Effective with the December 2018 Letting 17 2019 Standard Speci fications Section 104 Scope of Work
104.1Intent of the Contract
regarding the construction, exe cution, and completion of the work. Perform the work as the contract specifies.
104.2Revisions to the Contract
104.2.1 General
the contract or release the su rety. The contractor agrees to complete the contract as revised. Do not proceed with revised work without the project engineer’s prior written approval. Upon receiving written approval, proceed immediately with the revised work.
necessary. Whenever the words notice, notification, or notify a re used in 104.2 with reference to the contractor, the contractor shall provide notice as specified in 104.3 . The project engineer will determine if a potential contrac t revision is necessary and wil l notify the contractor of its determination in writing. The contractor must p roceed with the project engineer’s direction.
time as specified in 108.10 and will revise the contract price as specified in 109.4 . The contractor is entitled to no reimbursement fo r loss of anticipated profit.
necessary, and the cont ractor does not agree with the project e ngineer's decision, the contractor may pursue a claim under 105.13 . 104.2.2 Issuing Contract Change Orders 104.2.2.1 Change Orders for Extra Work
104.2.2.2 Change Orders for Differing Site Conditions
the site, the party discovering the condition shall promptly no tify the other party of the specific condition before further distur bing the site and before further performing the affected work.
and generally recognized as inherent in the work specified in t he contract.
specified in 104.3.2 , of the specific differing condition before further disturbing the site and before further performing the affected work.
materially differ and cause an in crease or decrease in the cost , time, or both, required to perform the work under the cont ract, the project engineer will adjust the contract price, time, or both, and modify the contract in writing accordingly. The project engineer will respond to the contractor as to whether or not an adjustment is warranted. The project engineer will follow the contractor notification procedures specified in 104.3 .
notice as specified in 104.3 . 104.2.2.3 Change Orders for Engineer-Ordered Suspensions
for an unreasonable period of time (not originally anticipated, customary, or inherent to the construction industry) and the co ntractor believes that additio nal payment, contract time, or both, is due because of the suspension or delay, the contractor shall no tify the engineer as specified in 104.3 .
time, or both, required for the performance of the contract has increased due to the suspension or delay and the suspension or delay was caused by conditions beyo nd the control of and not the fault of the contractor, its suppliers, or subcontractors at any approve d tier, and not caused by weather, the project engineer will make an adj ustment and modify the contrac t in writing accordingly. The project engineer will respond to the contra ctor as to whether or not an adjustment is warranted as specified in 104.3.6 .
Effective with the December 2018 Letting 18 2019 Standard Speci fications (3) The project engineer will not consider a contract adjustment u nless the contractor submits the request for adjustment within the time specified above.
performance would have been suspe nded by any other cause, or fo r which an adjustment is provided or excluded under any o ther term or condition of this contract. 104.2.2.4 Change Orders for Significant Changes in the Character of the Work 104.2.2.4.1 General
circumstances occur as follows:
basis for the adjustment as specified in 109.4.4 . If the department does not ack nowledge that the work has significantly changed, follow the notification procedures a s specified in 104.3 .
the contract, the department will pay for the altered work at t he contract price. 104.2.2.4.2 Altered Work
or nature from that involved or i ncluded in the original proposed construction. 104.2.2.4.3 Changed Quantities
changes affect the c ontractor's unit cost to perform the work a nd meet one of the following:
below 75 percent of the original contract quantity. Any allowance for an increase in quantity applies only to that portion in excess of 125 percent of the original contract bid item quantity, or in case of a decrease below 75 percent, to the work actually performed.
unit price for that bid item applies only to the quantity of th at bid item having a contract value as follows: Original Contract < $8M: In e xcess of 6.25 percent of the orig inal contract. Original Contract >= $8M: In excess of $500,000.
original value of that subcontract is decreased more than 50 pe rcent from the original contract quantity for that bid item. Either party to the contract may submit a reques t for a revision to the c ontract unit price for that bid item. The department’s total payment for the final red uced quantity will not exceed 75 percent of the original contr act quantity at the contract price.
