Effective with the December 2018 Letting 137 2019 Standard Spec ifications Section 340 Cracked and Seated Pavement
340.1Description
construction platform for a pavement overlay. 340.2 (Vacant)
340.3Construction 340.3.1 Equipment
transverse movement. The breaker must be capable of exerting a minimum of 12,000 foot-pounds of energy.
340.3.2 Cracking and Seating
unduly displace the concrete; damage drainage facilities, utili ties, or other property; or destabilize the base or subgrade.
area and having their maximum di mension transverse to the pavem ent centerline. Do not crack concrete within 2 feet of transve rse joints, or at other locati ons designated by the contract or engineer.
surface of the cracked and s eated pavement before opening to tr affic and again just before placing the asphaltic leveling co urse. Remove dust, dirt, debris, or other foreign or loose material.
340.4Measurement
340.5Payment
item: ITEM NUMBER DESCRIPTION UNIT
340.0100 Cracking and Seating SY
Effective with the December 2018 Letting 138 2019 Standard Spec ifications Section 350 Subbase
350.1Description
350.2Materials
not exceed 3/4 of the compacted thickness of any individual layer being placed.
- Within the right-of-way as the plans show or as allowed in 104.8 . - Beyond the right-of-way as specified for borrow in 208.3 .
350.3Construction
350.3.1 General
subbase. With the engineer's approval, the contra ctor may use c ement, fly ash, lime, or similar engineer-approved materials to stabilize the subbase.
layers, construct successive layers in the sequence and at the times the engineer directs. The engineer will phase that construction to provide a usable surface for traffic. 350.3.2 Preparing Subgrade
211. Excavate and backf ill areas of soft, yielding, or spongy subg rade or otherwise treat unstable areas as the engineer directs. 350.3.3 Constructing Subbase
subgrade material. Do not places ubbase material on a frozen su bgrade, subgrade covered by ice or snow, or on a wet or soft subgrade unless the engineer specific ally directs.
Follow the standard compacti on methods specified in 207.3.6.2 unless the contract requires the special compaction methods specified in 207.3.6.3 .
Maintain the finished subbase unt il it is covered, or until the engineer accepts the work if the contract does not require covering the subbase.
350.4Measurement
350.4.1 General
acceptably completed. 350.4.2 By Volume
original source position using one of the following methods: - Average end areas, with no correction for curvature. - Truncated prisms.
deposit. Notify the engineer before removing subbase material. The department will not measure material removed before the engineer measures the original volu me.
will determine the capacity of each vehicle used to the nearest 1/10 cubic yard. 350.4.3 By Weight
tickets submitted daily. Submit a ticket for each load showing the material, net weight, date, and project ID. For material with mor e than 7 percent moisture, the department will reduce the ticket weight by the weight of water exceeding 7 percent. The department will determine moisture content as a percent of dry weight.