Effective with the December 2018 Letting 98 2019 Standard Speci fications Section 207 Embankment
207.1Description
under the bid items in the road way and drainage excavation, bor row, or excavation for structures sections.
207.2Materials
perishable material. The contractor may place excess unstable topsoil and other unstable soil in embankments outside the roadwa y foundation as defined in 101.3 . Do not place frozen soil in embankments within the roadway foundation.
concrete or other materials that significantly affect scarifyin g, compacting, and finishing the subgrade.
piling through, use materials that do not contain stone or broken concrete retained on a 3-inch sieve and free from quantities of gravel, stone, or broken concrete p assing a 3-inch sieve or other material that significantly affects bori ng the holes or driving the pili ng.
207.3Construction
207.3.1 General
prepare the roadway foundation as specified in 205.3.2, unless the contract specifies otherwise.
place embankment on frozen subgrade.
winter if weather conditions prevail that cause substantial fre ezing of the materials during placement, except if using materials from rock excavation, or of a granula r nature and that contain only minor quantities of silt, clay, loam, or similar materials. 207.3.2 Placing Layers
ravines. Construct the embankmen t in layers by spreading and le veling the material during placement. Spread individual layers evenly to uniform thickness throughout and approximately parallel with the finished grade for the full width of the embankment, unless dir ected otherwise. Place the material in layers generally no thicker than 8 inches, to secure the required compaction. On side hills too steep to operate hauling equipment, over low wet ground, in marshes, or if filling in water, provide a single layer, just thick enough to support the hauling equipment while placing subsequent layers. 207.3.3 Placing in Marsh
material. Begin filling at one end of the marsh and proceed acr oss the marsh, close enough to the excavating operations to allow the equipment to remove any disp laced peat or muck as it accumulates ahead of the advancing embankment toe. Place fill material in a way that, and to a height that, effectively displaces unstable material from within the area of the proposed embankment. Build temporary surcharges, as required, to the height and horizontal dimensions the plans show. Progressively move temporary su rcharges ahead as the embankment advances.
layers and compact it to t he extent practicable. 207.3.4 Placing Rock
makes placing in 8-inch layers impracticable, then place the em bankment material in layers no thicker than the approximate average size of the larger rocks. Avoid ne sting and fill the voids with smaller stones and satisfactory soil or rock fines. 207.3.5 Hydraulic Fills
specified in 208.3 and construct as the engineer directs.
Effective with the December 2018 Letting 99 2019 Standard Speci fications 207.3.6 Compaction 207.3.6.1 General
compact embankments using standar d compaction methods unless th e contract specifies special compaction.
equipment, or excessive displacement or distortion under the co mpacting equipment. If these conditions exist, allow the materials to dry before compacting. If necessary, accelerate drying the materials by aerating or by us ing blade graders, harrows, discs , or other appropriate equipment to manipulate the material.
quantities the engineer deems necessary to aid, accelerate, and secure effective compaction.
compaction. The engineer may allow less compaction outside the roadway foundation if the contractor uses unstable soil. 207.3.6.2 Standard Compaction
than 8 inches before compaction . Compact each layer of the emba nkment until the compaction equipment achieves no further significant consolidation. Provid e the required compaction for each layer before placing any material for a succeeding layer.
practicable during placement. T he engineer may require specialized compaction equipment to provide additional compaction if, in the engineer's opinion, adequate c ompaction is not achieved without it.
other alternate compaction equipment that produces the required results. Obtain the engineer’s approval before using alter nate compaction equipment. 207.3.6.3 Special Compaction
ground surface in layers genera lly not exceeding 8 inches thick before compaction. If compacting granular material with equipmen t adaptable for this purpose, th e contractor may increase layer thickness to 12 inches if obtai ning the required dry density. E xcept as specified for construction methods in 207.3.2 , 207.3.3, 207.3.4 , and 207.3.5 , compact each layer of spread and leveled material by suitable compaction equipm ent, to not less than the specifie d dry density before placing the succeeding layer.
embankment areas outside the r oadway foundation as specified in 207.3.6.1(4) .
compact the full depth of the embankment to at least 95 percent of maximum dry density. For embankments over 6 feet in height, compact the material placed 6 feet below the finished subgrade to at least 90 percent of maximum d ry density and backfill materia l placed within 6 feet of the finished subgrade to at least 95 percen t of maximum dry density.
replace the fraction of materia l retained on the 3/4-inch sieve with No. 4 to 3/4-inch material. The engineer will determine the in-place dry density of compacted e mbankment material according to AASHTO T310 or by other engi neer-approved methods.
sieve from the sample that the ma ximum dry density was determined from, the engineer will adjust the maximum dry density according to approved department procedure.
constructed of materials that, because of numerous large stones or high percentages of material retained on the No. 4 sieve, t he engineer cannot accurately tes t according to the above procedures for determining maximum dry density or in-place dry density. 207.3.6.4 Subgrade Compaction in Cuts
pavement plus shoulders as specif ied for standard compaction in 207.3.6.2 , unless the contract specifies using special compaction.