original value of that subcontract is increased more than 50 pe rcent from the original contract quantity for that bid item and which as increased does not qualify for adjus tment as a major bid item. Either party to the contract may submit a re quest to the other for a revision o f the contract unit price for that quantity of the bid item that is in excess of 125 percent of the original c ontract quantity. 104.2.2.5 Change Orders for Eliminated Work
finds to be unnecessa ry for the project. If the project enginee r partially eliminates or completely eliminates work, the project engi neer will issue a contract change order for a fair and equitable amount as specified in 109.5 . 104.2.2.6 Change Orders for Revisions to Contract Time
104.3Contractor Notification
104.3.1 General
resolution of potential contrac t revisions identified by the contractor. Both contractor actions and department responses are outli ned. The contractor's non-compliance with the requirements of 104.3 may constitute a waiver of ent itlement to a pay adjustment unde r 109.4 or a time extension under
108.10
Effective with the December 2018 Letting 19 2019 Standard Speci fications 104.3.2 Contractor Initial Oral Notification
action, or some other situation results in or necessitates a co ntract revision, the contractor must promptly provide oral notification to the project engineer. Upon notification, the project engineer will attempt to resolve the identified issue. 104.3.3 Contractor 2-Day Written Notice
receipt of oral notification, pro vide a contractor 2-day written notice to the project engineer. At a minimum, provide the following:
possible to assist the project engineer in the timely resolutio n of an identified issue. The project engineer will not require, in subsequent submissions, duplicati on of information already provided. 104.3.4 Engineer One-Day Written Acknowledgment
provide a project engineer one-day written acknowledgment to th e contractor. The project engineer will continue to resolve the issue. 104.3.5 Contractor 5-Day Written Statement
written notice, augment the original written notice with an add itional contractor 5- day written statement to resolve the issue. In the written statement:
delay, or disruption.
may be based on incomplete information. The department will attempt to comprehend and resolve the potential change as quickly as pos sible. The contractor can hel p the department in this process by providing the requested inform ation as quickly as possible. 104.3.6 Engineer 5-Day Written Response
consider the statement and provide a project engineer 5-day res ponse in writing to the contractor with one or more of the following responses:
project engineer will give direction concerning the potential c hange.
statement as to why the issue is not a change to the contract. At a minimum, the project engineer will respond to the contractor’s iss ues and refer to the contract to show why the issues are not a change from the original contract.
item 1 or 2 of 104.3.6(1) applies. The project engineer will st ate the information nee ded and date it is to be received for further review.
issue as a claim a s specified in 105.13 . Alternatively, if the contract or and department mutually agree, the department will get a third-party advisory opinion according to the department’s dispute resolution procedures.
engineer has 14 calend ar days after receipt of the third party' s written recommendation to render a decision. If the department fails to respond in writing within those 14 calendar days or the contractor disagrees with the project engin eer's decision, the contractor may pursue the issue as a claim as specified in 105.13 .
Effective with the December 2018 Letting 20 2019 Standard Speci fications 104.4 Requests for Information
order for the requesting party to fulfill its contract obligations. The requesting party shall submit requests for information (RFI) on department form DT2502 either in hard copy or via email. RFI must conform to the following: - Be of reasonable scope. - Explain why a response is necessary to fulfill contract oblig ations. - Provide a requested response ti me, which must be reasonable i n relation to its scope.
the requested response time. If m ore time will be required to a dequately address the issue, the responding party shall provide a written status report within t he requested response time. The parties will discuss the status of outst anding RFI at each progress mee ting until the issue is resolved. 104.5 (Vacant)
104.6Roadway Maintenance and Traffic Control
104.6.1 General
results from the contractor’s o wn operations, negligence, or no ncompliance with the contract.
surfaces, on which construction has begun or been completed, or has been damaged by the contractor’s operations or ha s been damaged due to the contract or’s negligence or noncompliance with the requirements of the contract.
highways open to traffic or closed to through traffic.
temporary barrier as specified in part VI, of the WMUTCD and ensure that the contractor's use of the right-of-way conforms to 107.9 . Furnish, erect, and maintain traffic control devices and faci lities conforming to 643, or as the engineer directs, th roughout the life of the contra ct. Use drums, barricades, and temporary barrier to delineate and shield abrup t drop-offs and other hazards. Conduct flagging operations according to t he plan details and the WMUTC D. Adequately train flaggers in the methods described in the WMUTCD and associated video before all owing them to control traffic. Costs for flagging and guidance services and signs associated with flagging and guidance, are incidental to the co ntract. The departmen t will pay separately for temporary portable rumble strips required in the flagging plan details under contract special pr ovision bid item Temporary Portable Rumble Strips.
