification criteria for the Removing Old Structure bid items, the department will pay for t hat removal as extra work. 203.5.3 Removing Old Structure
a removal as a bridge-like str ucture if the structure is one or more of the following:
Effective with the December 2018 Letting 78 2019 Standard Speci fications 3. A rectangular culvert of any size.
diameter round pipe.
associated pipe culvert extensio ns, and multi-cell and multi-pi pe systems. If required in 104.7 or if the engineer directs removing a stru cture, conforming to the classi fication criteria for this bid item but not included in the contract, the depa rtment will pay for that removal as extra work.
girders as specified in 203.3.2.2(2) .
Effective with the December 2018 Letting 79 2019 Standard Speci fications Section 204 Removing or Abandoning Miscellaneous Structures
204.1Description
disposing of the resulting materials, or if required, salvaging and storing designated materials. 204.2 (Vacant)
204.3Construction 204.3.1 General
204.3.1.1 General Requirements
operations. Do not use any equipm ent or devices that might dama ge structures, facilities, or property to be preserved and retained. Complete operations necessary to remove or abandon an existing structure and that might endanger the new construction before c onstructing new work. 204.3.1.2 Backfilling
miscellaneous structures as specified fo r backfilling trenches in 203.3.5.
finished earth subgrade, or finished slopes, as necessary due t o the location of the removed structure. 204.3.1.3 Salvaging or Disposing of Materials
piles outside construction limits but within the right-of-way, at locations the engineer approves. Stockpile materials designated for salvage at locations the eng ineer approves, without contaminating the material with dirt or foreign matter.
disposing of materials under 203.3.4 . 204.3.2 Breaking Down and Removing 204.3.2.1 General
with the new construction as follows: - From within the roadway. - From within the removal limits the plans show. - From within the limits designa ted under the Obliterating Old Road bid item, whether specified or subsequently found necessary and required. - If the contract specifies, also wholly or partially remove st ructural elements occurri ng outside the limits of construction and bey ond the limits of Oblit erating Old Road.
foundations, and similar masonry structures as follows:
existing structure are to remai n in the surface of the finished work, remove the stru cture to an existing joint, or saw and chip the structure to a true line with a face perpendicular to the surface of the existing structure. Remove enou gh of the structure to provide proper gra des and connection to the new work. Maintain drainage as specified for drainage during construction in 205.3.3 .
for its disposal as specified fo r disposing of materials under 204.3.1.3 . 204.3.2.2 Removing Items 204.3.2.2.1 General
driveways, or rigid base including all surfaces or other paveme nts superimposed on them.
construction of butt joints. Remove existing pavement to the de pth the plans show by grinding, planing, chipping, sawing, or other engineer-appr oved methods.