Effective with the December 2018 Letting 100 2019 Standard Spec ifications (2) On grading projects that require special compaction, compact t he finished earth subgrade in cut sections to the width described in 207.3.6.4(1) and to a depth of at least 6 inches to at least 95 percent of maximum density. The engineer will determine the maximum den sity and attained density in the subgrade as specified for special compaction under 207.3.6.3 . 207.3.7 Shrinkage and Surcharge
allow for settlement; or place su fficient surcharge above the r equired elevation of earth grade over deposits of unstable material to secure displacement or settlement. 207.3.8 Slopes
slopes of rock fill embankments, c ompletely fill voids with roc k fines or soils, and trim slopes to a smooth uniform appearance.
the topsoil the finished embankment conforms to the required section. 207.3.9 Subgrade Intermediate Consolidation and Trimming
day consolidate and trim the subgrade to aid drainage and to pr otect against erosion. Consolidate and trim those portions of the subgr ade surface disturbed, operated over, or constructed during that workday. Consolidate and trim until float material is pressed f irmly against the subgr ade and produces a tight, smooth, well-drained surface. If rain is imminent duri ng the workday, consolidate and trim the subgrade before the rain falls to avoid ponding and erosion. 207.3.10 Backfilling Structures
other structures. This includes backfilling not performed incid ental to the excavation of these structures.
subgrade to at least 90 percent o f maximum density and backfill material placed within 6 feet of the finished subgrade to at least 95 percent of maximum density. Fo r bridge approaches, compact as specified in 207.3.6.3 . 207.3.11 Finish Grading
and scarifying.
207.4Measurement
207.5Payment
roadway and drainage excavation, borrow, excavation for structu res, granular backfill, structure backfill sections, and other contract bid items. The work includes formi ng, compacting, shaping, sloping, trimming, finishing, maintaining embankments, and other inciden tal work required under this section.
the engineer rejects under 207.3.11 .
Effective with the December 2018 Letting 101 2019 Standard Spec ifications Section 208 Borrow
208.1Description
earthwork summary the plans show for borro w. If the contract specifies moving material from one division to another, that material is not borrow.
208.2Materials
208.2.1 Quality
soil, stone, gravel, or other acc eptable materials, of a charac ter and quality satisfactory for the purpose intended. Use material free from sod, stumps, logs, and other p erishable and deleterious matter.
contract. 208.2.2 Source
4.1Material from within the right-of-way limits but outside e xcavation limits that the contract does not
already designate as excavation.
4.2Surplus excavation from other contracts.
4.3Material from old road fills, removed as specified in 214.
items to reduce the quantity of borrow required in that divisio n.
from whom the contractor proposes to obtain borrow material.
create or enlarge an area of open water if the contractor submi ts a written request. Include with that request written evidence that the following conditions are met:
water and that plan complies with all applicable ordinances or regulations.
department's bureau of aeronautics have been contacted and conf irm receipt of the following: - Contractor and landowner names and contact information including phone numbers. - Scale map showing the locati on of the proposed site in relati on to the airport. - Detailed reclamation plans showing the location, size, and ou tline of proposed new open water; slopes of the impoundment area; proposed re-vegetation plan; an d other requested information.
208.3Construction
excavation. Remove sod or other p erishable or unsuitable material from the proposed borrow source area. Excavate borrow sites in a way that allows the engineer t o accurately measure the material excavated and incorporated in the work.
specified in 205.3.12 .
in borrow site areas as specified in 201.3 .
overlying the borrow site. Stock pile the topsoil in sufficient quantities to cover all surfaces of excavated areas from 4 to 6 inches deep . If the topsoil overlying the bor row site is less than 4 inches deep, replace the topsoil to the original depth. After trimming and finishing the site, spread the salvaged