flaggers, watchers, and temporar y barrier to protect it. The en gineer may order the contractor to immediately remove and replace or otherwise repair the damaged work at no additional expense to the department.
contractor’s negligence in prop erly safeguarding public travel. 104.6.2 Temporary Roads
the engineer directs. Excavate and remove those portions of tem porary roads not incorporated into the final roadway section, and rest ore disturbed areas outside the construction limits to their original condition.
or as the engineer orders, and the associated restoration of di sturbed areas. The department will pay for this construction, removal, and restoration work at the contract unit prices of the bid items used, or as extra work, if the necessary bid items are not included in t he contract.
condition. The cost of maintaining these temporary roads is inc idental to the contract, except during suspensions under 104.6.7.
the engineer did not order, is incidental to the contract.
Effective with the December 2018 Letting 21 2019 Standard Speci fications 104.6.3 Road Closed to Traffic
traffic, furnish, erect, and main tain the traffic control devices at the project termini and at intersecting roads along the project the cont ract specifies or as the engineer directs. Unless specifically required in the contract, the contractor is not responsible to maintain the pavement structure or traffic signs of the detour that may be provided for the accommodation of traffic ar ound the portion of the road closed to traffic.
If the contract specifies, or i f the engineer orders, that a road or a portion of road is to be closed, notify the engineer at the ear liest possible date of when the closure is needed so the department can make arrangements to close the road and provide detours. 104.6.4 Road Closed to Through Traffic
and maintain the traffic control devices at the project termini and at intersecting roads along the project the contract specifies or the engineer direc ts. Also, furnish, erect, and maintain those traffic control devices within the project limits as may be required for the sa fe accommodation of local traffic as defined in 101.3 . At all times conduct the work i n a manner to provide safe, re asonably-direct, all- weather, 24-hour pedestrian and vehicular access to abutting pr operties along the highway being improved.
structure or traffic signs of t he detour that may be provided for the accommodation o f traffic around the portion of the road closed to through traffic. The department will pay for surfacing and base materials that the engineer deems necessary to maintain the roadway at co ntract unit prices, or as extra work. 104.6.5 Opening Section of Closed Road to Traffic before Work is Completed
may direct or authorize the c ontractor to open sections of the road to public traffic before the work is completed. The engineer may dire ct the contractor to open sections of the road for the convenience of the traveling public. The engineer may authorize the contractor to open sections of the road to public traffic due to the contractor’s request. Do not open the road t o public traffic without the engineer’s written direction or written authorization. By opening sections to public traffic, the contractor is not relieved of performing the maintenance. However, the department will assume all costs for repair and maintenance solely attributable to public traffic use, and beyo nd the control and without fault of the contractor. These maintenance expenses include costs associated with those traffic control devices or facilities specified in this section. The engineer’s direction or authorization to open sections of the road to public traffic does not const itute partial acceptance under 105.11.1 and waives no other contract provisions.
accommodation of the traffic.
except for injuries or damages r esulting from the contractor’s own operations, negligence, or noncompliance with the requirements for traffic control under 104.6.1.
construction operations in a way that causes the least obstruction to traffic. 104.6.6 Road Open to All Traffic
improvement or reconstruction, k eep the road open to all traffi c. Furnish, erect, and maintain the traffic control devices as required to keep the portions of the road be ing used by public traffic in a condition to safely and adequately accommodate pedestrian and vehicular traffic. The department will pay for necessary work and materials to m aintain the roadway at the con tract unit prices o f the bid items used or as extra work if the necessar y bid items are not included in the contract. 104.6.7 Traffic Control and Maintenance During Suspensions of the Work
traffic portions of the highway under improvement and temporary roads or portions thereof as the contractor and the engineer may agree upon for temporary accomm odation of necessary traffic during the period of suspension. During the period of suspension, main tain the surface of the traveled way of the temporary route or line of travel agreed upon.
Effective with the December 2018 Letting 22 2019 Standard Speci fications (2) When resuming work, replace or renew all work or material lost or damaged because of temporary use of the highway under improvement. Remove temporary roads and re store disturbed areas outside the construction limits to their original condition, as the enginee r directs. Complete the improvements in every respect as though prosecution had been continuous and without interference, except as the contractor and the engineer may o therwise have agreed upon at t he time the arrangement was made for the temporary accommodation of necessary traffic during the anticipated period of suspension.
department will pay for the following at the contract unit prices of the bid items used, or as extra work if the necessary bid items are not included in the contract.
highway.
corresponding restoration of dis turbed areas outside the constr uction limits.
suspension.
accommodate public travel during the suspension.
104.7Removing Structures and Obstructions
designated for replacement or that interfere with new construction. The department will:
removal bid items under 204.
removal bid items under 204:
3.1Pay as specified in 206.5.1, if the removal is located within the limits of an Excavation for
Structures bid item under 206.
3.2Otherwise, pay as incidental to the Excavation bid items under 205
roadway, but within the highwa y, if the contract specifies. Wit hin 104.7, highway means the entire highway right-of-way, including abutting portions of existing highways. The department will:
removal bid items under 204.
removal bid items under 204:
Pay as incidental to the Obliterating Old Road bid item, if the removal is located within the limits of
the Obliterating Old Road bid item under 214.
Otherwise, pay as incidental to the other contract bid it ems
104.8Rights in the Use of Materials Found on the Project
and horizontal excavation limits the plans show. Ensure that th e engineer determines the material’s suitability before using it. T he department will pay for both t he excavation of these materials at the corresponding contract bid price and the bid item for which the excavated material is used. The department will not charge the cont ractor for the materials fou nd within the above described excavation limits and so used . Replace, at no expense to the de partment, with other acceptable material all of the excavation material so removed and used for embankments, backf ills, approaches, or otherwise.
horizontal excavation limits t he plans show without the enginee r’s written authorization. Do not base bids on the anticipated approval of a request to excavate or re move material that is not within the above described excavation limits.
Effective with the December 2018 Letting 23 2019 Standard Speci fications 104.9 Final Cleanup
makes final payment as specified in 109.7 , the contractor shall remove fr om the right-of-way, and to the extent that the contractor i s responsible therefore, from the adjacent property, all surplus and discarded materials, rubbish, and temporary structures. Leave t he right-of-way in a neat and presentable condition. The contra ctor shall restore, at no expe nse to the department and in general conformity with the contract for the bid item or bid items invo lved, all work completed under previous contracts that the contractor has damaged.
commercial source or is not naturally submerged, the contractor shall do work as necessary and practicable to shape, slope, and trim and drain the site, including associated haul roads and adjacent areas disturbed by the contractor’s operations, so that it pres ents a stable, neat, trimmed appearance and that no water collects or st ands therein. Do not create or enlarge an area of open water except as allowed under 208.2.2 .
104.10Cost Reduction Incentive
.1 General
Revise 104.10.1(1) to eliminate CRIs for department genera ted ideas. This change was implemented in ASP 6 effective with the December 2017 letting.
incentive (CRI) for modifying t he contract in order to reduce d irect construction costs computed at contract bid prices. The initial submittal is referred to as a CRI concept and the seco nd submittal is a CRI proposal. The contractor and the department will equally sh are all savings generated to the contract due to a CRI as specified in 104.10.4.2(1) . The department encoura ges the contractor to submit CRI concepts.
determines a CRI concept has merit, the department will encoura ge the contractor to submit a CRI proposal. Follow the procedures specified in 104.10.3 for submitting a CRI proposal.
except through the contractor.
prices on the anticipated approval of a CR I proposal. If the department rejects a CRI proposal, complete the contract as specified in the original terms or as otherwise modified. Revise 104.10.1(5) to explicitly list pavement design changes the department will not allow under a CRI.
characteristics of the project. These functions or characterist ics include, but are not limited to, appearance, service life, economy of operations, ease of maintenance, design, and safety of structures and pavements, const ruction phasing or procedures, o r other contract requirements. The department will not con sider a CRI that changes the following: - Permanent or temporary pavement type. - Permanent or temporary structural cross section.
causing a delay to the project in considering a CRI or for refu sing to approve a CRI. The department may consider a noncompensable time extension as specified in 104.10.2(3) . The department will consider no contractor claims for additional costs related to t he acceptance or rejection of a CRI, including loss of anticipated profits, or increased material or labor costs. The department will reimburse the contractor for t he development costs of CRI propo sals as specified in 104.10.4.1(3) .
contractor submits it. Impose no restrictions on the CRI for its use or disclosure. The department has the right to use, duplicate, and disclose in whole or in part all data necessary for the utilization of the CRI. The department may use an ac cepted CRI or part of an accep ted CRI on other projects without obligation to the contractor. This provision does not deny righ ts granted by law with respect to patented materials or processes. The department will not use th is provision as the basis for rejecting the contractor's submittal of a CRI concept from past projects.
acceptance or rejection of the CRI Proposal.
Effective with the December 2018 Letting 24 2019 Standard Speci fications (9) Work produced under an approved CRI contract change order is s ubject to the provisions of 105.3.2 for nonconforming work.
.2 Submittal and Review of a CRI Concept
CRI concept. Estimate the overa ll CRI savings and the costs to develop the CRI proposal specified in
.3 . The engineer will use the cont ractor's estimate of the CRI pr oposal development costs as
specified in 104.10.4.1(3) . Indicate whether adequate time is available in the project sc hedule for submitting a complete CRI propo sal and for the department’s review before implementation.
submittal, notify the contractor in writing whether the CRI con cept has merit and whether the contractor should submit it as a CRI proposal. The contractor and the department can mutually agree to extend this 5-day review requirement. The department will no tify the contractor if a professional engineer registered in the state of Wisconsin should seal the C RI proposal. If the department informs the contractor to submit the CRI proposal, the department will share in the cost for developing the CRI proposal as specified in 104.10.4.1(3) .
review, the department may choose to evaluate the need for a no ncompensable time extension to the contract. The department will bas e its evaluation on the additi onal time that the department needs for its review of the CRI proposal and the effect on the contractor’s schedule caused by the added review time.
proposed in a CRI concept, the department may reject the CRI co ncept and revise the contract without obligation to the contractor.
specified in 104.2 .
the level of risk. The departm ent will assess the risk of the C RI relative to departmental design policies and criteria for the project. The department may reject a CRI c oncept for the following reasons:
.3 Submittal of the CRI Proposal
the CRI proposal. The contractor and department can mutually ag ree to extend this 10-day submittal requirement. Ensure that the CRI proposal includes sufficient d ata for the department to make an informed decision regarding the proposal and includes, at a minimum, the following information:
and disadvantages of each, which may include effects on service life, economy of operations, ease of maintenance, benefits to the trav eling public, desired appearance, and safety.
features and requirements. Su pport the proposed revisions with design computations as necessary for a thorough and expeditious evaluation.
compared to the new costs and qua ntities generated by the CRI. The department will us e these costs as specified in 104.10.4.2(1) to compute the proposed net savings.
the contract.
previously submitted the CRI on another department project, the contractor shall indicate the date, contract number, and action taken by the department.
changes. The department will use t hese costs as the contractor’ s CRI development and implementation costs as specified in 104.10.4.1(3) and 104.10.4.2(1) .
department requires it as specified in 104.10.2(2) .
Effective with the December 2018 Letting 25 2019 Standard Speci fications 10. If proposing design changes, the contra ctor may include wi th the additional inform ation, results of field investigations and surveys, des ign computations, and field chan ge sheets.
.4 Acceptance, Rejection, and Payment
.4.1 Acceptance, Rejection , and Payment of a CRI Proposa l
or reject the CRI proposal in wri ting. The contractor and the d epartment can mutually agree to extend this 10-day review requirement. P rovide requested additional information needed to evaluate the CRI proposal in a timely manner. The department may reject a CRI pr oposal for untimely submittal of additional information.
contractor for the cost of preparing the CRI proposal. The depa rtment will limit reimbursement to the contractor’s estimate of the CRI proposal development costs pro vided in the CRI concept submittal. The change order will also state the conditions for the departm ent's acceptance and which of the following the net savings will be based on:
department will measure after t he contractor com pletes the CRI.
rejects the CRI proposal, the dep artment will execute a contrac t change order to adjust the contract for the contractor’s CRI developmen t costs as listed in item 8 of 104.10.3(1) . The department will limit the contract revision amount to the contractor’s estimate of the CRI proposal development costs provided in the CRI concept submittal. The contract change order will te rminate the departm ent’s review of the CRI.
for other costs.
.4.2 Payment for the CRI Work
Revise 104.10.4.2(1) to clarify that the department may adju st bid prices that do not represent the fair value of work when computing CRI savings. This change was implemen ted in ASP 6 effective with the December 2017 letting.
department will pay for CRI's under the Cost Reduction Incentiv e administrative item. When all CRI costs are determined, the departm ent will execute a contract ch ange order that does the following:
NS = CW - CRW - CC - DC Where: NS = Net Savings CW = The cost of the work required by the original contract that is revised by the CRI. CW is computed at contract bid prices if applicable.[1] CRW = The cost of the revised work, computed at cont ract bid prices if applicable.[1] CC = The contractor’s cost of dev eloping the CRI proposal. DC = The department’s cost for investigating, evaluating, and imp lementing the CRI proposal. [1] The department may adjust contrac t bid prices that, in the engi neer's judgement, do not r epresent the fair value of the work deleted or proposed.
in construction costs from the adoption of all or part of the C RI proposal. The de partment will not include time savings resulting from the CRI in the calculation of net savings. Effective with the December 20 18 Letting 26 2019 Standard Speci fications Section 105 Control of the Work
105.1Engineer's Authority
(1)The engineer decides all questions regarding:
he quantity, quality, and acceptability of materials furnished and work performed.
(2)The engineer may suspend the work in writing for any reaso n at any time during the contract. Except as specified in 104.2.2.3 for engineer-ordered suspensions, the de partment will allow no additional payment or time extension due to a suspension of work. (3)The engineer will determine estimated quantities for prog ress payments as specified in 109.6 .
105.2Supplemental Plans and Drawings
Revise 105.2 to incorporate fabri cation library electronic submittal requirements for specified structures. 105.2.1 General (1)Submit to the engineer supplements to the approved contract plans, shop drawings, and the computations necessary to contro l the work. Do not change the a pproved contract plans without the engineer's written authorization. (2)If sufficient detail is not pro vided on the structure plans pr oduced by the departm ent, submit t o the engineer plans, shop drawings and the computations required to successfully prosecute the work. (3)If required in the cont ract, submit plans fo r temporary structures, cribs, cofferdams , fals ework, shoring, and form work. Ensure that these plans and accompanying drawings and computations are signed and sealed by a professional engineer registered in the state o f Wisconsin. (4)Include a transmittal letter with each submittal made under 10 5.2. Indicate on shop drawin gs all deviations from the contract dra wings and itemize these deviati ons in the transmittal letter. The department will file and may revi ew these submittals. The department’s review does not relieve the contractor of the responsibility for obtaining satisfactory res ults, for the accuracy of dimensions and details, or for conformity of thes e drawings with the contract. The contractor may begin work on associated items without t he department's review. (5)Include the cost of furnishing all shop drawings in the unit p rice for one or more asso ciated bid item. 105.2.2 Fabrication Library Submittals (1)If specific contract provisions require submittals under 105.2. 2, also chec k and electronically submit shop drawings and computations to the department’s fabrication library a minimum of 2 weeks before the start of fabrication. Conform to the fabrication library su bmission standards. Procedures for accessing the fabrication library are located at: https ://wisconsindot.gov/Pages/doing-bus/eng-consultants/cnslt-rsrces/strct/fab-sharepoint.aspx
105.3Con
formit y with the Con tract 105.3.1 General (1)Perform all work the contract specifies. Produce quality work within limits of precision reasonably expected of good construction. Pr oduce work conforming to the lines, grades, cross-sections, dimensions, and material requireme nts the contract specifies or the engineer establishes. Monitor construction operations to identif y potential unacceptable work as defined in 101.3 . Promptly remove and replace, or otherwise correc t, unacceptable work at no expe nse to the department. (2)The contractor may request a plan dimension change between US standard and SI metric dim ensions for a portion of the work. The engineer will only consider this dimension change if the modified work is essentially equivalent to the spec ified work. The department wi ll pay for this modified work as specified in item 4 of 109.1.1.1(2) . Do not proceed with the modi fied work without the engineer's written permission. (3)The contract may specify specif ic values with allowable tolera nces, ranges , minimums, or maximums. Control operations to p roduce work that falls within the specif ied tolerance or r ange, falls above a specified minimum, or falls bel ow a specified maximum. If the c ontract does not specify a tolerance, range, minimum, or maximum value , control operations to produce work conforming to the contract within accepted manufacturing or c onstruction industry standards.
Scope of Work in other states
Get an email when 104 changes
Wisconsin revises spec sections through supplementals and new editions. We check this one every week and email you the day it changes. Free, no account.